MSD II Week 6 Update. P13265: Motorcycle Safety Lighting and Portable Electronics Charging System. Mike: Action Items Status. Lens Covers Incomplete Still waiting on shell Bike Wiring Harness/ Tx Box In Progress (almost complete) Test fit on bike, confirmed fit w/no permanent mods.

Download Presentation

MSD II Week 6 Update

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Msd ii week 6 update

MSD II Week 6 Update

P13265: Motorcycle Safety Lighting and Portable Electronics Charging System


Mike action items status

Mike: Action Items Status

  • Lens Covers

    • Incomplete

    • Still waiting on shell

  • Bike Wiring Harness/ Tx Box

    • In Progress (almost complete)

    • Test fit on bike, confirmed fit w/no permanent mods.

  • Wireless XBee Test

    • Complete

    • Captured waveforms from bike for all light sources

  • Assist Tyler with Shell

    • In Progress


Mike action items status1

Mike: Action Items Status


Mike next steps for week 7

Mike: Next Steps for Week 7

  • Finish board population w/TJ ~5 hrs

  • Edit/ complete Tech Report ~ 10 Hours

  • Assist Tyler with Shell~ 10 Hours

  • Begin lens covers? ~5 hrs


Tyler action items status

Tyler: Action Items Status

  • Finish New Mold

    • In Progress

    • More, various setbacks, near completion

  • Shell Assembly

    • Incomplete:

    • Pending completion of new shell

  • Poster Work

    • Incomplete:

    • All time this week was dedicated to getting the mold done.


Tyler next steps for week 7

Tyler: Next Steps for Week 7

  • Shell/Backpack Assembly ~ 15 Hours

  • Tech Paper ~ 4 Hours

  • Complete Assembly Plan ~ 4 Hours

    • Will be completed as backpack is assembled

  • Poster Work ~ 6 Hours


Ben action items status

Ben: Action Items Status

  • Electronics box

    • Finished but must be narrowed before gluing

  • Quick Connect

    • Testing was performed this weekend, with the length of the male end confirmed (along with the mounting of the female end).


Ben next steps for week 7

Ben: Next Steps for Week 7

  • Reduce box width- 5 hours

    • Must reduce the width of the top piece, bottom piece, both short sides, and redrill top in new corners

  • Install standoffs- ~2 hours

    • Placement of all standoffs must be precise

  • Tech paper

    • I will write my section for Friday


Eric action item status

Eric: Action Item Status

  • MSP430 Development

    • Incomplete, In Progress, Complete:

    • Explain

  • Board Build and Testing

    • Incomplete, In Progress, Complete:

    • Explain


Eric next steps for week 7

Eric: Next Steps for Week 7

  • NS #1 ~ # Hours

    • Explain

  • NS #2 ~ # Hours

    • Explain

  • NS #3 ~ # Hours

    • Explain


Tj action items status

TJ: Action Items Status

  • Populate PCBs

    • In Progress:

    • Should have adapters today and will complete final rework Friday afternoon

  • Test XBee's in Lab and on Bike

    • In Progress:

    • Dev Kit issues resolved with current limiting resistors

    • Bike signals captures and will be replicated in lab

  • EDGE Update

    • In Progress

    • Site cleanup and more formatting additions


Tj next steps for week 7

TJ: Next Steps for Week 7

  • Populate and Debug PCBs ~ 10 Hours

    • Finish all rework and go through Test Plan

  • XBee Lab Test ~ 2 Hours

    • Replicate motorcycle signals and ensure correct signal transmission

  • Assemble Tech Paper Rough Draft ~ 5 Hours

    • Put together segments and add additional information


Killian action items status

Killian: Action Items Status

  • Refine Sketches

    • Complete

    • Sketches, done, scanned into photoshop and started to apply gradient. Initial linework for illustrator renderings has begun, need to group sections and start to apply color/gradients

  • Backpack Assembly

    • In progress

    • Cut out a bunch of the cross sections, getting control panel 3-D printed

  • Poster Layout

    • In progress

    • Discussed gameplan with Tyler and Mike


Msd ii week 6 update

https://www.facebook.com/photo.php?v=10201084405291756&ref=notif&notif_t=video_tag


Killian next steps for week 7

Killian: Next Steps for Week 7

  • Complete Photoshop and Illustrator Renderings ~ 6 Hours

    • Just need to finish applying everything and possibly do a few other sketches of inserting items (phone, laptop, tablet)

  • Assist with Assembly ~ 7 Hours

    • Help with shell shaping and vacuum forming, painting control panel

  • Draw up Outlines of Poster, begin inserting text and graphics ~ 3 Hours

    • Hope to have a pretty set layout by next week


Major week 7 action items

Major Week 7 Action Items

  • Mike - Complete Tx Box

  • Tyler - Backpack Assembly

  • Ben - Finish Electronics box, quick connect

  • Eric -

  • TJ - Populate and Debug PCBs

  • Killian - Renderings and Assembly


Lessons learned

Lessons Learned

  • Mike

  • Tyler

    • Make sure to double check other peoples work thoroughly if your work is dependent on theirs. It's not okay to assume the thought of every problem that could arise.

  • Ben

    • Double check offset calculations


Lessons learned cont

Lessons Learned cont.

  • Eric

  • TJ

    • SMT population takes a long time and first revisions of boards often need to be reworked and modified for prototyping applications

  • Killian

    • You can print two items at once with 3-D printers, 3-D printing quality is very limited in the innovation center