Concrete and Asphalt Crushing

Concrete and Asphalt Crushing. Port is emerging from multi-year, multi-party litigation, involving a tenant bankruptcy and efforts by the Port to collect on the prior tenant’s insurance Port obtained “title” to pile in Spring of 2007

Download Presentation

Concrete and Asphalt Crushing

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Concrete and Asphalt Crushing Port is emerging from multi-year, multi-party litigation, involving a tenant bankruptcy and efforts by the Port to collect on the prior tenant’s insurance Port obtained “title” to pile in Spring of 2007 Judgment against tenant’s insurer just entered within last several weeks Port to begin contracting effort to clear pile starting this summer/fall

  2. Concrete and Asphalt Crushing Concrete crushing provides synergies with existing Port tenants. Current batch plants must haul some material to Brisbane, due to close in near future. Critical to reaching City’s zero waste goal. Emergency management component: after an earthquake where does debris go? Moved out of City by rail? Barge? May need to process (i.e., crush) before shipping. Concrete and asphalt crushing yields raw materials that can go back into concrete (aggregate for non-structural applications) or asphalt (newer asphalt plants can handle up to 30% recycled content). Without adequate market for products containing asphalt grindings (i.e., new asphalt plant), crushing enterprise may need to limit how much asphalt can be processed.

  3. Concrete and Asphalt Crushing • Two recent expressions of interest in rock crushing to Port Real Estate Division from private market • 4-5 other companies expressed interest last year • Likely would require 6 acres, interim leasing opportunity • Lease-based environmental financial assurances to avoid repeating the past

  4. San Francisco’s Asphalt Plant Pier 90-94 Backlands Opportunities June 9, 2007

  5. San Francisco’s Existing Municipal Asphalt Plant

  6. OverviewCurrent Asphalt Plant Site 1 = City Municipal Plant (Jerrold Avenue/Quint Street) 2 = Private Property 3 = DTIS 4 = SFWD CDD 5 = Southeast Wastewater Treatment Plant 6 = Central Shops 7 = Peninsula Joint Power Authority 8 = SE Community Center Greenhouse

  7. OverviewAsphalt Plant History • City has operated a plant since 1909. • Current plant built in 1954, renovated 1992-93. • Silos constructed in 2004, improved efficiency of plant, and increased capacity ($2.1 Million) • Permitted capacity of 100,000 tons/year (Air District)

  8. OverviewAsphalt Plant Production Projected funding and tonnage based upon FY 2007-2016 Capital Plan

  9. Plant Economics There isn’t enough demand for asphalt in San Francisco to support more than one Asphalt Plant. If a modern plant were built at Pier 90-94 Backlands, the City would close its plant at 1801 Jerrold.

  10. Bay Area Asphalt Plants Berkeley Asphalt Dutra Materials CCSF Asphalt Plant Cal Rock++ Graniterock Graniterock

  11. Advantages of having a plant in San Francisco • Because there is only one plant nearby (in South San Francisco), the City would be subject to monopolistic pricing of asphalt without a plant in the City. • No recycling. More than 24,000 tons of asphalt grindings would be disposed of annually, many of them in landfills. • An additional 18,000 miles of trucking would be required; apx. 3,500 additional gallons of diesel fuel annually for DPW alone.

  12. Advantages of having a plant in San Francisco • Without a plant, there is no guarantee of asphalt in an emergency. Large amounts of asphalt were supplied by the Plant immediately after the 1989 Earthquake for emergency repairs in SOMA and the Marina. • Unreliable supply of asphalt. If the South City plant were to be closed, or supplying other jobs, DPW crews would be idled.

  13. Advantages of having a plant at Pier 90-94 Backlands Raw materials delivered by barge & rail • Gravel arrives from British Columbia by barge and is trucked through the neighborhood to the existing plant. • Other materials and petroleum additives could be delivered by rail, instead of by truck. New plant would be cleaner & more efficient w/easy access to recycled materials from adjacent rock crushing.