slide1
Download
Skip this Video
Download Presentation
Extension of Time (EOT) and Related Costs in Construction

Loading in 2 Seconds...

play fullscreen
1 / 39

Extension of Time (EOT) and Related Costs in Construction - PowerPoint PPT Presentation


  • 58 Views
  • Uploaded on

Extension of Time (EOT) and Related Costs in Construction. By Khalil T. Hasan Construction Solutions ( www.cspk.org ). Presented at the FIDIC Middle East Contract Users’ Conference February 2013 – Dubai, UAE. www.cspk.org. Time is of Essence

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' Extension of Time (EOT) and Related Costs in Construction' - rama-lawson


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
slide1

Extension of Time (EOT) and Related Costs in Construction

By

Khalil T. Hasan

Construction Solutions (www.cspk.org)

Presented at the

FIDIC Middle East Contract Users’ Conference

February 2013 – Dubai, UAE

www.cspk.org

slide2

Time is of Essence

  • Delays are inevitable on construction projects
  • The only project to have completed on time is a Mosque. Divine intervention (or God’s help) was understood to be the force behind the timely completion of this Mosque.
  • Time and Money go hand-in-hand. When projects get late, additional costs are incurred.
  • This makes it imperative to take control of project delays; timely and effectively.

www.cspk.org

slide3

Majority of construction projects worldwide are administered by the FIDIC forms of contract.

  • FIDIC recognises delay and related costs and has provisions related thereto. For example;
    • Sub-Clauses 8.4 & 20.1 (FIDIC 1999 Edition)
    • Clauses 44 & 53 (FIDIC 1987 Edition)

www.cspk.org

slide4

The FIDIC Provisions define the conditions where delay may be claimed as the basis for an Extension of Time (EOT). Some examples are;

    • Late provision of design or drawings
    • Unforeseeable Physical Conditions encountered on Site
    • Inclement Weather
    • Variations instructed by the Engineer (Additional Works etc.)

www.cspk.org

slide5

Meanwhile the principles of how delay and related costs should be calculated are not defined by FIDIC. This leads to issues; issues which are usually contentious due to various \'schools of thoughts\' and varied interpretations existing worldwide.

  • Disputes are the usual outcome.

www.cspk.org

contentious issues in delay analysis resulting in disputes
Contentious Issues in Delay Analysisresulting in Disputes
  • Critical Path
  • Who owns the Float?
  • Concurrent (or Contractor) Delays and how these effect Entitlement
  • EOT and its relation with Compensation for Delay
  • Which is the best Method of Delay Analysis?
    • As-Planned Vs. As-Built Comparison
    • Impacted As-Planned
    • Collapsed As-Built / But-For
    • Time Slice / Sub-Networks / Time-Impact
    • Etc.

www.cspk.org

slide7

In orderto eliminate disputes or facilitate settlement of disputes, there are now certain standards used worldwide. The leading standards are;

    • Society of Construction Law’s
    • Delay and Disruption Protocol (SCL Protocol)
    • AACE 29R-03 (Forensic Schedule Analysis)

www.cspk.org

slide8

The SCL Protocol was

finalized in October 2002 after several years of deliberations and considerable debate and agreement between experts from different backgrounds

www.cspk.org

slide9

The objective of the SCL Protocol was to bring reasonableness and fairness into the delay assessment process and to eliminate widespread manipulation of complex delay issues

www.cspk.org

slide10
The SCL Protocol tried to standardize

the issues such that disputes would be

reduced or eliminated

www.cspk.org

slide11

It is recommended that;

should be adopted as a Standard and should be, where possible, incorporated in the Construction Contracts

www.cspk.org

slide12

The SCL Protocol can be downloaded from:

www.eotprotocol.com

www.cspk.org

slide13

The remaining slides of this lecture will review and discuss the basic Principles suggested and recommended by the

SCL Protocol

www.cspk.org

slide14

Basic Principles

suggested and recommended by

the SCL Protocol

www.cspk.org

slide15

The Principles suggested by the

SCL Protocol are simple.

Some of the key principles suggested by the Protocol are;

www.cspk.org

slide16

RULE NO. 1

If there is an Employer’s delay, which is beyond the Contractor’s control, and if this delay impacts the Completion Date of the Works,

the Contractor should be entitled to receive an Extension of Time (EOT).

[This will effectively result in an extended Time for Completion and will relieve the Contractor from having to pay penalties for delay (or Delay Damages under FIDIC)]

www.cspk.org

slide17

RULE NO. 2

For the case of recovery of delay (or prolongation) costs incurred due to the Employer delays, the Contractor must be able to prove that there has been no other delay, which is in his own control, and which is equally (or partly) contributing for delaying the Time for Completion.

This category of delay is called a ‘Concurrent’

(or Contractor’s) Delay

[In order to win a Delay Costs Claim, the Contractor must be able to prove that he has not been responsible for Concurrent Delays to the Time for Completion]

www.cspk.org

slide18

RULE NO. 3

Where Contractor’s Delay to Completion occurs concurrently with Employer’s Delay to Completion, the Contractor’s concurrent delay should NOT reduce any

Extension of Time (EOT), which is due.

[Result of Rule No. 1 will not change and is irrespective of the result of Rule No. 2]

www.cspk.org

slide19

The foregoing Rules proposed by the SCL Protocol are meant to bring fairness and reasonableness into the delay assessment process.

[The emphasis of the SCL Protocol is that no one Party should benefit from default of the other Party]

www.cspk.org

slide20

The Illustrations demonstrating the principles of the SCL Protocol are contained in the following Figures A to G

www.cspk.org

slide23

Principles & Provisions of the SCL Protocol

relevant to Figure B

Core Principle No. 7 - Float as it relates to time

Unless there is express provision to the contrary in the contract, where there is remaining float in the programme at the time of an Employer Risk Event, an EOT should only be granted to the extent that the Employer Delay is predicted to reduce to below zero the total float on the activity paths affected by the Employer Delay.

Guidance Section 1.12.1

If as a result of an Employer Delay, the Contractor is prevented from completing the works by the Contractor’s planned completion date (being a date earlier than the contract completion date), the Contractor should in principle be entitled to be paid the costs directly caused by the Employer Delay, notwithstanding that there is no delay to the contract completion date (and therefore no entitlement to an EOT), provided also that at the time they enter into the contract, the Employer is aware of the Contractor’s intention to complete the works prior to the contract completion date, and that intention is realistic and achievable.

www.cspk.org

slide25

Principles & Provisions of the SCL Protocol

relevant to Figure C

Core Principle No. 4 - Procedure for granting extension of time

The EOT should be granted to the extent that the Employer Risk Event is reasonably predicted to prevent the works being completed by the then prevailing contract completion date…..The goal of the EOT procedure is the ascertainment of the appropriate contractual entitlement to an EOT; the procedure is not to be based on whether or not the Contractor needs an EOT in order not to be liable for liquidated damages.

Core Principle No. 5 – Effect of delay

For an EOT to be granted, it is not necessary for the Employer Risk Event already to have begun to affect the Contractor’s progress with the works, or for the effect of the Employer Risk Event to have ended.

www.cspk.org

slide27

Principles & Provisions of the SCL Protocol

relevant to Figure D

Core Principle No. 4 - Procedure for granting extension of time

The EOT should be granted to the extent that the Employer Risk Event is reasonably predicted to prevent the works being completed by the then prevailing contract completion date…..The goal of the EOT procedure is the ascertainment of the appropriate contractual entitlement to an EOT; the procedure is not to be based on whether or not the Contractor needs an EOT in order not to be liable for liquidated damages.

Core Principle No. 5 – Effect of delay

For an EOT to be granted, it is not necessary for the Employer Risk Event already to have begun to affect the Contractor’s progress with the works, or for the effect of the Employer Risk Event to have ended.

www.cspk.org

slide29

Principles & Provisions of the SCL Protocol

relevant to Figure E

Guidance Section 1.2.11

…an EOT should be granted to the extent that the Employer Risk Event is predicted to prevent the works being completed by the then prevailing contract completion date. This process requires consideration of the available float…

Guidance Section 1.4.12

…Where there has been Employer Delay, this may prevent the Employer charging the Contractor with LDs for failure to achieve a contract completion date…

www.cspk.org

slide31

Principles & Provisions of the SCL Protocol

relevant to Figure F

Guidance Section 1.4.8

Where an Employer Risk Event occurs after the contract completion date, in a situation where failure to complete by the contract completion date has been caused by Contractor Delays, the principle set out in Section 1.4.7 above should apply, except where the Employer Risk Event is a non-compensable Employer Risk Event. In such an event, no EOT (or compensation) should be due. Where an EOT is due after the contract completion date, the Employer Risk Event does not exonerate the Contractor for all its delays prior to the Employer Risk Event occurring. The effect of the Employer Risk Event should be assessed as described above and any EOT found due should simply be added to the contract completion date.

www.cspk.org

slide33

Principles & Provisions of the SCL Protocol

relevant to Figure G – Slide 1/2

Guidance Section 1.4.1

Where Contractor Delay to Completion occurs concurrently with Employer Delay to Completion, the Contractor’s concurrent delay should not reduce any EOT due.

Guidance Section 1.4.7

Where Employer Risk Events and Contractor Risk Events occur sequentially but have concurrent effects, here again any Contractor Delay should not reduce the amount of EOT due to the Contractor as a result of the Employer Delay.

Concurrency (Appendix A – Definations and Glossary)

True concurrent delay is the occurrence of two or more delay events at the same time, one an Employer Risk Event, the other a Contractor Risk Event and the effects of which are felt at the same time. The term ‘concurrent delay’ is often used to describe the situation where two or more delay events arise at different times, but the effects of them are felt (in whole or in part) at the same time. To avoid confusion, this is more correctly termed the ‘concurrent effect’ of sequential delay events.

www.cspk.org

slide34

Principles & Provisions of the SCL Protocol

relevant to Figure G – Slide 2/2

Core Principle No. 9 - Concurrent delay – its effect on entitlement to extension of time

Where Contractor Delay to Completion occurs or has effect concurrently with Employer Delay to Completion, the Contractor’s concurrent delay should not reduce any EOT due.

Core Principle No. 14 - Link between extension of time and compensation

Entitlement to an EOT does not automatically lead to entitlement to compensation (and vice versa).

Core Principle No. 10 - Concurrent delay – its effect on entitlement to compensation for prolongation

If the Contractor incurs additional costs that are caused both by Employer Delay and concurrent Contractor Delay, then the Contractor should only recover compensation to the extent it is able to separately identify the additional costs caused by the Employer Delay from those caused by the Contractor Delay. If it would have incurred the additional costs in any event as a result of Contractor Delays, the Contractor will not be entitled to recover those additional costs.

www.cspk.org

slide35

Key Guideline, Suggestion and Advice of the SCL Protocol

Guidance Section 3.2.13

Although the programme should be the primary tool for guiding the CA in his determination of EOT, it should be used in conjunction with the contemporary evidence to ensure that the resulting EOT is fair and reasonable. It will also be necessary for the parties to apply common sense and experience to the process to ensure that all relevant factors are taken into account, and that any anomalous results generated by the programme analysis are managed properly.

www.cspk.org

slide37

Congratulations we have come to the end of the Lecture.

You are now a Qualified and Certified Delay Claims Analyst and Expert.

www.cspk.org

slide38

FIDIC and Construction Solutions

thank you for your attendance and contribution.

We wish you all Good Luck.

www.cspk.org

slide39

We urge all participants to review the SCL Protocol on their own. Construction Solutions’ Claims Management Division (www.cspk.org)will remain available for further discussions on the foregoing and any other relevant issue.

  • This Lecture was delivered by the Managing Partner of Construction Solutions, Mr. Khalil Tayab Hasan. For any queries and clarifications, please feel free to contact Mr. Hasan at;

www.cspk.org

ad