1 / 28

Project Management in Practice

Project Management in Practice. Allocating Resources to the Project. Outline:. Crashing a project Fast-Tracking a project Resource Loading Resource Leveling. Homework: 20 (omit e ) using MSP 21 (an AOA diagram may help!) by hand and Excel. Crashing A Project.

nevin
Download Presentation

Project Management in Practice

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project Management in Practice Allocating Resources to the Project

  2. Outline: • Crashing a project • Fast-Tracking a project • Resource Loading • Resource Leveling Homework: 20 (omit e) using MSP 21 (an AOA diagram may help!) by hand and Excel

  3. Crashing A Project c=6 f=8 a=7 d=4 b=6 g=5 e=9

  4. Ex: Table 6-1, Crashing A Project e=3 b=2 c=2 a=3 d=4

  5. Ex: Table 6-1, Crashing A Project e=3 b=2 c=2 a=3 d=4 e(-2) a(-1) d(-1) Dur 5 Alternatives: e(-2) d(-1), from incremental, Proj cost = 220+70+30=$300 e(-2) a(-1) d(-1), from original, Proj cost=120+70+40+30=$260

  6. Ex: Table 6-1, Crashing A Project e=3 1 b=2 c=2 a=3 2 d=4 3 Dur 4 Alternatives: e(-2) a(-1) d(-1), from incremental, d(-1), b(-1), Proj cost=260+30+60=$350 a,b,e fully crashed this is as far as we can go we cannot get the project duration under 4

  7. Ex: Table 6-1, Crashing A Project

  8. Table 6-1, Example (8 days, baseline) AOA 3 e3 b2 a3 2 1 c2 4 6 d4 5 Alternate Solution Method

  9. Crashing a Project Example (21 days, baseline) AOA c6 2 4 a6 f9 1 d7 6 b7 3 5 g7 e5

  10. Example (21 days, baseline) AOA c6 2 4 a6 f9 1 d7 6 b7 3 5 g7 e5

  11. Example (21 days, baseline) AOA Using Excel Solver c6 2 4 a6 J8 f9 B17 B19 1 J11 J6 d7 6 J9 J7 B21 b7 J12 J10 3 5 g7 e5 B18 B20

  12. Example (21 days, baseline) AOA AOA Event Time for a node: Time when all preceding activities are complete. Timewhen all preceding activities are complete. Max time of paths to node (if more than 1 path), or If one path to node, it is equal to the time to the node. Using Excel Solver c6 2 4 a6 J8 f9 B17 B19 1 J11 J6 d7 6 J9 J7 B21 b7 J12 J10 3 5 g7 e5 B18 B20

  13. Example (21 days, baseline) AOA Using Excel Solver

  14. Example (21 days, baseline) AOA Node Constraints: 2) 3) 4) 5) 6) Solution (amount to crash each activity) must be integer and >=0: Event Times must be >=0: Activity crash amount must be <= their max: Node 6 (all activities complete) must be <= Project Deadline: Using Excel Solver

  15. Example (21 days, baseline) AOA Using Excel Solver

  16. Project Cost versus Project Duration Example Cost Table $750 $650 $550 $470 $430 $400

  17. Fast-Tracking a Project c d h c d h

  18. Resource Loading • Amount of specific resources that are scheduled for use on specific activities or projects at specific times. • Usually a list or table.

  19. Resource Loading

  20. Resource Loading

  21. No Resource Loading 7 Day Work Week Format Gantt Chart Wizard Resource LevelingUnloaded d,e 5 7 7 13 e2 f6 0 5 5 7 a5 7 13 0 3 3 8 0 5 b3 c5 9 11 g2 3 6 6 11 11 13 5 9 d4 7 11

  22. Added Resources Added Resource Names to Gantt Resource Tab Clear Leveling (button) Resource LevelingLoaded, Unleveled 5 7 7 13 e2 f6 0 5 5 7 a5 7 13 0 3 3 8 0 5 b3 c5 9 11 g2 3 6 6 11 11 13 5 9 d4 7 11

  23. View, Gantt Chart, More Views Resource Usage View, Gantt Chart, More Views Resource Graph Resource LevelingLoaded. Unleveled

  24. Resource Tab Level All Used d’s (LS/LF) slack to avoid overloading of Amy Resource LevelingLoaded, Leveled 5 7 7 13 e2 f6 0 5 5 7 a5 7 13 0 3 3 8 0 5 b3 c5 11 13 g2 3 6 6 11 11 13 7 11 d4 7 11

  25. View tab, Gantt Chart, More Views Resource Usage Resource LevelingLoaded, Leveled

  26. Unleveled Resource LevelingSuppose activity c needed Sue instead of Gus?

  27. Leveled e finishes at 7, but f cannot start Sue is still busy on c Resource LevelingSuppose activity c needed Sue instead of Gus? 8 14 5 7 e2 f6 0 5 5 7 a5 7 13 8 14 0 3 3 8 0 5 b3 c5 11 13 g2 3 6 7 12 b cannot LF at time 7 because Joe is needed on e at time 6 12 14 7 11 d4 e cannot start at time 6 and finish at 8 because Amy is needed on task d at time 7 d cannot start until time 7 because Amy is not free 8 12

  28. Leveled Resource LevelingSuppose activity c needed Sue instead of Gus?

More Related