An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. DESY assembly infrastructure for XFEL BQU preparation Marco Schalwat TTC Topical Workshop on SRF Cryomodule Clean Room Assembly CEA Saclay, 12th november 2014

  2. Outline • Overview on components • Overview assembly steps and devices • Shipment procedures • Quality control • Conclusion

  3. Overview on components Quadrupole BQU complete Beam-position monitor CEA (BPM_R) Beam-position monitor DESY (BPM_C) Gate valve with vaccum measuring device

  4. Overview on assembly steps and needed devices First day: - Assembly of connection quadrupole and beam-position monitor (BPM) - 6x high pressure rinsing (about 5 hours with 100 bar ultra pure water) - drying in class ISO 4 Second day: - assembly of elbow valve to quadrupole - assembly of UHV Feedthrough to BPM - install vacuum / RGA Third day: - leak check - assembly of connection bpm to gate valve - install vacuum / RGA Fourth day - final leak check of completed BQU unit - prepare packaging in ISO 4 and shipment

  5. transport procedures Transportation of the BQU (incl. Transport frame 450kg) from DESY Hamburg to CEA Saclay

  6. Quality control • All components are handed over for assembly under ISO 4 conditions „ready for assembly“ Particulates • Up to BQU 10 a cross check of particles was done on each component • From BQU 11, a particle check before closing the Qpole Unit was performed check with particle counter 2 minutes, max concentration allowed 10 (0,3 µm)/min qft Vacuum • RGA and leak check after each assembly step • Integral leak check after finishing the Qpole Unit At CEA • Vacuum check after transportation with vacuum diagnostic unit

  7. Conclusion • For the XFEL project a weekly delivery of Beamposition – Quadrupol - Units is requested and done at DESY Status • 36 units are produced up to now • 27 units are shipped to CEA Saclay under ISO 4 conditions (cleanroom to cleanroom hand out) • Up to now only one unit was rejected • Unexpected with vacuum degradation during storage of BQU was observed and investigated • A weekly hand out is established

  8. Thank you ! Thanks to all colleagues for their support.