Status Report # 2 Commhut -Home Security Wire Protection System Team 7 Ronald, Robert, Orlando, Jaime An interfacing module to communicate with previously designed protective case. Overall Need and Design Milestones.

nibaw
Download Presentation

Overall Need and Design Milestones

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Status Report # 2Commhut -Home Security Wire Protection SystemTeam 7Ronald, Robert, Orlando, JaimeAn interfacing module to communicate with previously designed protective case.

  2. Overall Need and Design Milestones • OVERALL NEED: To protect the communication lines of home security systems by detecting intrusion. • DESIGN MILESTONES: • Develop Detailed Schematics for interface (On going) • Receive sample code and sample products from Mr. Poston (Mid February) • Understand and test the Development Board for the PIC Microcontroller (2/13/09) • Meet with Travis Poston for updates on UL certification and other business oriented happenings. (2/4/09)

  3. Completed Tasks • Team meeting to discuss the duties of each member and further discussion of the case. (1/29/09) • Ordered the basic parts needed to test the penetration and tampering of the case.(1/30/09) • Ordered two different back up power supplies to be used for the modem and PIC. (1/30/09)

  4. Pending/Ongoing Tasks • Develop Functional Code to link modem with microcontroller. • Test protective case in all possible environments it might encounter. • Develop comparator circuit to trigger on a change in current received from a damaged or removed case. • Speak with a mechanical engineer to develop several samples of the case and create the demonstration environment.

  5. Tasks to Begin Next Week • Begin building the project test site. (2/11/09) • Make three different testing models. (2/13/09) • Start building the website. (2/9/09) • Begin on the power phase including back up power. (2/13/09)

  6. CommHut Design Backup Analog DC Signal Roberto Rosas Orlando Pina Jaime Gomez Ron Barnes Back up Batteries 15% Backup Analog DC Signal Digital Sensor Output Penetration Sensor Digital Modem Activation Signal Magnetic Sensor Microcontroller Modem 20% 20% 15% Analog DC Signal Phone Line Communication Analog DC Signal AC/DC Converter 12% 40% Analog AC Signal Emergency Alert AC Power

  7. Current Schedule

  8. Desired Outcome