Pre-proposal Meeting Agenda Thursday May 14, 2009 US-95, Garwood to Sagle, District 1

GARVEE Transportation Program. Pre-proposal Meeting Agenda Thursday May 14, 2009 US-95, Garwood to Sagle, District 1. US-95, Garwood to Sagle, Athol Stage - Key No. 09791 US-95, Garwood to Sagle, Granite South Stage - Key No. 11894. GARVEE Transportation Program. Agenda

Download Presentation

Pre-proposal Meeting Agenda Thursday May 14, 2009 US-95, Garwood to Sagle, District 1

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. GARVEE Transportation Program Pre-proposal Meeting Agenda Thursday May 14, 2009 US-95, Garwood to Sagle, District 1 US-95, Garwood to Sagle, Athol Stage - Key No. 09791 US-95, Garwood to Sagle, Granite South Stage - Key No. 11894

  2. GARVEE Transportation Program Agenda Welcome & Introductions (Andrea Aliev) GARVEE Program Current Status (Ed Randol) General Project Information - Both projects (Amy Schroeder and Steve Alters) KN 09791 US-95, Garwood to Sagle, Athol Stage (Steve Alters) KN 11894 US-95, Garwood to Sagle, Granite South Stage (Steve Alters) Questions – KN 09791 and KN 11894 (Steve Alters, Kimball Ohsiek, and Joe Samer) Key Dates and Selection Criteria (Andrea Aliev)

  3. key map garwood_sagle.pdf Garwood to Sagle corridor

  4. Ultimate Section – Four lanes with grade separated intersections Ultimate Typical Section – Four Lanes & 22-foot paved median Garwood to Sagle environmental document (ROD December 2009) Initial Typical Section – Four Lanes & 4 to 14-foot paved median US-95 Cooridor review (August 2008) Specific Information - Both Projects

  5. Schedule (Estimated) Selection of Design Consultant Team: June 2009 Begin Intermediate Design, Consultant NTP: July 2009 Intermediate Design Review: November 2009 Complete Roadway Final Design: October 2010 PS&E Approval: December 2010 Specific Information - Both Projects

  6. Athol Stage.pdf Athol Stage – KN 09791

  7. ITD performing Preliminary design – Estimated completion June 2009 ITD Bridge designing Athol Structure Known Utilities Verizon Kootenai Electric Cooperative, Inc. Time Warner Cable Avista Utilities – Gas Linwood Estates – Water Northern Lights Electric, Inc. City of Athol Athol Stage – KN 09791

  8. Granite South Stage – KN 11894 Granite South Stage.pdf

  9. ITD performing Preliminary design – Estimated completion June 2009 Known Utilities Verizon Sprint Cell Tower Linwood Estates – Water Northern Lights Electric, Inc. Trans Canada Gas Transmission Northwest Granite South Stage – KN 11894

  10. Questions?