1 / 26

Tracking system PNPI Status report A.Krivshich June 14, 2004 “MUON” Collaboration meeting Gatchina, Russia

Tracking system PNPI Status report A.Krivshich June 14, 2004 “MUON” Collaboration meeting Gatchina, Russia. РС 1. E. ТРС . μ - muons . РС 2. Tracking system for μp-capture experiment. Proportional chambers and PC-2 Two sets of PC2 electrodes under production.

paul
Download Presentation

Tracking system PNPI Status report A.Krivshich June 14, 2004 “MUON” Collaboration meeting Gatchina, Russia

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Tracking system PNPI Status report A.Krivshich June 14, 2004 “MUON” Collaboration meeting Gatchina, Russia

  2. РС 1 E ТРС μ - muons РС 2 Tracking system for μp-capture experiment

  3. Proportional chambers and PC-2 Two sets of PC2 electrodes under production. It order to finish the PC2 production and start its testing we would propose to discuss and fix a possible amount of materials in the PC2 cathodes during this workshop. • New design of cathode. • Aluminum. Thickness 40m. Soft. • Aluminum. Thickness 40 m. Hard. • Aluminum. Thickness 10m. Soft. • Aluminized Mylar (50m). Old design of cathode. Diameter of wires 55m. Stainless steel. Wire spacing is 1 mm.

  4. Time Projection Chamber TPC#1. It is tested about 15 months. TPC#2. It is tested about 3 months. TPC#3. It has to be assembled after finishing of TPC#1 and TPC#2 tests.

  5. Electrode wiring at PNPI Frame manufacturing at PNPI Ultra sound cleaning Dust control by light emission in nitrogen TPC assembling in clean room Print circuit depositing at STU Hydrogen Nitrogen Gas supply system TPC production chain TPC testing in vessel

  6. 90Sr Old (PNPI) vessel ТРС № 1 Date of TPC birth – 18 February 2003 Туре of vessel - Old one (PNPI) Gas admixtures Oxygen NitrogenWater After filling≤0.5 ppm ≤0.5 ppm≤1 ppm One month after filling ≤1 ppm 8 ppm≤ 1 ppm

  7. TPC#1. Stage # 1 Gas - Nitrogen Pressure- 5 Bar Training period- 7 days Training results- Idc ≤ 2nA (HV = 7000V) Testing period- 11 months Heating conditions- 1200C; 24 hours; 4 times. Tests duration- 5 months. Testing results- Idc ≤ 2nA (HV = 6500V)

  8. Outer cathode wire has been broken in the solder point. Chamber was disassembled. The wire was taken out. Chamber was assembled again. Pressure- 10 Bar Testing period- 10 days TPC#1. Stage # 2 Date of start – 4 February 2004 Gas - Hydrogen Test results- Idc ≤ 5nA (HV = 6500V)

  9. Results of the TPC#1 electrodes visual inspection No traces of dust. No dark spots on the anode. A few light-gray spots (2-3mm diameter) have been observed on the cathode planes. Dark current after chamber assembling Idc ≤ 5nA (HV = 6500V)

  10. Periodic breakdowns occurred Breakdown current exceeded 50A under HV=6500V. Time interval between the breakdowns under irradiation by 90Sr source 67 hours …………………. HV=5300V 48 hours …………………. HV=5400V 48 hours …………………. HV=5500V 6 hours …………………. HV=5600V Long term operation characteristics of TPC#1 under irradiation At HV = 5200V (I = 2nA) No breakdowns during one month

  11. Conclusion about TPC#1. 1. The results obtained during more than one year of TPC#1 operation looks quite well. We believe that TPC design and technology of its assembling are reliable and quite promising. 2. A couple of days ago TPC#1 has been taken out from the vessel to study the reasons of breakdowns. 3. The main possible reason of the breakdown occurring is the charge accumulation on the dielectric with consequent discharge. 4. Very probable that main reason of breakdowns is some mistake during TPC assembling.

  12. 90Sr ТРС #2 Date of TPC birth –24 March 2004 Туре of vessel - New one (PNPI+PSI) Stage #1 Gas - Nitrogen Pressure- 5 Bar Training period- 3 days Training results- Dark current is rising up/down from 0.005 to 6A at HV=5200V. It was fixed the number of anode wire which are associated with this current. Conclusion: take out TPC from the vessel to see what happened.

  13. Results of the TPC#2 electrodes visual inspection 1.No traces of dust. 2.No dark spots on the anode. 3.One dark spot (3mm diameter)has been observed on the cathode (top) directly in front of labeled anode wire . Date of start – 6 April 2004 (One week later) Gas - Nitrogen, 5 Bar Test duration - One week Stage #2 HV=5400VHV=6300V Neighbor wire0.6 A2.4 A Central wire2.5 A3.0 A Neighbor wire2.2 A3.0 A

  14. Nitrogen. 5 Bar. Total currant Currant from central wire

  15. Stage #3 Gas - Hydrogen. 10 Bar Date of start – 14 April 2004 Testing period- 7 days Obtained results. 1. TPC is running more unstable. First trip (10A)was at HV=4700V. 2. Current in hydrogen exceeds current in nitrogen by 2-3 times. 3. Dark current is about 20A at HV=6200V. Conclusion: take out TPC from the vessel to see what happened again.

  16. Results of the TPC#2 electrodes visual inspection 1.No traces of dust. 2.No dark spots on the anode. 3.Three dark spots have been observed on the cathodes. 3.1. Two of them are placed symmetrically with respect each other directly in front of labeled anode wires. 3.2. Diameter of top (cathode) spot increased up to about 12mm. 3.3. Diameter of bottom (strip-cathode) spot was about 7mm. 3.4. Third spot had diameter about 3mm and placed far away from mentioned above sports.

  17. Element distribution along the hot spot that are placed on the cathode wires Strip-cathode Cathode

  18. 90Sr 90Sr source has been collimated Actions 1. Cathode wires with spots have been replaced by new one. 2. TPC was assembled again. 3. Hydrogen. 10 Bar. 4. Date of start – 4June 2004 5.Testing period- 1.5 months (till now) 6. Main cathode - HV = 25 kV Stage #4

  19. After taking out of cathode wires with two hot spots the dark current behavior improved significantly. So, the point where dark current is rising up more than 100 times has been shifted from HV=4.7kV to about 5.8kV.

  20. Summary • We feel ourselves quite optimistic because the life become more better. • At the moment we have quite good experimental facilities to perform the TPC study at PNPI. We can work with two TPC simultaneously and we do it. 2. Working characteristics of TPC#1 and TPC#2 looks quite promising. Our goal is to investigate TPC behavior, including extremely high working conditions. TPC must be reliable working device. 3. It is necessary to investigate the nature of dark spots on the cathodes and prevent their creation. 4. We are going to start production of TPC#3 and TPC#4 only after finishing of TPC#1 and TPC#2 investigations. 5. We believe that at least one of these TPC will work in the next our beam run at PSI.

More Related