Update on FCPS Construction/Renovation Projects. September 2009. Cassidy Elementary – Renovation. Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date: August, 2010 GC Contract Sum: $9,061,000 Total Project Cost: $11,067,360

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' Update on FCPS Construction/Renovation Projects' - ray


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
Update on fcps construction renovation projects

Update on FCPS Construction/Renovation Projects

September 2009


Cassidy elementary renovation
Cassidy Elementary – Renovation

  • Architect: Tate.Hill.Jacobs: Architects

  • General Contractor: D.W. Wilburn, Inc.

  • Substantial Completion Date: August, 2010

  • GC Contract Sum: $9,061,000

  • Total Project Cost: $11,067,360

  • Change Orders to Date (1): $3,152

  • Current Phase: 1 (On Schedule)

  • Estimated Completion: 34%


Cassidy elementary renovation1
Cassidy Elementary – Renovation

Rendering of Final Façade


Cassidy elementary renovation2
Cassidy Elementary – Renovation

  • Work Completed in Last 30 Days:

  • Concrete seating walls complete at playground and mulch in place.

  • Storm sewers at rear of building complete.

  • Morton parking lot extension complete.

  • Second floor joist and slab structure complete at new additions.

  • Masonry load bearing walls complete on Admin Addition. Brick Veneer complete on rear addition.

  • Mechanical and electrical work rough-ins continue in new additions.


Cassidy elementary renovation3
Cassidy Elementary – Renovation

  • Current Work Effort (September):

  • Storm sewer and underground detention system to complete.

  • Stage floor to be poured and masonry load bearing walls installed.

  • Roof joists and deck to be installed. Roofing finish to start before end of month.

  • Interior metal framing to begin in enclosed areas.

  • Elevator installation to be complete by end of month.

  • Sprinkler rough-ins to begin.

  • Rooftop mechanical units to be installed.

  • Electric transformer to be installed.


Cassidy elementary renovation4
Cassidy Elementary – Renovation

New Admin. Addition

New Classroom Wing Corridor 2nd Fl

New Media Center from 2nd Fl.

New Stage Addition


Russell cave elementary renovation
Russell Cave Elementary – Renovation

  • Architect: Pearson & Peters Architects

  • General Contractor: Congleton-Hacker Construction

  • Substantial Completion Date: August, 2010

  • GC Contract Sum: $5,001,150

  • Total Project Cost: $6,103,400

  • Change Orders to Date (2): $11,180

  • Current Phase: 1 (On Schedule)

  • Estimated Completion: 42%


Russell cave elementary renovation1
Russell Cave Elementary – Renovation

Rendering of Final Façade


Russell cave elementary renovation2
Russell Cave Elementary – Renovation

  • Work Completed in Last 30 Days:

  • Roof at new addition is complete and the addition is dried in.

  • Renovation of (4) classrooms on the south side continues, demolition is complete, new mechanical and electrical rough-in is in process.

  • Stone veneer on addition base is in process.

  • New windows have been installed at (4) classroom renovation.

  • Current Work Effort (September):

  • Interior ramp and stair in new addition will be poured.

  • New horizontal blinds will be installed in cafeteria.

  • Framing for knee walls at new windows and soffits in renovated classrooms will be installed.

  • Block filler and painting will begin. New floor material will be delivered the first week of September

  • Demolition of the general construction items will begin in the gymnasium.


Russell cave elementary renovation3
Russell Cave Elementary – Renovation

New Classroom Windows

New Media Center

Interior of Cafeteria

New Kitchen


Arlington elementary renovation
Arlington Elementary – Renovation

  • Architect: RossTarrant Architects

  • General Contractor: WS Construction

  • Substantial Completion Date: August, 2010

  • GC Contract Sum: $9,920,194

  • Total Project Cost: $12,450,800

  • Change Orders: $36,900 (#1--Demo)

  • Current Phase: 1 (On Schedule)

  • Estimated Completion: 17%


Arlington elementary renovation1
Arlington Elementary – Renovation

Rendering of Final Façade


Arlington elementary renovation2
Arlington Elementary – Renovation

  • Work Completed in Last 30 Days:

  • Mock up of exterior wall materials has been completed.

  • Water detention system is in place.

  • Joists have been set in the gymnasium and the slab is scheduled to be poured on 9/16.

  • CMU walls continue in the kitchen.

  • Current Work Effort (September):

  • Demolition is almost complete.

  • The shoring of the existing structure is in place and reconstruction of the bearing wall between existing and new construction has begun.

  • Mechanical, electrical and plumbing work continues on site and in the existing building.

  • Foundations continue at the main entry and in the media center.


Arlington elementary renovation3
Arlington Elementary – Renovation

Water Detention System

New Walls for Kitchen

Bearing Wall Between Old & New Construction

Mechanical, Electrical Plumbing Work


Bryan station middle renovation
Bryan Station Middle – Renovation

  • Architect: Clotfelter-Samokar Architects

  • General Contractor: Preston Construction Group

  • Substantial Completion Date: August, 2010

  • GC Contract Sum: $10,769,400

  • Total Project Cost: $13,345,600

  • Change Orders to Date (1): $9,118

  • Current Phase: 1A (On Schedule)

  • Estimated Completion: 39%


Bryan station middle renovation1
Bryan Station Middle – Renovation

Rendering of Final Façade


Bryan station middle renovation2
Bryan Station Middle – Renovation

  • Work Completed in Last 30 Days:

  • Renovated Cafeteria now being used.

  • Media Center Renovation nearing “finishes” stage.

  • Science Room renovation work in progress.

  • New Music Suite Addition progressing well.

  • Current Work Effort (September):

  • Science and Computer room renovation to progress rapidly to meet November 1 scheduled substantial completion date. This also includes kitchen and Media Center.

  • New addition to progress to the point where roof joist can begin installation.

  • HVAC preparations to be made for switchover in phasing.

  • Site-work to develop so that bus lane can be reinstalled.


Bryan station middle renovation3
Bryan Station Middle – Renovation

Renovated Cafeteria

Media Center

Science Room Renovation

New Music Suite Addition


Leestown middle renovation
Leestown Middle – Renovation

  • Architect: Lucas/Schwering Architects

  • General Contractor: D.W. Wilburn, Inc.

  • Substantial Completion Date: August, 2010

  • GC Contract Sum: $11,182,000

  • Total Project Cost: $13,682,854

  • Change Orders to Date (1): $2,874

  • Current Phase: 1, 1a, 1b (On Schedule)

  • Estimated Completion: 24%


Leestown middle renovation1
Leestown Middle – Renovation

Rendering of Final Façade


Leestown middle renovation2
Leestown Middle – Renovation

  • Work Completed in Last 30 Days:

  • Phase 1 A, B & C demolition efforts on-going.

  • Phase 1B Asbestos abatement on-going.

  • Phase 1 A, B & C hollow metal door frames.

  • Phase 1 A & B interior masonry wall erection on-going.

  • Phase 1 A & B interior masonry in-fill & patch work started.

  • Phase 1 A, B & C Erection of Structural steel started.

  • Phase 1 A, B & C setting of bar joists started.

  • Court yard seating walls and concrete paving are on-going.

  • Foundations for the courtyard addition are on-going.

  • Metal stud walls in Administration Suite are complete.

  • Cafeteria soffits are on-going.

  • Above ceiling ductwork has started in the Cafeteria.


Leestown middle renovation3
Leestown Middle – Renovation

  • Current Work Effort (September):

  • General demolition in Phases 1A, B & C will continue.

  • Plumbing, HVAC, electrical demolition on-going.

  • Structural steel and bar joists will continue to be erected

  • Metal roof decking to start.

  • Electrical and Plumbing rough-ins on-going.

  • Masonry load bearing masonry at Kitchen to be completed.

  • Phase 1C (Courtyard addition) foundation to be completed.

  • Phase 1C slab to start.

  • Erection of two story Fire Wall to begin.

  • Installation of hollow metal door frames on-going in Phase 1B & C.

  • Phase 1A & B, Work at existing built-up roofs to start.

  • Installation of new built-up roof at Phase C.


Leestown middle renovation4
Leestown Middle – Renovation

New Addition at Kitchen

Steel Erection at Courtyard Addition

New Addition Kitchen Serving Line

Seating Wall at Courtyard


Lafayette high stadium replacement
Lafayette High Stadium – Replacement

  • Architect: Strand & Associates

  • General Contractor: Judy Construction Co.

  • Substantial Completion Date: Fall 2010

  • GC Contract Sum: $4,333,000

  • Total Project Cost: $4,899,578

  • Change Orders to Date: $0

  • Current Phase: Phase 1



Lafayette high stadium replacement2
Lafayette High Stadium – Replacement

Existing Football Stadium



Central bus garage adaptive reuse
Central Bus Garage – Adaptive Reuse

  • Architect: Lucas/Schwering Architects

  • General Contractor: James R. Leake & Sons, Inc.

  • Substantial Completion Date: August, 2009

  • GC Contract Sum: $2,782,000

  • Total Project Cost: $5,672,810

  • Change Orders to Date (3): $31,275

  • Current Phase: Construction

  • Estimated Completion: 72%



Central bus garage adaptive reuse2
Central Bus Garage – Adaptive Reuse

  • Work Completed in Last 30 Days:

  • All new shop equipment has been delivered with lifts, hose reels, exhaust system and work tables installed.

  • Paving for car parking has been completed. Striping is complete.

  • Installation of plant material and sod is proceeding.

  • Exterior overhead sectional doors have been installed

  • All masonry is complete

  • 90% of overhead electric complete

  • Painting is proceeding.

  • Installation of floor tile and carpet in the administration area is proceeding.

  • Ceramic wall tile is proceeding in the toilet areas.

  • Mechanical work is proceeding.

  • Installation of electrical devices is proceeding.


Central bus garage adaptive reuse3
Central Bus Garage – Adaptive Reuse

  • Current Work Effort (September):

  • Complete installation of all plant material.

  • Complete administration area and prepare punch list September 23rd.

  • Owner to start floor waxing floors and move in at the administration area September 25th.

  • Parking lot light poles to be installed.

  • Installation of interior doors and hardware proceeding

  • Continue work on the shop area.


Central bus garage adaptive reuse4
Central Bus Garage – Adaptive Reuse

Service Equipment and Lifts at Shop area

Administration Area

Ceramic Wall Tile at Toilet Rooms

Plant Material at Car Parking Lot