33% RPS Implementation Analysis Flow Chart. RETI (preliminary resource build-out) September. LTPP Decision February. Scenarios and Metrics; Assumptions and data August/September. Consultant Straw Proposal with 33% scenario definition November. Resource Build-outs Initial - November

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' Consultant Straw Proposal with 33% scenario definition November' - pepin


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript

33% RPS Implementation Analysis Flow Chart

RETI (preliminary resource build-out)

September

LTPP Decision

February

Scenarios and Metrics; Assumptions and data

August/September

Consultant Straw Proposal with 33% scenario definition

November

Resource Build-outs

Initial - November

Final - February

Renewable Integration Analysis

Data Collection:

IOU and POU contract and resource data

Project-level Barrier Analysis

February

Beyond 2020 policy analysis

Environmental Screens