West Melbourne Lease Requirements. CICCC 12 March 2009. Stage 1by 2004 (Complete). New Vapour Emission Control System (Combustor) Upgrade Acrylate Storage Tanks (10 tanks) to have: Under tank liner for leak detection New dock lines and hard piped exchange areas

Download Presentation

West Melbourne Lease Requirements

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


West melbourne lease requirements

West Melbourne Lease Requirements

CICCC 12 March 2009


Stage 1by 2004 complete

Stage 1by 2004 (Complete)

  • New Vapour Emission Control System (Combustor)

  • Upgrade Acrylate Storage Tanks (10 tanks) to have:

  • Under tank liner for leak detection

  • New dock lines and hard piped exchange areas

  • Sealed truck loading systems and cast steel pumps with double mechanical seals

  • High pressure alarms


Stage 2 by 2008

Stage 2 by 2008

50% of flammable/hazardous tanks to have: (60% actually done)

  • Tank renovations including foundations where required (16 tanks)

  • Under tank liner for leak detection (16 tanks)

  • Hard piped exchange areas (all complete)

  • New piping systems, cast steel pumps and sealed truck loading systems (all complete)

  • High pressure alarms (all complete)


Stage 3 by 2012

Stage 3 by 2012

Remaining 50% of flammable/hazardous tanks to have:

  • Tank renovations including foundations where required

  • Under tank liner for leak detection

  • Hard piped exchange areas

  • New piping systems, cast steel pumps and sealed truck loading systems

  • High pressure alarms

  • Installation of impermeable liner to tank bunds and bund walls (Plant C done)


Plans for 2009

Plans for 2009

  • Tank renovations and under tank liner for leak detection for 3 tanks (1 done already)

  • Install new fill lines to all remaining tanks

  • Remove existing carbon beds and replace with static carbon bed

  • Replace old boilers unmanned system