1 / 5

4 / 13 / 0 9

Burrowes Renovation Project Schedule. Design Complete October 18, 2013 Primary Bid Period Oct. 28 – Nov. 22, 2013 Furniture relocation to swing space Nov. 1, 2013 – Jan. 2014 Occupant relocation to swing space Dec. 2, 2013 – Jan. 10, 2014 (planning / schedule / logistics)

nitesh
Download Presentation

4 / 13 / 0 9

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Burrowes Renovation Project Schedule • Design Complete October 18, 2013 • Primary Bid Period Oct. 28 – Nov. 22, 2013 • Furniture relocation to swing space Nov. 1, 2013 – Jan. 2014 • Occupant relocation to swing space Dec. 2, 2013 – Jan. 10, 2014 • (planning / schedule / logistics) • PDRB / Central Admin. review December 10, 2013 • BOT approval January 17, 2014 • Contract Award Jan. 20 – 31, 2014 • Construction start February 3, 2014 • Construction Complete December 2015 • Occupancy Dec. 2015 – Jan. 2016 4/13/09

  2. Swing Space Summary • Ritenour Building • Keller Building • Former Verizon Building • Marion Place • Allenway Building • 112 West Foster Avenue • Parking? 4/13/09

  3. Burrowes Renovation Project Construction area site plan - typical configuration for Feb. 2014 – Dec. 2015 (construction limits will increase May – August 2014 for utility work) Staging area Curtin Road Burrowes Building construction area Sackett Pollock Road Construction Access Route Willard Construction Logistics

  4. Burrowes Renovation Project Construction area site plan - typical configuration for Feb. 2014 – Dec. 2015 (construction limits will increase May – August 2014 for utility work) Paterno Library Construction trailer location Contractor Staging Area Davey Lab Pond Lab Burrowes Oswald Tower Chandlee Lab Burrowes Construction Area

  5. Burrowes Renovation Project Construction area site plan: May – August 2014 (not all areas will be closed entire duration) Staging area Curtin Road Burrowes Building construction area Sackett Pollock Road Construction Access Route Willard Utility infrastructure improvements summer 2014 – Pattee Mall closed and brief closure of Pollock Road & Brown B Lot Construction Logistics

More Related