1 / 9

Southwest Renewable Energy Transmission Conference

Southwest Renewable Energy Transmission Conference. May 21, 2010 This report contains transmission planning data that may be conceptual in nature and is subject to change. The transmission projects listed may change scope or not be constructed. Transmission Ownership Colorado.

paul
Download Presentation

Southwest Renewable Energy Transmission Conference

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Southwest Renewable Energy Transmission Conference May 21, 2010 This report contains transmission planning data that may be conceptual in nature and is subject to change. The transmission projects listed may change scope or not be constructed.

  2. Transmission OwnershipColorado

  3. PSCo System Statistics2009 • 4153 Miles of Transmission • 251 Substations Served • 25 Generators Served • 9 Wind Generators (1258 MW) • 1 Solar Generator (8 MW PV) • PSCo Operating Company Peak Load 6249 MW (Actual) (7/14/2009) • PSCo Balancing Authority Peak Load 7457 MW (Actual) (7/14/2009) • Historical Peak Operating Company Load 6927MW (7/212005) • Historical Peak Balancing Authority Load 7766MW (7/212005)

  4. Senate Bill 07-100 • Upon recommendations by the 2006 Transmission Task Force on Reliable Electricity Infrastructure, the 66th General Assembly passed Senate Bill 07-100 • Under SB 07-100, PSCo must meet the following requirements: • Designate “Energy Resource Zones (ERZ)” • Develop plans for the construction or expansion of transmission facilities necessary to deliver electric power consistent with the timing of the development of beneficial energy resources located in or near such zones • Consider how transmission can be provided to encourage local ownership of renewable energy facilities • Submit proposed plans, designations, and applications for certificates of public convenience and necessity to the commission for simultaneous review

  5. Senate Bill 100 Project Status *Project status and dates subject to change

  6. Current SB-100 Transmission Plan10-22-2009 New Ault-Cherokee 230 kV ~ISD 2015-2016 New Pawnee-Smoky Hill 345 kV, ISD 2013 New Pawnee-Daniels Park 345 kV -2nd circuit ~ISD 2016-2017 New Missile Site 230 kV (ISD 2010) & 345 kV (ISD 2013) New Midway-Waterton 345 kV ISD 2011 New Lamar-Comanche 345 kV & Lamar - Missile Site 345 kV ~ISD 2016-2017 New San Luis Valley-Calumet-Comanche 230 & 345 kV lines ~ ISD 2013 New Lamar –Vilas 345kV ~ISD 2016-2017

  7. High Plains Express Initiative • Two 1,280 mile, 500kV, AC lines through WY, CO, NM and AZ • 3,500 – 4,000 MW of transmission capacity • Connects Regional Projects • 11 parties participating • Under second phase feasibility studies

  8. Completion of HPX Initiative • Increased local generation • Inclusion of new renewable generation plants • Reduced carbon footprint in the local community • Cost of energy favors export of local generation • Inability to utilize all local generation • Sell generation on the wholesale market to New Mexico and Arizona

  9. PSCo Public Website and Contact Information • SB-100 web site • http://www.sb100transmission.com • High Plains Express web site • http://www.highplainsexpress.com