IDM Chapter 104
This presentation is the property of its rightful owner.
Sponsored Links
1 / 37

IDM Chapter 104 Utility Coordination Joe Gundersen Senior Utility Engineer, INDOT PowerPoint PPT Presentation


  • 136 Views
  • Uploaded on
  • Presentation posted in: General

IDM Chapter 104 Utility Coordination Joe Gundersen Senior Utility Engineer, INDOT November 19, 2013. Agenda. Learning Objectives Introduction Table of Contents Waiver/Certificate Special Provision 107-R-169 Approve Consultants or Contractor Work In State Contract Records Checklist

Download Presentation

IDM Chapter 104 Utility Coordination Joe Gundersen Senior Utility Engineer, INDOT

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Idm chapter 104 utility coordination joe gundersen senior utility engineer indot

IDM Chapter 104

Utility Coordination

Joe Gundersen

Senior Utility Engineer, INDOT

November 19, 2013


Agenda

Agenda

  • Learning Objectives

  • Introduction

  • Table of Contents

  • Waiver/Certificate

  • Special Provision 107-R-169

  • Approve Consultants or Contractor

  • Work In State Contract

  • Records

  • Checklist

  • Roles and Responsibilities


Learning objective

Learning Objective

  • Explain why IDM Chapter 104 was developed

  • Identify the components of IDM Chapter 104

  • Know and apply Waiver or Certificate

  • Write special provision 107-R-169

  • Know how to approve Consultants & Contractors

  • Know when to do relocation Work In Contract

  • Know what records to maintain

  • Know and apply the IDM Ch 104 Checklist

  • Know and apply applicable roles


Introduction

Introduction

  • Design Manual

    • IDM Ch. 104 replaces IDM Ch. 10

    • IDM Ch. 104 – revised August 2013

    • IDM Ch. 104 is 100% relevant

    • But it is only 70% of where we want to be.

  • Suggestions for improvement email:

    • [email protected]


Table of contents 1

Table of Contents (1)

  • General Information

    • Introduction

    • Responsibilities and Roles

    • Utility Rule 105 IAC 13

    • Utility Waiver

    • Utility Coordination Certificate

    • Utility Coordination Special Provision

    • Utility Coordination References

    • Definitions and Acronyms

  • Utility Coordination Process

    • Subsurface Utility Engineering


Table of contents 2

Table of Contents (2)

  • Design Considerations

  • Reimbursement

  • Highway Utility Agreement

  • Reimbursement

  • Cost Estimate

  • Consultant and Contractor Approval

  • Utility Work in State Contact

  • Utility Coordination Records


105 iac 13

105 IAC 13

  • Minor or major project

    • Minor is less than 12 months design

    • Major is more than 12 month design

    • Project Manager makes the decision

    • Input from the Utility Coordinator

    • Affects duration of Utility Coordination


105 iac 131

105 IAC 13

  • Geographical limits

    • Limits of expected utility involvement

    • In the area means in the geographical limits

    • Defined by the Project Manager

    • Minimum is survey limits


Waiver

Waiver

  • Use a waiver for routine maintenance projects such as:

    • Mowing

    • Herbicide treatment

    • Sweeping

    • Pavement markings

    • Etc.

  • Waiver includes only an affidavit

  • Format is at INDOT website


Wavier example

Wavier Example


Certificate

Certificate

  • Use a certificate for all projects with potential utility involvement

  • Certificate includes:

    • Affidavit

    • Utility information

  • Format is at INDOT website


Certificate1

Certificate

  • Utility descriptions include:

    • Name of utility

    • Utility is in the area of the project

    • Utility is/is not in conflict with project

    • Relocation work plan approved date

    • Utility is eligible for reimbursement

    • Type of agreement and status

    • Specifically address:

      • Yes work in contract

      • Not work in contract


Idm ch 104 certificate example

IDM Ch. 104 – Certificate Example


Certificate example

Certificate Example


Certificate example1

Certificate Example

  • Example

  • The facilities of TDS Telecom (parent company of Communications Corporation) utility are in the area of this project and are in conflict with the project. The relocation work plan for this utility was approved 7/26/2013. This utility is eligible for reimbursement and the agreement is not yet issued.


Idm ch 104 sp 107 r 169

IDM Ch. 104 – SP 107 R 169

  • Remember –

    • These are instructions to the Contractor

  • For each utility in the area state:

    • Utility name

    • Utility is in the area of the project

    • Utility is or is not in conflict with the project

    • Designated Representative: name, telephone, email

    • Activities before utility begins construction

    • Expected duration of relocation work

    • General location of their existing facilities

    • General scope of their relocation work


Special provision 107 r 169

Special Provision 107 R 169


References

References

  • Code of Federal Regulations

    • 23 CFR 645

  • Indiana Code

    • Majority of references

  • Indiana Administrative Code

    • 105 IAC 13

  • INDOT Standard Specifications

  • FHWA Program Guide 23 CFR 645

  • ASCE 38-02 Standards for SUE


Definitions

Definitions

  • Section includes

    • Definitions

    • Acronyms

    • Abbreviations

  • Intent was to be consistent with:

    • Standard Specifications

    • Design Manual

  • Review at your own pace and time


Contractor approval

Contractor Approval

  • Primary responsibilities:

    • Proper solicitation procedures were followed

    • Costs are reasonable

  • Utility submits letter requesting approval

  • Utility submits supporting documents

    • Continuing contract with rate sheet

    • Bid tabulations and lowest qualified bidder selected

  • UC reviews documents – recommendation

  • OSA approves and signs letter

  • Complications?


Work in contract

Work In Contract

  • INDOT prefers to use work in contract

    • When eligible for reimbursement

    • When work requires extensive coordination

  • Requires Des. No. for each facility type

  • Utility must provide:

    • Approved work plan

    • Final stamped plans

    • Specifications

    • Engineer’s estimate

    • List of quantities

    • Signed agreement


Records

Records

  • Keep copies of the following:

    • Maintain a utility coordination log

      • Activities

      • Conversations

    • All signed documents

    • All notices to proceed

    • See specific requirements


Roles

Roles

  • Roles and Responsibilities

  • Key to understanding IDM Ch. 104

    • There a 6 specific roles described:

      • Designer – 16 responsibilities

      • Surveyor – 5 responsibilities

      • Utility Coordinator – 81 responsibilities

      • Utility Oversight Agent – 20 responsibilities

      • Authorized Representative – 6 responsibilities

      • Project Manager – 9 responsibilities


Responsibilities

Responsibilities

  • Responsibilities are listed in:

    • IDM Chapter 104

    • Checklist for utility coordination

    • They are not the same

    • Checklist has tasks and sub-tasks

  • Checklist – please get your copy

  • Checklist – let us review


Checklist

Checklist

  • Why a checklist?

    • Currently 12 milestones in SPMS

    • Milestone start and finish not defined

    • Indentified sub-tasks to define each milestone

  • Results

    • Checklist for utility coordination

    • Milestones defined by specific sub-activities

    • Milestones reduced from 12 to 4


Milestones

Milestones


Initiation phase

Initiation Phase


Initiation phase1

Initiation Phase


Initiation phase2

Initiation Phase


Initiation phase3

Initiation Phase


Initiation phase4

Initiation Phase


Initiation phase5

Initiation Phase


Letter permit addendum

Letter Permit Addendum


Letter work complete

Letter Work Complete


Letter request invoice

Letter Request Invoice


Summary

Summary

  • Learning Objectives

  • Introduction

  • Table of Contents

  • Waiver/Certificate

  • Special Provision 107-R-169

  • Approve Consultants or Contractor

  • Work In State Contract

  • Records

  • Checklist

  • Roles and Responsibilities


Questions

Questions?


  • Login