Episode 3 / CAATS II joint dissemination event

Episode 3 / CAATS II joint dissemination event. Lessons Learnt. Episode 3 - CAATS II Final Dissemination Event. Philippe Leplae EUROCONTROL Episode 3. Brussels, 13 & 14 Oct 2009. Content. Project objectives Lessons learnt method Lessons learnt in: management validation

onan
Download Presentation

Episode 3 / CAATS II joint dissemination event

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Episode 3 / CAATS II joint dissemination event Lessons Learnt Episode 3 - CAATS II Final Dissemination Event Philippe Leplae EUROCONTROL Episode 3 Brussels, 13 & 14 Oct 2009

  2. Content • Project objectives • Lessons learnt method • Lessons learnt in: • management • validation • concept clarification • result integration • validation techniques • Conclusion Episode 3 - CAATS II Final Dissemination Event

  3. Project objectives • Provide detail on key concept elements in SESAR • Initial operability and performance assessment • Initial technical impact assessment • Analysis of available tools for SESAR validation • Report on validation methodology …… • Hence specific emphasis on lessons learnt Episode 3 - CAATS II Final Dissemination Event

  4. Lessons learnt method • 2 workshops, Madrid and Brétigny • 9 different sessions on 5 main topics involving more than 30 participants • Validation strategy and project DOW • Project management • Concept clarification • Integration and Consolidation • EP3 validation techniques and levels of maturity • Most project members also working in SESAR • Strong desire to provide feedback to SESAR Episode 3 - CAATS II Final Dissemination Event

  5. High level lessons learnt • System view should drive validation activities • Need to adapt DOW and management to required flexibility • Need time to develop system driven project • We have developed artefacts to drive it • Many different techniques tried on Episode 3 • Suited to low maturity level concept elements • Guidelines on when and how to use it are produced • Importance of support tools • Good strategy useless without tools to support it • Tools also require investment in training • This provides harmonized working methods, key to make distributed project work Episode 3 - CAATS II Final Dissemination Event

  6. Lessons learntin management • Our challenges: • Wide range of disseminated partners • Crossed responsibilities and thinly spread effort • Innovative tasks • High quality requirements • Tight deadlines • Our answers: • Development of tools for distributed work • Training on the tools, and specific delivery process • A lot of co-ordination activities • Follow-up actions: • Build more flexibility in the programme (DOW and contract) Episode 3 - CAATS II Final Dissemination Event

  7. Lessons learntin validation • Our challenges: • Maturity lower than expected at programme onset • E-OCVM V2 not well adapted to concept wide validation • Lack of E-OCVM expertise inside team • Wide range of results • Our answers: • We built a framework with guidelines, principles, templates. • Developed assumptions management • Performance framework and DOD’s provided at start • Guidance provided through system WP and co-ordination cell • Thorough review of experimental plans • Open issue: • Maturity assessment at start of each validation activity Episode 3 - CAATS II Final Dissemination Event

  8. Lessons learntin concept clarification • Our challenges: • Multiple sources from SESAR (CONOPS, OI’s,etc…) • Lack of details for validation • Multiple sources to update DOD’s • Our solutions: • Propose a structure, around process model and DOD’s • Develop different modes of descriptions • DOD’s • Operational scenarios • Story boards • Develop collaborative working methods to update documents • Follow-up: • Establish a recognised authority to select among options • Use hot topics to drive validation Episode 3 - CAATS II Final Dissemination Event

  9. Lessons learntin result integration • Our challenges: • Exercises not providing consistent results • Different granularity of results • Various degree of validity of quantitative data • Our solutions: • Influence diagrams help understanding benefit mechanism and identify where performance is improved • Influence model has been developed ready to be fed with results • Management of assumptions to interpret results • For subsequent coverage: • Steer validation activities from the performance framework • Use of models developed in EP3 to provide more quantitative data to performance model Episode 3 - CAATS II Final Dissemination Event

  10. Lessons learnt in validation techniques • Successful used of different techniques • Prototyping • Macro-modelling • Various sorts or gaming • Expert groups • Work packages integrated different techniques • Combine results of very different nature • Various sequences of activities tried • Expert groups key to success • Benefits of industry assessment: • “Reality check” • Should run as a complementary process to operational validation Episode 3 - CAATS II Final Dissemination Event

  11. Validation techniques:Expert Groups • Lessons learnt • Useful at all maturity levels • Need good facilitation techniques by somebody with OPS expertise • Need current operation experts + concept experts • Storyboards good method to structure EG debates • Our input to SESAR • Storyboards technique • Various facilitation techniques • Hot topics • Guidelines document Episode 3 - CAATS II Final Dissemination Event

  12. Validation techniques:Gaming • Lessons learnt • To be associated with Expert Groups and modelling • Suited to clarify roles and responsibilities for all maturity levels • More flexible than prototyping as not in real time (interruptions feasible) • Progression from paper-based gaming to platform gaming • Our input to SESAR • Different platforms • CHILL • DARTIS • ACCES platform • Paper based gaming and associated web based tool • Guidelines document Episode 3 - CAATS II Final Dissemination Event

  13. Validation techniques:Prototyping • Lessons learnt: • Not a cheap RTS! • Allowed to fail • Concept clarification-no quantitative data • Successive runs with same team of OPS staff • Our input to SESAR • First results on: • PRNAV, CDA in descent phase. • Acceptability of 4D trajectory to controllers • Guidelines document Episode 3 - CAATS II Final Dissemination Event

  14. Validation techniques:Modelling • Lessons learnt: • Use of process modelling and network modelling • Process modelling complement gaming • Need to work on precise concept elements • Macro-modelling • Our input to SESAR: • 3 innovative tools developed in EP3 • One abandoned (unsatisfactory results) • One providing results when applied to mature concept elements • One promising for network wide assessments • Guidelines document Episode 3 - CAATS II Final Dissemination Event

  15. Conclusion • Episode 3 is the first ATM-wide concept validation programme • We had to develop tools and methods adapted to this new challenge • Another 2 months to complete our work (WP and final report) • We provide to SESAR: • New tools • New methods • An integrated approach • First validation results… • See www.episode3.aero • And our most precious output: • A team with the expertise and concrete experience already working on the SESAR projects: Episode 3 - CAATS II Final Dissemination Event

  16. Episode 3 - CAATS II Final Dissemination Event

  17. Thank you