HBD FEE test result summary + production schedule. 16mv test pulse result 5X attenuator + 20:1 resistor divider at input (to reduce the noise on the test pulse input) Result on the digitized baseline noise Large input pulse Digital filter

Download Presentation

HBD FEE test result summary + production schedule

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Hbd fee test result summary production schedule

HBD FEE test result summary+ production schedule

  • 16mv test pulse result

    • 5X attenuator + 20:1 resistor divider at input

      • (to reduce the noise on the test pulse input)

  • Result on the digitized baseline noise

  • Large input pulse

  • Digital filter

    • A nice, necessary, feature to remove the low frequency noise.

  • First look of the production schedule


Fee testing block diagram

FEE testing block diagram

20:1 attenuator

FEM

Pulse

Generator

Preamp

Test

Jig

5x

attenuator

ADC+FPGA

receiver

scope

Pulse

Generator

trigger

data

Clock

Master

L1 trigger

computer

ADC

Test point for receiver output

Receiver


Hbd fee test result summary production schedule

HBD ADC board

FPGA

ADC

Receiver/

shaping

Signals from Preamp


Hbd fee test result summary production schedule

Test stand

ADC module

Preamp test jig


Hbd fee test result summary production schedule

16MV test pulse on all the channels on FEM number 2

The test is done by moving test jigs cables (6 outputs) 8 times.

60Mhz noise

kicks back

from ADC

Preamp

output

Output of

FEM

receiver

10mv, 100ns per division

Digital sum

20mv/division


Hbd fee test result summary production schedule

Digitized 16mv test pulse result

2 samples at rising edge

1-2 ns time jitter on the test pulse

Reverse the signal cable

RMS


Rms on the baseline in varies conditions

RMS on the baseline in varies conditions

16mv test pulse generated about 210 ADC counts


Hbd fee test result summary production schedule

Overflow pulse

Preamp pulse

200mv, 20ns

per division


Hbd fee test result summary production schedule

Preamp pulse seen by channel 4 with noisy power line (100 events)

A

D

C

Digitized result

samples

Baseline distribution

Sample # 4

ADC


Hbd fee test result summary production schedule

Digital filtered preamp pulse on channel 4 data with noisy power line (100 events)

pulse(n+2) –pulse(n)

sample

Baseline distribution

Sample # 4

ADC


First look at production

First look at production

  • Assume RUN 7 electronics installation in Sept 06.

    • One month contingency  August

  • 2 months  PCB production + assembly

    • We only have to build 50 FEMs. This time could be shorten.

    • Schedule final design review on the electronics.

      • chain test with detector

        • To understand ground, gain/shaping time of the FEM etc

        • Once the parts is solder to the PCB, it is final…

  • 3 months  parts procurements

    • 1 month to generate P.O. and 2 months to get the parts

  • March is the time to buy parts.

    • Once we send out RFQ, we will know how good is the 3 months estimate.

  • Risks

    • March is the time to get ready for the RUN 6 test

      • Split manpower and attention