TDAQ commissioning

TDAQ commissioning. R. Fantechi. TDAQ commissioning. Coordination activity started on January Several items to be attacked already in January Regular meetings: 15/1, 29/1, 6/2 First topics attacked: PC Farm Run Control L0TP tests. PC farm. Basic constraints Data throughput in input

quanda
Download Presentation

TDAQ commissioning

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TDAQ commissioning R. Fantechi

  2. TDAQ commissioning • Coordination activity started on January • Several items to be attacked already in January • Regular meetings: 15/1, 29/1, 6/2 • First topics attacked: • PC Farm • Run Control • L0TP tests

  3. PC farm • Basic constraints • Data throughput in input • Good estimate: 25-30 full 10 Gblinks (52-56 from detectors) • Number of 10 Gb ports on the router available for PCs • O(30) • CPU needed for L1/L2 processing • Unknown • Estimation of an extreme case: run the full reconstruction with (guessed) 1 sec/event, the power of 30 2*12 core PC will process 40 KHz of data

  4. HP8212 with 88x 10Gb and 24x 1Gb HPxx 48x 1Gb + 4x 10Gb 52(56)x 10Gb ports to detector area 30x 10Gb ports to online farm 34x 1Gb ports to merger 30 farmcomputers HP2920 24x 1Gb or 48x 1Gb ... DCS IPMI 3 mergercomputers? CernTN 1Gb link 10Gb link CernCDR + GPN

  5. PC farm discussion • Focus on O(30) PCs • 2 CPUs, 8 or 12 cores, 64 GB of memory • Good PS and at least a PCI 16X GEN 3 for a GPU • GPU to be installed in a second time to boost L1/L2 capacity • Keeping the network infrastructure as simple as of today • Several investigations ongoing • Alberto and Paolo looking for offers in Italy • RF looking for existing CERN-wide contracts in IT or LHC experiments, to profit from good discounts • Jonas searching the market in Germany and evaluating the cost of his proposal of assembling PCs on shelves inside the racks • Some points still to be defined for the pf-ring driver

  6. PC farm discussion • 2 more mergers are needed • Connect the 1 Gb/s outputs of the 30 PCs to a 48 port 2920 with 4 10 Gb interfaces • 3 10 Gb interfaces to go to the 3 mergers • The fourth one back to the router do go to the CDR • Additional network switch needed for IPMI control

  7. PC farm discussion • Start to think for a strategy if more power is needed • GPUs is one way, but no work has started yet • However, there is a limit to the number/power of GPUs to be put in a PC • Power supply capability, PCI slots • Cost tradeoff for high performance GPUs • On the other side, increase the number of PCs • Change the network configuration • Either build a tree of routers (topology and configuration to be checked) or go to a more expensive Brocade router to replace the actual HP8xxx one • Limited solution (Jonas): equip each one of the 30 PCs with 2 10 Gb Interfaces and connect other 30 PCs in cascade • On top of this, consider that according to the performance of the trigger we may have an input rate of less than 30 10 Gb links. This will create free slots in the router for more PCs. Again not a scalable solution

  8. L0TP • No request for the time being for a test at CERN • Ferrara claims it is able to exercise the L0tp proto with a clever PC program • Possibility of a test here middle of March • ECN 3 facilities always ready (continuous dry run) • Clock, Talk board • Service PCs • Everything restarted at the beginning of 2014 • Regularly used for the CREAM tests • To be eventually integrated with more TEL62s

  9. Network • Almost all the switches available in IT • A first batch of installations in ECN3 are foreseen soon • LAV4-11, CHANTI, router line cards • Followed by the LKr switches • Complete with Straws and the rest • All fiber patches for clock and network ordered • Insulation of the network • A cluster of two virtual machines running Windows Terminal server have been defined and available to us • Work to be started to configure the accesses • Another VM with Linux available to start the same exercise for Linux applications

  10. Run control • Meeting on the upgrade of the run control before Christmas • Nicolas has prepared a draft note • To be finalized this week • Implementation starting in March • Main points • Maintain configuration files in a central database • To be transferred to the detector clients at init/startrun • Utility to handle the interaction with the database • Clients to be upgraded/written • Tdspy (main effort), LKrinit, LKrcalib, GTK and Straw init, L0tp

  11. TTCex & LTUs • All the requested TTCex available since Feb 2013 • MK I type • No new production in the near future • Few spare modules available in PH-ESE, but more could come at the end of the year, due to some dismantling in CMS • Occasion to procure a reasonable number of spares • Preparation of the final LTU crate(s) • See Marian talk

  12. Crates • Long saga following the initial failures in 2012 • Problem not understood on sysreset line • Filtering ok for LAV • Several checks done on the existing crates • A test board prepared to check voltages and sysreset functionality • Indeed, one PS found with a problem on 48 V (not going immediately to zero after power off) • Other two with sysreset problem • All three were damaged in 2012 (badly repaired?) • These three sent back to Wiener as the first ones to have the filtering upgraded

  13. Crates • It is anyway time now to make the order • Sent from the pool coordinator at the end of March • 6 crates on hold, 5 prepared in December • Organize a set of hot spares • Two full LAV-type crates in Valeri’s lab • It should be safe to have in addition one PS LAV type + 1 PS TEL type as additional spares • Available at the experiment for a first line intervention

  14. Crate summary • Prototype crates • 1 LAV type (Frascati) + 1 TEL type (Roma2, now at CERN) • 2011 order • 8 LAV type: LAV1, LAV2, LAV3, CEDAR,MUV, CHOD, Straw, spare • 2012 order (on hold, to be unblocked) • 6 LAV type: LAV4, LAV5, LAV6, LAV7, LAV8, LAV9 • However one filtered LAV PS has been delivered • 2013 order (prepared, wait for our ok) • 4LAV type: LAV10, LAV11, 2*CHANTI • 4 TEL type: 3*L0/LKR, 1 RICH CHOD was originally RICH, it will be LAV12

  15. Items for the next meetings • Decision on the PC farm purchases • Tuning of the PC farm software • Rates, merger output rate, diagnostics, documentation • Review of the requirements of the various detectors • GTK, Straw, TEL62s, Gandalf, LKr • As far as network, PC farm, etc • Scheduling of common and private dry runs • Synergy with computing WG for CDR and storage • Together with IT in the newly formed coordination meetings