An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. R. CHAER* E. CORNALINO E. COPPES Facultad de Ingeniería & UTE UTE UTE Uruguay Uruguay Uruguay Modeling and simulation of the Power Energy System of Uruguay in 2015 with high penetration of wind energy

  2. SUMMARY This paper presents the results of detailed simulations of the operation of the power system of Uruguay, for the year 2015 when it reached the target of 1200 MW of wind power in the system. This level of win integration will be near the 60% of de peak of demand. The results show that this level of integration is manageable thanks to the large installed hydro power capacity in the country.

  3. A picture of 2015 Capacity vs. Peak • The ceil-goal for 2015 is to reach 1200 MW of installed wind power capacity. • The Expected demand for 2015 is about 1500 MW on average, with a peak of 2000 MW. • Wind penetration then will be of 60% in capacity and 33% in energy • How the system will be operated in 2015 with this such high share of wind power? • Are the available resources enough to compensate the wind power variations? 60% Energy 33%

  4. Uruguay – 2015 (expected generation by source)

  5. Wind Stochastic Model - CEGH A stochastic model with Gaussian Space Correlations with Histogram was identified using hourly series of wind measures obtained in 7 sites distributed over the country during 2 year . The model represents the temporal and geographicalcorrelationbetween sites andpatterns thewind direction for site. Also represents the annual and daily seasonality the resource

  6. This stochastic model was used to perform a simulation of operation of the system in 2015 using an integration time-step of one hour with the simulator SimSEE. All power plants in Uruguay are represented in this simulation, including: hydroelectric plants with their storage capacity and gas-oil, fuel-oil, bio-fuel and natural gas fired thermal units. Details

  7. Two major questions Is the model used for long-term planning valid for dealing with high wind energy integration? Does the energy system of Uruguay has enought resources to handle the time variability of wind?

  8. Modelling for Long Term Planning The model usedfor the optimal planningof investments ingenerationuses a weeklytime stepdivided into fourtime bands. (patamares) This model isexecutedhundredsof thousands oftimes fordetermining theoptimal investmentplan. Due toweeklyintegration stepthe model is notable toadequately representthe effect oftimevariationsof thewindfarms outputover the rest ofthe generating units.

  9. ModellingLong term vs. Short term Investment Planning - Long term Time Step: weekly dividen in 4 hourly-bands (PATAMARES) Hydros with reservoires: Bonete Wind Farms Output: stochastic, averaged by hourly-band Operation Planning - Short term Time Step: hourly Hydros with reservoires: Bonete, Palmar and Salto Grande Wind Farms Output: stochastic, averaged by hourly-band

  10. Wind Energy (Weekly – Hourly) There is no significant differencessince the weakly modelof wind farms production was calibratedaveraging the hourly model.

  11. Hydroelectric (Weekly – Hourly) Could be in the order of 582 GWh per year of energy surplus available from the hydro-subsystem in the actual operation of the system. This surplus is achieved by the effect of better management of the lakes with short-term storage capacity.

  12. Exports (Weekly – Hourly) Could be in the order of 50 GWh per year of energy surplus available for export in the actual operation of the system. This surplus is achieved by the effect of better management of the lakes with short-term storage capacity.

  13. For expansion planning it was assumed that the system purchases all the energy generated by wind farms at 65 USD/MWh; and that all the energy surplus are exported at 10 USD/MWh to neighboring countries. So a 50 GWh/year of exportable surplus respresents a overcost of 50000 x (65-10) = 2 MUSD/year. This represent an increase in the price of wind energy of 0.75 USD/MWh. Exportable surplus = Overcost

  14. Prices used for the long term planning. The estimates of the optimal amount of wind power to be installed in the system were performed initially priced at 90 USD/MWh and subsequently with 70 and 65 USD/MWh obtaining the same results in terms of the amount of power to be installed within the margin of error of the used tools. Therefore this change in price due to surpluses recorded in the hourly simulation over the weekly one, does not change the conclusions regarding the optimal amount of wind power to be installed in the system.

  15. First conclusion As shown, the economic impact of the difference between both runs, changes the price of wind power less than the price variations that were considered in the study of sensitivity. Then, we consider validated the model used for planning respect to the result of install 1200 MW in the next years. But in the future to continue adding wind farms to the system, the weekly time step must be shorten to represent adecuality the filtering efect of the small lakes. For filtering the wind energy variation they are not small.

  16. Does the energy system of Uruguay has enought resources to handle the time variability of wind energy?

  17. 1 second 1 minute 1 hour 1 day 1 weak 1 month 1 year What are the variations? Turbine-Machine intertial filter Geographical filter inter-farms Forecasting Extra load following resources Traditional operation resources

  18. Salto Grande (50% UY) 945MW 8 days Bonete 155MW Baygorria 140 days 108MW 3 days Hydroelectric Plants1541 MW Palmar 333MW 22 days

  19. 6 x 50 MW = 300 MW GT Punta del Tigre 8 x 10 MW = 80 MW Engines 2 x 100 MW = 200 MW GT La Tablada 540 MW CC (in bidding proccess) Fast fuel fired units

  20. 2000 MW With Argentina 570 MW with Brasil For planning purposes the import is considered closed. Interconnections

  21. A week of 2015

  22. Net Demand

  23. January 2015hydrology assuming historical low

  24. January 2015 assuming very high hydrology

  25. considering two scenarios, one with 1200 MW wind power installed capacity and one without wind power. Results were analyzed from the point of view of increasing variability of power generation, induced by wind generation. To do this we compared the variations in power from one hour to the following for energy sources with possibilities of fast regulation: hydraulics, gas turbines and engines. We do that by comparing the cumulative probability plots of the time differences of power, P(h) - P(h-1), of the simulated cases with wind and without wind. Hourly Simulations 2015

  26. Fast-Thermal units variations

  27. Hydro power

  28. Hydro subsystem It notes that the expected time variations of the hydraulic power to the system without wind power are the same level as the historical variations of the periods in which Salto Grande is not carrying out secondary regulation, while the expected variations for the system with 1200 MW of wind are similar to the historical variations in when Salto Grande is carrying secondary regulation.

  29. Exports

  30. Exports As can be seen in 80% of time is not necessary to use exporting power to regulate the system. It is remarkable that to meet the requirements in the remaining 20% of the time Uruguay has the ability to export to Argentina through the existing interconnection of 2000 MW and to Brazil through the interconnection of 70 MW already in operation plus 500 MW currently under construction. If the interconnections are not able to handle these increases of 200 MW the solution should be to reduce the power generated in the wind farms in those situations.

  31. The system should be capable to handle the variability of the 1200 MW in 2015. If the 2570 MW interconnection with Brazil and Argentina can not be used to absorb variations of 200 MW in less than 20% of the time, you should use to reduce the power generated by wind farms in those circumstances. Second Conclusion

  32. That all folks.