RSEP Reform

RSEP Reform. Creating a Planning Process to Support Resource Adequacy. The RTEP Approach Results in “Transmission Only” Solutions to Reliability Problems. The Problem: RTEP has been passive towards non- transmission solutions.

oma
Download Presentation

RSEP Reform

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. RSEP Reform Creating a Planning Process to Support Resource Adequacy

  2. The RTEP Approach Results in “Transmission Only” Solutions to Reliability Problems • The Problem: RTEP has been passive towards non- transmission solutions. • Given the weak signals for Generation and Demand Response investment in New England, this approach limits cost-effective and timely alternatives and creates a “transmission only” set of results. • Under RTEP assumptions, no more generation can be built in SWCT until Phase II is finished – which is increasingly uncertain and expensive. • The Solution: RSEP must be reformed to include cost-effectiveness analysis for combinations of alternative solutions. • Non transmission components of expansion plans must be explored and presented as potential ways to reduce costs and improve the timeliness of reliability investment.

  3. The Way We Were • RTEP process developed: • During period of optimistic generation investment and nascent electricity markets • When little consideration was paid to demand response options • Assuming that, somehow, market forces would attract new generation as needed

  4. The Way We are Today RSEP process must be revisited to address changed circumstances: • Investment in generation sector reduced and extremely cautious regarding returns • Existing units are in jeopardy • Load response seen as a key initiative • Developed markets continue not to send appropriate price signals in generation-deficient areas

  5. RSEP Reform • RSEP should include analysis of costs of alternative solutions, and combinations of alternative solutions. Such information will: • Provide load and their agents with an understanding of the costs of transmission vs. alternative solutions. • Provide suppliers with information on generation solutions that can be supported by the existing system, and provide transmission plans that will support cost-effective new generation. • Interconnection studies are not an efficient way to accomplish this. • Allow investors, load, and their agents to identify the combination of transmission, demand response, and generation that can resolve reliability needs in the most cost-effective and timely manner.

  6. RSEP Reform--SWCT • Transmission has been planned for the area since the early 70s. • The only meaningful addition has been the 345Kv radial from Long Mountain to Plum Tree. • It has not become easier or less expensive to build in the area. • Signficant generation cannot be sited without relieving short-circuit constraints through Phase II or alternate means. • Phase II is getting further away, more expensive, less reliable, and increasingly likely to have major costs allocated to Connecticut.

  7. SWCT • RSEP should develop one or more credible alternate plans for SWCT including: • Demand response • Emergency generation • Transmission alternatives that will allow needed supply to be sited in the area and support reliability prior to the completion of Phase II • The overall need for specific transmission investments should be reevaluated in light of any more cost-effective alternatives identified by this comprehensive planning approach “We Need Them All”