Large Public Works Projects and the General Contractor/ Construction Manager (GC/CM) Procedure: A New Way to Save Money, Time and Aggravation. Presenters. Dan Chandler, PE Principal Olympic Associates Company. Mark Henderson, AIA

Related searches for Large Public Works Projects and the General Contractor

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Large Public Works Projects and the General Contractor' - onan


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
Slide1 l.jpg

Large Public Works Projects and the General Contractor/ Construction Manager (GC/CM) Procedure: A New Way to Save Money, Time and Aggravation


Presenters l.jpg
Presenters

Dan Chandler, PE

Principal

Olympic Associates Company

Mark Henderson, AIA

Associate Principal, Health Care PracticeCallison Architecture

John Lynch, PE

Assistant Director

Washington State Department of General AdministrationDivision of Engineering and Architectural Services

Dick Goldsmith

Director, Legal Services and Health PolicyAssociation of Washington Public Hospital Districts


Topics l.jpg
Topics

  • Setting the stage

    • Traditional and alternative contracting methods

  • The GC/CM process

    • Statutory requirements

    • Contractual arrangements

    • Contracting steps

    • The Public Hospital District (PHD) Project Review Board

  • “ The good, the bad & the ugly”

    • Panel perspectives


Setting the stage l.jpg
Setting the Stage

  • Traditional method:“Design, Bid, Build”

  • Alternative method:GC/CM procedure


Statutory requirements l.jpg
Statutory Requirements

  • Determine if the project qualifies for GC/CM procedure

    • Value: over $10 million

      • Complex scheduling; or

      • Operation of existing facility during construction; or

      • Critical involvement of GC/CM during design phase

    • Value: between $5 million and $10 million

      • Authority for 10 demonstration projects


Statutory requirements cont l.jpg
Statutory Requirements (cont.)

  • Submit application to Public Hospital District (PHD) Project Review Board for approval

  • Obtain preliminary and final determination from PHD Commissioners (RCW 39.10.030)

    • Public review and comment


Contractual arrangements l.jpg
Contractual Arrangements

Public Hospital District

Designer

GC/CM

Sub-contractors


Responsibilities l.jpg
Responsibilities

  • GC/CM

    • Pre-construction services

    • Bidding the work

    • Construction services

  • PHD

    • Design

    • Project administration

    • Financing


Selecting the gc cm l.jpg
Selecting the GC/CM

  • Timing (early in the process)

  • Designing and planning

  • Request for qualifications (RFQ)

  • Pricing

    • General conditions

    • Fee only


Setting the price l.jpg
Setting the Price

  • Guaranteed Contract Cost (GCC)

    • Specified general conditions

    • Maximum Allowable construction cost (MACC)

    • % fee X MACC

    • GC/CM contingency

    • Sales tax

  • GCC excludes

    • Architect/Engineer (A/E) fee

    • Furnishings, fixtures and equipment (FF&E) costs

    • Other costs typically borne by Owner


Bidding the job l.jpg
Bidding the Job

  • GC/CM bids out all work

  • Can bid in phases

  • Can self-perform up to 30% of MACC

    • Low bid

    • Work customarily performed

    • Bid opening managed by PHD

    • Notice of intent to bid in public solicitation


Changing the work and owning the risk l.jpg
Changing the Work and Owning the Risk

  • Change Order

    • Owner’s contingency

    • Increases GCC

  • “Team Change” Funds

    • GC/CM contingency

    • GCC unchanged


Rewarding good work l.jpg
Rewarding Good Work

  • Incentive Clauses

    • Up to 5% of the MACC (typically much lower than 5%)

    • Paid out of contingencies at end

    • Based on good management by GC/CM


Phd project review board approval l.jpg
PHD Project Review Board Approval

  • Composition of board

  • Duties

  • Determinations

  • Policies and procedures


Application information l.jpg
Application Information

  • Current project total budget including

    • Estimated construction costs

    • Costs for professional services, equipment, and furnishing costs

    • Off-site costs

    • Contract administration costs

    • Other related project costs

  • Anticipated project design and construction schedule

  • Summary of PHD’s construction activity for the past six years


Application information cont l.jpg
Application Information (cont.)

  • Detailed explanation of why the PHD believes the use of the GC/CM procedure is in the public interest

  • Detailed explanation of why the PHD is qualified to use the GC/CM procedure, including a summary of the relevant experience of the PHD’s management team


An owner s perspective l.jpg
An Owner’s Perspective

  • Likes

    • Qualified contractors

    • Pre-construction services

    • Guaranteed MACC

    • Team approach

    • Management of project contingencies

    • GC/CM’s financial stake

  • Dislikes

    • Higher owner overhead costs

    • More management staff than with “Design, Bid, Build”

    • Higher A/E costs

    • Management of project risks


A project manager s perspective l.jpg
A Project Manager’s Perspective

  • Likes

    • Method and project matched

    • Necessary management skills obtained

    • RFQ and contract done correctly

    • Value of GC/CM in pre-construction services maximized

    • Risks and contingencies managed

  • Dislikes

    • Incentives can be risky

    • Advantages lost if not done well


An architect s perspective l.jpg
An Architect’s Perspective

  • Likes

    • Qualified contractors

    • Real value in pre-construction services

    • Teamwork reduces disputes

  • Dislikes

    • Some increase in A/E workload

    • “Inequality” among GC/CMs


Resources l.jpg
Resources

  • Washington Health Care Facilities AuthorityJohn Van Gorkom, Executive Director P.O. Box 40935Olympia, WA 98504-0935(360)753-6185www.whcfa.wa.gov/

  • Office of the Superintendent of Public Instructionhttp://www.k12.wa.us/SchFacilities/GCCM.aspx


Legal sources l.jpg
Legal Sources

  • Contracting process for GC/CM – RCW 39.10.061

  • Composition, duties, determinations and application of PHD Project Review Board – RCW 39.10.117

  • Authorization of demonstration projects – RCW 39.10.068(1)(b)


Legal sources22 l.jpg
Legal Sources

  • Public review after PHD Public Review Board approval – RCW 39.10.030

  • Other public works requirements include:

    • Licensed or registered contractors – RCW Chapter 39.06

    • Bonded contractors – RCW Chapter 39.08

    • Payment of prevailing wages – RCW Chapter 39.12

    • Contract retainage – RCW 60.28.011