Route 17 George Washington Highway
This presentation is the property of its rightful owner.
Sponsored Links
1 / 15

Contract awarded to low bidder EV Williams $25.2 million Contract separated into Three Phases PowerPoint PPT Presentation


  • 86 Views
  • Uploaded on
  • Presentation posted in: General

Route 17 George Washington Highway York County State Project: 6017-099-129,P101, R201, C501, B604 UPC: 60843 Project Status August 20, 2013. Contract awarded to low bidder EV Williams $25.2 million Contract separated into Three Phases Mostly Geographical Limits Each Phase has Three Stages

Download Presentation

Contract awarded to low bidder EV Williams $25.2 million Contract separated into Three Phases

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Route 17 George Washington HighwayYork CountyState Project: 6017-099-129,P101, R201, C501, B604UPC: 60843Project StatusAugust 20, 2013


  • Contract awarded to low bidder EV Williams

    • $25.2 million

  • Contract separated into Three Phases

    • Mostly Geographical Limits

  • Each Phase has Three Stages

  • Notice to Proceed: July 12, 2013

  • Completion: December 31, 2016

  • Roadway Substantially Complete by 09/30/16


Phase 1: August 2013 to February 2015

Private Utility Relocation

Ends Near Bowling Alley

Phase 1


Phase 2: February 2015 to December 2015

Ends At Washington Sq.

Phase 2


Phase 3: December 2015 to December 2016

Ends At Wolf Trap Rd

Phase 3


Each phase has three stages

Phase 1 Stage 1

  • Add temporary pavement near bridge

2) Shift Traffic to outside and narrow lanes

3) Construct Median and Middle of Bridge

August 2013 to February 2014


Each phase has three stages

Phase 1 Stage 2

1) Shift SB Traffic to Middle of Bridge

3) NB Traffic

2) Construct SB side of Bridge

February 2014 to May 2014


Each phase has three stages

Phase 1 Stage 3

1) Shift SB Traffic to Outside on New Bridge

2) Shift NB Traffic to Middle of Bridge

3) Construct NB side of Bridge

May 2014 to February 2015


Phases 2 and 3 have three stages

Stage 1

2) Place traffic control barrels

1) Add temporary pavement


Phases 2 and 3 have three stages

Stage 2

1) Place traffic control barrels

2) Shift traffic toward median

Perform construction on the outside lanes


Phases 2 and 3 have three stages

Stage 3

1) Place traffic control barrels

3) Perform construction in median

2) Shift traffic toward the outside


Stage 1


Stage 2


Stage 3 Bridge Stage 2 Road


Stage 3 Road