1 / 9

PDR Vacuum Spool Clearances Check

PDR Vacuum Spool Clearances Check. T. Brown September 1, 2003. VV spool assembly clearance space allocation goal. 1.00 VV insulation 0.25 minimum gap at final position (also makes up part of the space needed for final assembly in the area of the VV spool piece)

norman
Download Presentation

PDR Vacuum Spool Clearances Check

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PDR Vacuum Spool Clearances Check T. Brown September 1, 2003

  2. VV spool assembly clearance space allocation goal 1.00 VV insulation 0.25 minimum gap at final position (also makes up part of the space needed for final assembly in the area of the VV spool piece) 0.188 VV fabrication tolerance (3/16”) 0.06 MC fabrication tolerance (1/16”) 1.50” 0.25” Additional assembly tolerance for final assembly (this value is 0.75” for the assembly of the MC over the VV). 1.75” Target clearance set for the MC to VV spacing in spool region

  3. Reverence VV-06 vessel spool had 1.50 clearance to MC during assembly. With weld prep added to basic VV-06 spool the clearance degraded to 1.32” Ref VV-06 basic spool 1.319” clearance Note: We accepted the 1.5” clearance because we were expecting a .25” build reduction in the Type C MC.

  4. Ref VV-06 basic spool Spool altered to eliminate crease PDR baseline spool New PDR spool shape exceeds original boundary in some areas

  5. Baseline PDR Vacuum Vessel and Module Coil clamp envelope

  6. 5.100 3/8 1/8 VPI layer 4.10 Clamp Winding 4.671 2.336 2.836 0.375 0.375 (9.5 mm) Vacuum Vessel 2.175 (55.2 mm) PFC’s Plasma Component Build Dimension Comparison PDR Build Reference Build VPI layer ? 2.961 1.50 (1.0 insulation + 0.25 gap + 0.188 VV tol + 0.06 MC tol) 0.388 1.0 0.787 The clamp is .125” thicker but a large corner radii HELPS the spool assembly

  7. ProE clearance study results (this took a 2 hr run!) 1.060” low side The two servos driving the spool are not properly adjusted to arrive at a maximum clearance value (see next slide).

  8. Servo’s can be adjusted to obtain an average minimum clearance of 1.56 inches between the MC and new PDR VV spool piece. 1.060” low side 1.564 average 2.068” high side

  9. Is 1.56” clearance OK? 0.5 Jim C needs 0.5” assembly gap at spool for final assembly 0.00 change VV spool tolerance to +0 / -.060 0.06 MC fabrication tolerance 1.00 Insulation 1.56” This will work! Per discussion with Brad, the VPI layer is under the clamps 2.961 1.75” Target clearance that initially was set for the MC to VV spacing in the spool region can be reduced if the spool tolerance is changed to +0 / -.06; or we can increase the clearance by going back to a 3/8” thick clamp.

More Related