Procost version 3 0 modifications
This presentation is the property of its rightful owner.
Sponsored Links
1 / 14

ProCost Version 3.0 Modifications PowerPoint PPT Presentation

  • Uploaded on
  • Presentation posted in: General

EES. Consulting. ProCost Version 3.0 Modifications. RTF Update Kevin Smit Kelly Tarp 425-889-2700. A registered professional engineering corporation with offices in the Seattle, Bellingham, and Portland metropolitan areas Telephone (425) 889-2700 Facsimile (425) 889-2725.

Download Presentation

ProCost Version 3.0 Modifications

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.

- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript

Procost version 3 0 modifications



ProCost Version 3.0 Modifications

RTF Update

Kevin Smit

Kelly Tarp


A registered professional engineering corporation with officesin the Seattle, Bellingham, and Portland metropolitan areas

Telephone (425) 889-2700 Facsimile (425) 889-2725

What is procost

What is ProCost?

  • It’s the Council’s energy efficiency measure cost-effectiveness model

    • Calculates costs and benefits for EE measures

    • Produces a wide range of results, from different perspectives

  • Developed in MS Excel using various worksheets and the Visual Basic macro functions.

  • Who uses ProCost?

    • The Council: to develop the supply curves for the regional power plans

    • The RTF: for measure and program cost-effectiveness analysis

    • Others including utility personnel, consultants, etc.

  • The current version is “2.3 Build 257f”

Procost structure

ProCost Structure

The main ProCost file contains the ProCost VB macro and performs all the calculations.

The MC_And_Loadshape file contains data that is read into ProCost.

Excel Workbooks

Excel Worksheets

Overall objectives of v3 0

Overall Objectives of V3.0

  • ProCost Functionality Changes:

    • Early Retrofit Measures – savings value changes within the measure lifetime

    • Simultaneous Calculations for Retrofit and Lost Opportunity Measures – enable different risk credit values for each

    • Marginal Line Losses – line loss varies by time segment and conservation load shape

    • Periodic Replacements Costs – End Effects

    • User-defined Time Segments Up to 8760 Hours per Year

  • Documentation

    • User’s Guide

    • Reference Manual

Simultaneous retrofit and lo

Simultaneous Retrofit and LO

  • Lost opportunity measures have higher avoided cost threshold (more valuable to acquire if lost otherwise)

  • Requires two input values for the Risk Mitigation Credit

  • New input row in “ProData”, Utility System Parameter section

  • New Column on measure input/output worksheet:

Periodic replacement costs

Periodic Replacement Costs

  • End effects for periodic replacement costs – not in V2.3

  • Added the capability to correctly handle the short remaining portion prior to the end of measure life.

Used same partial replacement method used for capital cost end effects

  • Impacts of the following not shown:

  • Present value time zero

  • Input cost reference year

  • Program start date

  • Sponsor shares

Procost version 3 0 modifications

Early Retrofit Capability: Measures installed prior to the end of the useful life of pre-conditions baseline

Two savings values within a measure life

Remaining Useful Life

Marginal line losses

Marginal Line Losses

  • Marginal line losses not in V2.3

  • Added the capability to handle marginal line losses by time segment(approved by RTF in 2008)

Marginal line losses cont

Marginal Line Losses (cont.)

  • Changes to user input

  • Results comparison

User defined time segments

User Defined Time Segments

  • Version 2.3 uses Monthly by 4-Segment = 48 bins/year

  • Added capability for up to 8760 (hourly) time segments

  • Key Components:

    • For testing, EES generated 8760 data from 48 segment data

    • Restructured MC_AND_LOADSHAPE format

    • Load shapes, load factors, and coincidence factors for user defined time segments developed under a separate RTF effort

    • Separate MC_AND_LOADSHAPE file for each segment type (e.g., 48 and 8760 segments)

    • New header in MC_AND_LOADSHAPE

User defined time segments cont

User Defined Time Segments (cont.)

  • Challenges:

    • MC_AND_LOADSHAPE file size

      • Current model requires 8760 segments X 20 years for each load shape

      • Separate MC file for each segment type (e.g., 48 and 8760 segments)

      • Current 8760 segment MC file contains just 3 load shapes for testing plus all 20 year price forecasts (65 MB)

      • Suggested calendar function will reduce data to a single year X 8760 segments

      • Estimated file size = 64 MB (1 year X 8760 segments X 200 load shapes)

      • Additional options to reduce file size by condensing data to 1 worksheet

    • 8760 runtime

      • MC file takes approx. 45 sec. to open + additional 45 sec. to run ProCost

      • Static versus dynamic arrays – kept static, but using dynamic could improve efficiency

      • Precision – reduced arrays to single precision from double

Testing 8760 capability

Testing 8760 Capability

  • EES completed initial testing against 48-bin an analysis

  • Council staff testing impact of change

  • Initial findings to be reported on Feb 20, 2013



  • User’s Guide

    • How to use ProCost

    • High level “getting started” guide

  • ProCost Reference Manual

    • How ProCost works

    • Every thing else about ProCost

What s next

What’s Next?

  • Prior to 3.0 Release

    • Integrate the new conservation load shape data and calendar function

    • Stabilize the ProData interface

    • Additional testing and developing of test cases

    • Cost reference year, 2006

  • Longer Term Items

    • New MC file format

    • Source review

    • New capability for capacity and peak kW

    • Batch processor tool

    • Online version

  • Login