Emerging Technology Allows Greater Flexibility for the Design and Operation of FLNG

Loading in 2 Seconds...

play fullscreen
1 / 23

Emerging Technology Allows Greater Flexibility for the Design and Operation of FLNG - PowerPoint PPT Presentation


  • 44 Views
  • Uploaded on

Emerging Technology Allows Greater Flexibility for the Design and Operation of FLNG. By Peter J H Carnell Matthew Humphrys. Worldwide Higher Heating Value (HHV) Specifications. Spot sales complicated by differences in LNG specification Lean LNG gives more marketing flexibility

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' Emerging Technology Allows Greater Flexibility for the Design and Operation of FLNG' - reece


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
emerging technology allows greater flexibility for the design and operation of flng
Emerging Technology Allows Greater Flexibility for the Design and Operation of FLNG
  • By
  • Peter J H Carnell
  • Matthew Humphrys
worldwide higher heating value hhv specifications
Worldwide Higher Heating Value (HHV) Specifications
  • Spot sales complicated by differences in LNG specification
  • Lean LNG gives more marketing flexibility
    • Easier for user to add LPG than N2
transportation study results for conventional floating lng flng
Transportation Study Results for Conventional Floating LNG (FLNG)
  • Based on Qmax LNG Vessels
    • Length 400m, breadth 80m, displacement 550,000Te
  • High Plant Utilisation Rate Required
  • Need Spare Storage Capacity to allow for loading delays
    • LNG Storage Capacity 350,000 m3
    • LPG Storage Capacity 80,000 m3
    • Condensate Storage Capacity 160,000 m3
floating lng hull layout

Liquefaction Plant

LPG Storage

LNG Storage

Condensate Storage

Flare tower

Accommodation

Seawater intake reservoir

Machinery Space

Floating LNG Hull Layout
  • Comparable to the Worlds Largest Ship
    • Knock Nevis; Length 458m - Breadth 69m
  • Larger than Very Large Crude Carriers
    • Length 333m - Breadth 58m
ship to ship lng transfer time log
Ship to Ship LNG Transfer Time Log
  • 2 – 3 day window for transfers
  • Difficult operation for two huge vessels
  • LPG & condensate needs additional transfer equipment & operations
issues with higher hydrocarbons c 2 on flng
Issues with Higher Hydrocarbons (C2+) on FLNG
  • LPG marketable, but adds complexity and reduces LNG storage (or increases vessel size)
  • LPG system increases fire risk by ~30%
  • C2 content of LPG limited to 2% (vapour pressure)
  • Excess C2 may exceed fuel gas demand
  • C2 –rich fuel gas may exceed NOx emission limit on gas turbine
  • ‘Slopping’ on FLNG can create variable Boil Off Gas, hence variable Fuel Gas composition & Wobbe Number
    • Impact on Fuel Gas burners
catalytic de richment
Catalytic De-Richment
  • Catalytic De-Richment (CDR) converts higher hydrocarbons (ethane up to naphtha) to methane
  • Well established technology developed for substitute natural gas (SNG)
  • Overall reactions:

4C2H6 + 9H2O  7CH4 + 7H2O + CO2

2C3H8 + 7H2O  5CH4 + 5H2O + CO2

4C4H10 + 19H2O  13CH4 + 13H2O + 3CO2

C5H12 + 6H2O  4CH4 + 4H2O +CO2

typical cdr operating conditions
Typical CDR Operating Conditions*

Temp 275 °C: Press 30 bara: Steam/Carbon 0.833

* Patented catalyst

catalytic de richment1
Catalytic De-Richment
  • Catalytic De-Richment (CDR) converts higher hydrocarbons to methane
    • Increased LNG production
    • Simplified FLNG design
  • Well established technology
  • Reduces flaring where ethane in excess of fuel gas demand
  • Generates constant Wobbe number fuel gas
  • Lean LNG gives more marketing flexibility
why must mercury be removed
Why Must Mercury be Removed?
  • Avoid corrosion of equipment using aluminium alloys, copper alloys and some other alloys
    • LME (liquid metal embrittlement)
    • Amalgam corrosion
  • Process cheaper mercury-distressed crudes
  • Avoid emissions to environment
  • Comply with HSE directives & protect employees
    • Feb ’09 UN Environment Programme – World-wide treaty to limit Hg exposure

LME

slide16

2004 Moomba Explosion

  • Losses:
  • Caused by LME of aluminium heat exchanger inlet, by Hg
  • Leading insurers put the insured loss at A$320million (USD245 million)
  • Energy crisis in NSW & South Australia
    • Supplies were limited to 30-40% capacity
    • Cutbacks by major industrial customer
    • Job layoffs
puraspec mercury removal technology
PURASPEC Mercury Removal Technology
  • Uses variable valency metal sulphide
  • Hg + MxSy → MxSy-1 + HgS
  • Metal sulphide can be generated in situ from mixed metal oxide (patented co-removal of H2S & Hg)
  • Grades for gas and liquid hydrocarbons (LPG, condensate etc)
  • Can be used on saturated gas
full cradle to grave service
Full Cradle to Grave Service
  • Optimisation of Mercury Removal Unit (MRU) design with customer
  • Data sheets and vessel drawings
    • Low PD radial flow designs possible
  • Provision of most suitable absorbent
  • Supervised loading and discharge
  • Recycling of spent absorbent
    • Absorbents are made from materials compatible with smelters
    • Only audited, approved smelters used
    • Certificate proves environmentally safe disposal
mercury distribution gas processing plant mercury survey results

Recommended location of MRU

Typical location of (carbon) MRU

Regeneration

Medium

Compression

Export

Export

Fuel Gas

4%

5%

25%

20%

Cooling/

Al Heat

Exchanger

19%

Molecular Sieve/

Glycol Unit

Separation

Amine

System

<10 nanogram / Nm3 inlet specification

NGL’s

90%

15%

65%

LP

Compression

Amine

Gas

Oil

90%

100%

2%

NGL’s

Multiphase

flow

Separation

Waste Water

Water

Glycol

2%

8%

Wells

Amine

Overboard

Oil Storage/

Export

Mercury Distribution – Gas Processing Plant Mercury Survey Results

4%

fit and forget technology
Fit and Forget Technology
  • Intervention only required for charging and discharging
  • High mercury capacity gives long bed life
  • Sharp absorption profile means bed can cope with high excursions in mercury in feed and in the flow rate of feed
fpso se asia
FPSO SE ASIA

MRU on FPSO

conclusions
Conclusions
  • Catalytic De-Richment can be used to increase LNG production
    • Free up space for LNG storage or reduce size of vessel
    • Simplifies FLNG design and improves safety
    • Potentially reduce the need for flaring
  • Mercury removal essential
    • Location upstream of acid gas & water removal maximises protection of equipment, people and environment