1 / 8

Beam Pipe Meeting Introduction

Beam Pipe Meeting Introduction. D. Schulte. Goal of the Meeting. The beam pipe area is critical for the FHC design Magnet aperture is a main cost driver Beam aperture is a main beam performance factor Thickness of shielding gap is critical to link the two

pink
Download Presentation

Beam Pipe Meeting Introduction

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Beam Pipe Meeting Introduction D. Schulte D. Schulte: Beam pipe kickoff meeting

  2. Goal of the Meeting • The beam pipe area is critical for the FHC design • Magnet aperture is a main cost driver • Beam aperture is a main beam performance factor • Thickness of shielding gap is critical to link the two • Beam screen cooling is one of the main power consumption sources • Beam pipe area design interacts with many expertises • Magnet design • Cooling and power efficiency • Wakefields, impact beam stability, optics and feedback • Electron cloud, impacts the time structure and background in the experiments • Vacuum design • Need an integrated task force/working group • Define baseline beam aperture, magnet aperture and shielding gap • Develop strategies for alternative solutions • Later also touch field quality at injection • This meeting should kick-start the technical discussion of this task force D. Schulte: Beam pipe kickoff meeting

  3. Synchrotron Radiation Load • Main difference between LHC and FHC • Synchrotron radiation is 25 to 44 W/m per beam averaged over the arc for (15T and 20T) • Important to avoid heating of magnets • Total radiation is 4.4 to 5.8 MW for both beams • Total cooling efficiency is critical • Cooling needs to be done at relatively high temperature due to Carnot inefficiency -> Philippe • Four approaches • Conventional beam screen -> Philippe, Nicolas • Conventional beam screen with high temperature superconductor • Photon stops -> Nicolas • Open midplane magnet • Are there more? D. Schulte: Beam pipe kickoff meeting

  4. Beam Screen Simplified sketch • Current draft baseline • beam aperture: 2x13mm • magnet aperture; 2x20mm • Space for shielding etc: 7mm • Needs to be reviewed • Impedance effects • Strong dependence on radius • Field dependent • increase above approx. 20K • Potential cures • Increase of aperture • Superconducting coating • Amorphous carbon coating against ecloud (Gijs De Rijk, Roberto Kersevan) D. Schulte: Beam pipe kickoff meeting

  5. Open Midplane • Less impact of warm surface impedance on beam • Could also help against electron cloud • Maybe easier to shield magnet • Could reduce space between beam screen and magnet • But very difficult magnet design • Likely reduced field • Similar studies for muon collider D. Schulte: Beam pipe kickoff meeting

  6. Photon Stops • Photon stops could take most of the heat load and be cooled at a higher temperature • Photons travel for approx 12-21m at injectionand around 14.5m at full energy (20T design) • For 13mm beam pipe radius 10mm radius for photon stops requires 1.8m spacing • Would need very short magnets or have to integrate the stops into the dipoles • Maybe space between beam and magnet aperture can be reduced • Reflectivity of photons (4keV critical energy) might be OK D. Schulte: Beam pipe kickoff meeting

  7. Conclusion • Beam pipe design is very critical • Magnet cost • Power consumption • Beam stability • Electron cloud • Consider four different approaches • All have advantages and disadvantages • Need to explore them to some level • Will require R&D • Will form an integrated working group • Experts from the different fields • Meet regularly • To work out details • To come up with novel ideas • Will need to find a time slot and make sure that each field can be represented D. Schulte: Beam pipe kickoff meeting

  8. Potential Next Steps • Define conventional solution • Temperature of beam screen • Design of screen and inner kryostat • Probably thickness is independent of the inner aperture • Can then define inner aperture from beam dynamics • Define strategy with high temperature superconductor coating • Material • Electron cloud mitigation • Inner kryostat/beam screen • Aperture • Define a strategy for photon stops • Integration of stops into dipoles • Required shielding gap thickness • Determine impedance effects • Define strategy toward open midplane magnets • Is it worth exploring? D. Schulte: Beam pipe kickoff meeting

More Related