Construction of the pipeline distribution system and distribution of gas in the municipalities of
This presentation is the property of its rightful owner.
Sponsored Links
1 / 6

Construction of the pipeline distribution system and distribution of gas in the municipalities of Travnik , Vitez , Busovača i Novi Travnik PowerPoint PPT Presentation


  • 83 Views
  • Uploaded on
  • Presentation posted in: General

Construction of the pipeline distribution system and distribution of gas in the municipalities of Travnik , Vitez , Busovača i Novi Travnik.

Download Presentation

Construction of the pipeline distribution system and distribution of gas in the municipalities of Travnik , Vitez , Busovača i Novi Travnik

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Construction of the pipeline distribution system and distribution of gas in the municipalities of travnik vitez busova a i novi travnik

Construction of the pipeline distribution system and distribution of gas in the municipalities of Travnik, Vitez, Busovačai Novi Travnik


Construction of the pipeline distribution system and distribution of gas in the municipalities of travnik vitez busova a i novi travnik

Thisproject envisions theconstruction of the distribution networkfor fourmunicipalities.The cantonal government has prepared feasibility study.Thestudyincludes the preliminary design of the distribution network.Connecting using measuring and regulating stations on transport pipeline Zenica – Travnik, built by BH Gas.The concession is awarded through 30-year public tender according to DBOT system (Design, Build, Operate, Transfer).


Construction of the pipeline distribution system and distribution of gas in the municipalities of travnik vitez busova a i novi travnik

  • In preparing the study for the degree of efficiency of gasification 3 different assumptions were taken into account:

  • Optimistic– the gas network will connect 75% of the housing units,

  • Medium – the gas network will connect 50% of the housing units,

  • Pessimistic - the gas network will connect 25% of the housing units.

  • Two different variants were taken in consideration for heating housing units:

  • Variant a – heat the dwelling, or 90m2,

  • Variant b – heat of half of the area, or 45m2.

Gasification project of individual municipalities takes place in three stages:Phase I – works to perform in the first year of the project,Phase II – works to perform in the third year of the project,Phase III – works to perform in the fifth year of the project.


Consumption of natural gas sm 3

Total construction costs (€)

Consumption of natural gas (Sm3)


Justification of investments

TRAVNIK

Justification of investments

NOVI TRAVNIK, VITEZ i BUSOVAČA


Construction of the pipeline distribution system and distribution of gas in the municipalities of travnik vitez busova a i novi travnik

  • MINISTARSTVO PRIVREDE

  • Adresa: Stanična 43, 72270 Travnik, BIH

  • Telefon: +387 30 / 511-217,

  • Fax: +387 30 / 511-729,

  • e-mail: [email protected]

  • www.sbk-ksb.gov.ba


  • Login