An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. THE PROJECT CYCLEandPROCUREMENT

  2. THE BANK’S LOAN PROCESSING CYCLE Country Assistant Strategy PROJECT IDENTIFICATION IMPLEMENTATION COMPLETION REPORT PROJECT PREPARATION PROJECT SUPERVISION PROJECT PRE-APPRAISAL/APPRAISAL LOAN APPROVAL SIGNING AND EFFECTIVENESS LOAN NEGOTIATIONS

  3. IDENTIFICATION PROCUREMENT ISSUES • Public sector procurement procedure/rules (Eligibility) - CPAR • Private construction, manufacturing industry and consultant participation • NGO, UN Agencies, Community Participation • Acceptability of National Bidding Procedures • Borrower Capacity • Institutional Setup • Strengthening Needs

  4. PROJECT PREPARATION • World Bank’s Assistance for Preparation • Procurement arrangements • Selection of procurement methods • Cost estimates and packaging • Procurement planning • Bidding Documents • Workshops/Training Seminars

  5. PROJECT PREPARATION ISSUES (contd.) • Other donors – their procurement procedures • Capacity Assessment of implementing agency(ies) and measures for strengthening (Operational Manual, Procurement Training, International Procurement Consultants, Project Launch Workshop)

  6. APPRAISAL • Procurement • Review of preparedness, cost estimates, procurement arrangements • Implementation schedule • Institutional • Capability to implement project • Training, staff needs

  7. APPRAISAL • Results • Project Appraisal Document (PAD) • Draft Legal Documents • Covenants • Agreements (Loan/Guarantee)

  8. PROJECT APPRAISAL DOCUMENT (PAD) • At Appraisal agreement reached with Borrower • Procurement arrangements • Procurement plans • Review procedures and thresholds • Procurement reporting and monitoring during implementation

  9. NEGOTIATIONS • Minutes of negotiations record relevant issues especially any understanding reached or changes in scope, thresholds for non-ICB and prior reviews, waivers, etc. • Finalize bidding and contract documents for first year

  10. NEGOTIATIONS • Ensure procurement Schedule 4 of Loan Agreement and Annex 6 of PAD reflect changes if any including thresholds • Issue GPN (Updated Annually)

  11. BOARD PRESENTATION • Board Presentation for Approval • Approved Project for Implementation

  12. IMPLEMENTATION ROLES AND RESPONSIBILITIES

  13. PROCUREMENT RELATIONSHIPS World Bank Loan/Credit Agreement Borrower Complaints Supplier Works Contractor Consultant • Prequalification/ • Expression of Interest • Bidding/Selection Documents • Contracts

  14. THE BANK’S ROLE • Lend for specific projects • Assist the Borrower • Provide information on projects • Sign Loan Agreement • Review Compliance with Loan Agreement • Supervise and monitor the process • Verify withdrawal applications • Address complaints

  15. BORROWER’S ROLE Responsible for Procurement • Prepare procurement plan • Prepare and issue bidding documents • Invite bids • Receive and evaluate bids/proposals • Award contracts • Implement

  16. BANK REVIEW PROCESS • PRIOR REVIEW • Procurement plan, institutional capacity • Advertising and procedures • Pre-qualification documents and evaluation results • Bidding documents • Bid evaluation reports • Contract • Contract Amendments • Procurement Supervision to ensure compliance • Post Review

  17. PROJECT EVALUATION • Implementation Completion Report • Borrower/Bank responsibility • Evaluations implementation performance of parties including procurement • Audit Report by Independent Bank Department (OED) • Procurement Audit

  18. PROJECT CYCLE PROCUREMENT • IDENTIFCATION Address unique procurement issues • PREPARATION Procurement plan capacity assessment • APPRAISAL Finalization of procurement plan; action plan based on capacity assessment and technical assistance; institutional arrangements • NEGOTIATIONS Agreement on Procurement arrangements in loan agreement • IMPLEMENATION Procurement of goods, works and services as per loan agreement • EVALUATION Address procurement results in implementation

  19. RESPONSIBILITIES BORROWER WORLD BANK Identification (Joint) Preparation (Borrower) Appraisal (World Bank) Negotiations (Joint) Board Approval (World Bank) Signing & Loan Effectiveness (Joint) Implementation (Bor.) Supervision (WB) Project Evaluation (Joint)