Update on FCPS Construction/Renovation Projects. September 2009. Cassidy Elementary – Renovation. Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010 GC Contract Sum:$9,061,000 Total Project Cost:$11,067,360

Download Presentation

Update on FCPS Construction/Renovation Projects

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Update on fcps construction renovation projects

Update on FCPS Construction/Renovation Projects

September 2009


Cassidy elementary renovation

Cassidy Elementary – Renovation

  • Architect: Tate.Hill.Jacobs: Architects

  • General Contractor: D.W. Wilburn, Inc.

  • Substantial Completion Date:August, 2010

  • GC Contract Sum:$9,061,000

  • Total Project Cost:$11,067,360

  • Change Orders to Date (1):$3,152

  • Current Phase:1 (On Schedule)

  • Estimated Completion:34%


Cassidy elementary renovation1

Cassidy Elementary – Renovation

Rendering of Final Façade


Cassidy elementary renovation2

Cassidy Elementary – Renovation

  • Work Completed in Last 30 Days:

  • Concrete seating walls complete at playground and mulch in place.

  • Storm sewers at rear of building complete.

  • Morton parking lot extension complete.

  • Second floor joist and slab structure complete at new additions.

  • Masonry load bearing walls complete on Admin Addition. Brick Veneer complete on rear addition.

  • Mechanical and electrical work rough-ins continue in new additions.


Cassidy elementary renovation3

Cassidy Elementary – Renovation

  • Current Work Effort (September):

  • Storm sewer and underground detention system to complete.

  • Stage floor to be poured and masonry load bearing walls installed.

  • Roof joists and deck to be installed. Roofing finish to start before end of month.

  • Interior metal framing to begin in enclosed areas.

  • Elevator installation to be complete by end of month.

  • Sprinkler rough-ins to begin.

  • Rooftop mechanical units to be installed.

  • Electric transformer to be installed.


Cassidy elementary renovation4

Cassidy Elementary – Renovation

New Admin. Addition

New Classroom Wing Corridor 2nd Fl

New Media Center from 2nd Fl.

New Stage Addition


Russell cave elementary renovation

Russell Cave Elementary – Renovation

  • Architect: Pearson & Peters Architects

  • General Contractor: Congleton-Hacker Construction

  • Substantial Completion Date:August, 2010

  • GC Contract Sum:$5,001,150

  • Total Project Cost:$6,103,400

  • Change Orders to Date (2):$11,180

  • Current Phase:1 (On Schedule)

  • Estimated Completion:42%


Russell cave elementary renovation1

Russell Cave Elementary – Renovation

Rendering of Final Façade


Russell cave elementary renovation2

Russell Cave Elementary – Renovation

  • Work Completed in Last 30 Days:

  • Roof at new addition is complete and the addition is dried in.

  • Renovation of (4) classrooms on the south side continues, demolition is complete, new mechanical and electrical rough-in is in process.

  • Stone veneer on addition base is in process.

  • New windows have been installed at (4) classroom renovation.

  • Current Work Effort (September):

  • Interior ramp and stair in new addition will be poured.

  • New horizontal blinds will be installed in cafeteria.

  • Framing for knee walls at new windows and soffits in renovated classrooms will be installed.

  • Block filler and painting will begin. New floor material will be delivered the first week of September

  • Demolition of the general construction items will begin in the gymnasium.


Russell cave elementary renovation3

Russell Cave Elementary – Renovation

New Classroom Windows

New Media Center

Interior of Cafeteria

New Kitchen


Arlington elementary renovation

Arlington Elementary – Renovation

  • Architect: RossTarrant Architects

  • General Contractor: WS Construction

  • Substantial Completion Date:August, 2010

  • GC Contract Sum:$9,920,194

  • Total Project Cost:$12,450,800

  • Change Orders: $36,900 (#1--Demo)

  • Current Phase:1 (On Schedule)

  • Estimated Completion:17%


Arlington elementary renovation1

Arlington Elementary – Renovation

Rendering of Final Façade


Arlington elementary renovation2

Arlington Elementary – Renovation

  • Work Completed in Last 30 Days:

  • Mock up of exterior wall materials has been completed.

  • Water detention system is in place.

  • Joists have been set in the gymnasium and the slab is scheduled to be poured on 9/16.

  • CMU walls continue in the kitchen.

  • Current Work Effort (September):

  • Demolition is almost complete.

  • The shoring of the existing structure is in place and reconstruction of the bearing wall between existing and new construction has begun.

  • Mechanical, electrical and plumbing work continues on site and in the existing building.

  • Foundations continue at the main entry and in the media center.


Arlington elementary renovation3

Arlington Elementary – Renovation

Water Detention System

New Walls for Kitchen

Bearing Wall Between Old & New Construction

Mechanical, Electrical Plumbing Work


Bryan station middle renovation

Bryan Station Middle – Renovation

  • Architect: Clotfelter-Samokar Architects

  • General Contractor: Preston Construction Group

  • Substantial Completion Date:August, 2010

  • GC Contract Sum:$10,769,400

  • Total Project Cost:$13,345,600

  • Change Orders to Date (1):$9,118

  • Current Phase:1A (On Schedule)

  • Estimated Completion:39%


Bryan station middle renovation1

Bryan Station Middle – Renovation

Rendering of Final Façade


Bryan station middle renovation2

Bryan Station Middle – Renovation

  • Work Completed in Last 30 Days:

  • Renovated Cafeteria now being used.

  • Media Center Renovation nearing “finishes” stage.

  • Science Room renovation work in progress.

  • New Music Suite Addition progressing well.

  • Current Work Effort (September):

  • Science and Computer room renovation to progress rapidly to meet November 1 scheduled substantial completion date. This also includes kitchen and Media Center.

  • New addition to progress to the point where roof joist can begin installation.

  • HVAC preparations to be made for switchover in phasing.

  • Site-work to develop so that bus lane can be reinstalled.


Bryan station middle renovation3

Bryan Station Middle – Renovation

Renovated Cafeteria

Media Center

Science Room Renovation

New Music Suite Addition


Leestown middle renovation

Leestown Middle – Renovation

  • Architect: Lucas/Schwering Architects

  • General Contractor: D.W. Wilburn, Inc.

  • Substantial Completion Date:August, 2010

  • GC Contract Sum:$11,182,000

  • Total Project Cost:$13,682,854

  • Change Orders to Date (1):$2,874

  • Current Phase:1, 1a, 1b (On Schedule)

  • Estimated Completion:24%


Leestown middle renovation1

Leestown Middle – Renovation

Rendering of Final Façade


Leestown middle renovation2

Leestown Middle – Renovation

  • Work Completed in Last 30 Days:

  • Phase 1 A, B & C demolition efforts on-going.

  • Phase 1B Asbestos abatement on-going.

  • Phase 1 A, B & C hollow metal door frames.

  • Phase 1 A & B interior masonry wall erection on-going.

  • Phase 1 A & B interior masonry in-fill & patch work started.

  • Phase 1 A, B & C Erection of Structural steel started.

  • Phase 1 A, B & C setting of bar joists started.

  • Court yard seating walls and concrete paving are on-going.

  • Foundations for the courtyard addition are on-going.

  • Metal stud walls in Administration Suite are complete.

  • Cafeteria soffits are on-going.

  • Above ceiling ductwork has started in the Cafeteria.


Leestown middle renovation3

Leestown Middle – Renovation

  • Current Work Effort (September):

  • General demolition in Phases 1A, B & C will continue.

  • Plumbing, HVAC, electrical demolition on-going.

  • Structural steel and bar joists will continue to be erected

  • Metal roof decking to start.

  • Electrical and Plumbing rough-ins on-going.

  • Masonry load bearing masonry at Kitchen to be completed.

  • Phase 1C (Courtyard addition) foundation to be completed.

  • Phase 1C slab to start.

  • Erection of two story Fire Wall to begin.

  • Installation of hollow metal door frames on-going in Phase 1B & C.

  • Phase 1A & B, Work at existing built-up roofs to start.

  • Installation of new built-up roof at Phase C.


Leestown middle renovation4

Leestown Middle – Renovation

New Addition at Kitchen

Steel Erection at Courtyard Addition

New Addition Kitchen Serving Line

Seating Wall at Courtyard


Lafayette high stadium replacement

Lafayette High Stadium – Replacement

  • Architect: Strand & Associates

  • General Contractor: Judy Construction Co.

  • Substantial Completion Date:Fall 2010

  • GC Contract Sum:$4,333,000

  • Total Project Cost:$4,899,578

  • Change Orders to Date:$0

  • Current Phase:Phase 1


Lafayette high stadium replacement1

Lafayette High Stadium – Replacement

Existing Campus


Lafayette high stadium replacement2

Lafayette High Stadium – Replacement

Existing Football Stadium


Lafayette high stadium replacement3

Lafayette High Stadium – Replacement

New Football Stadium


Central bus garage adaptive reuse

Central Bus Garage – Adaptive Reuse

  • Architect: Lucas/Schwering Architects

  • General Contractor: James R. Leake & Sons, Inc.

  • Substantial Completion Date:August, 2009

  • GC Contract Sum:$2,782,000

  • Total Project Cost:$5,672,810

  • Change Orders to Date (3):$31,275

  • Current Phase:Construction

  • Estimated Completion:72%


Central bus garage adaptive reuse1

Central Bus Garage – Adaptive Reuse

Façade


Central bus garage adaptive reuse2

Central Bus Garage – Adaptive Reuse

  • Work Completed in Last 30 Days:

  • All new shop equipment has been delivered with lifts, hose reels, exhaust system and work tables installed.

  • Paving for car parking has been completed. Striping is complete.

  • Installation of plant material and sod is proceeding.

  • Exterior overhead sectional doors have been installed

  • All masonry is complete

  • 90% of overhead electric complete

  • Painting is proceeding.

  • Installation of floor tile and carpet in the administration area is proceeding.

  • Ceramic wall tile is proceeding in the toilet areas.

  • Mechanical work is proceeding.

  • Installation of electrical devices is proceeding.


Central bus garage adaptive reuse3

Central Bus Garage – Adaptive Reuse

  • Current Work Effort (September):

  • Complete installation of all plant material.

  • Complete administration area and prepare punch list September 23rd.

  • Owner to start floor waxing floors and move in at the administration area September 25th.

  • Parking lot light poles to be installed.

  • Installation of interior doors and hardware proceeding

  • Continue work on the shop area.


Central bus garage adaptive reuse4

Central Bus Garage – Adaptive Reuse

Service Equipment and Lifts at Shop area

Administration Area

Ceramic Wall Tile at Toilet Rooms

Plant Material at Car Parking Lot