An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Restructure of WP4 – provisional ideas and numbers to promote discussion Ian Wilmut

  2. Effort estimates/distribution from start of project • This table was created by Tim at start of project • This section has gone (now in past) • This will not happen in the planned timescale (production preparation) • These are dramatically reduced by 130nm delay • This should probably be too much given 130 delay, but is harder than expected and perhaps should be left as is.

  3. Effort estimates/distribution from start of project • This table was created by Tim at start of project • This section has gone (now in past) • This will not happen in the planned timescale (production preparation) • These are dramatically reduced by 130nm delay • This should probably be too much given 130 delay, but is harder than expected and perhaps should be left as is.

  4. Effort estimates/distribution from start of project • This table was created by Tim at start of project • This section has gone (now in past) • This will not happen in the planned timescale (production preparation) • These are dramatically reduced by 130nm delay • This should probably be too much given 130 delay, but is harder than expected and perhaps should be left as is.

  5. Effort estimates/distribution from start of project • This table was created by Tim at start of project • This section has gone (now in past) • This will not happen in the planned timescale (production preparation) • These are dramatically reduced by 130nm delay • This should probably be too much given 130 delay, but is harder than expected and perhaps should be left as is.

  6. Effort estimates/distribution from start of project • This table was created by Tim at start of project • This section has gone (now in past) • This will not happen in the planned timescale (production preparation) • These are dramatically reduced by 130nm delay • This should probably be too much given 130 delay, but is harder than expected and perhaps should be left as is.

  7. Sources for this effort • Already some effort expected to be used in WP4 has moved to WP2 and WP6 (mostly to WP2) • Of the remaining effort we have both “engineer” and “technician” effort available. • Two “new” tasks are identified as good applications of this effort • Tracker Alignment – originally conceived as strips only but should probably apply to pixels as well • HVCMOS mechanics – If CMOS is to be pursued we should consider the mechanics of it. • We must maintain core of WP4 to make and test staves and to populate them. Whatever additional tasks we consider this is necessary. • At TUMM on Monday we agreed that Alignment would be baseline activity, but we would consider this carefully over next few months.

  8. Estimates of effort for Alignment • Probably 0.55 + 1.76 - 0.1 - 0.1 = 1.21 FTE available from production prep (yellow) • Probably 3.53 + 3.78 – 1 – 1 = 5.31 FTE available from stave QA (Red) • Probably 4.57 + 3.78 - 1.3 - 1.3 =5.75 FTE available from Stave core assembly (green) • Hard to understand effort available form module mounting, guess 1 FTE/year = 2 FTE (Purple) • So total effort that might be available =14.27FTE (7 full time people per year) • This is artificial as: • NM tech at Liverpool will not be funded • John Morris has left QMUL • Martin died and his replacement is yet to start. • IW estimate of effort made available is 5FTE/Yr for 2 year • But…

  9. Some people have voted with their feet already. • We need to understand these figures accurately, but my estimate is: • Graham Beck 15->20% extra now in pixels • Peter Sutcliffe 5->10% extra effort now in pixels • Stephanie Yang 20->30% extra now in pixels • Tim Jones ???? • Georg Viehhauser ???? • Total perhaps another 1-2FTE year now in WP2 not WP4 • So we might have 3FTE/Yr in WP4 available to work on Alignment/HVCMOS • I think this number is high, but then I think a lot of the figures are high.

  10. Conclusion • 130nm delay has hammered WP4 schedule • Implication is that we have effort that can now address other areas. Alignment and HVCMOS are most prommising. • The figures above are very provisional (more to give people something to shout at) • We must not stop the remaining part of the core WP4 programme, and we do need to have new deliverables within the programme.