Control system overview hamid shoaee controls system manager
This presentation is the property of its rightful owner.
Sponsored Links
1 / 30

Control System Overview Hamid Shoaee Controls System Manager PowerPoint PPT Presentation


  • 51 Views
  • Uploaded on
  • Presentation posted in: General

Control System Overview Hamid Shoaee Controls System Manager. Injector control system commissioning & Support Linac/BC2 Controls installation status Plans for the remainder of e- Controls Summary. Accomplishments in the past six months. Providing ongoing support for the injector operation

Download Presentation

Control System Overview Hamid Shoaee Controls System Manager

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Control system overview hamid shoaee controls system manager

Control System OverviewHamid ShoaeeControls System Manager

  • Injector control system commissioning & Support

  • Linac/BC2 Controls installation status

  • Plans for the remainder of e- Controls

  • Summary


Accomplishments in the past six months

Accomplishments in the past six months

  • Providing ongoing support for the injector operation

    • New Software, as well as upgrades & enhancements

    • Commissioning of additional controls subsystems

  • Field installation of large amount of cable plant, networking, racks & electronics for BC2/Linac

  • Development of detailed plans for LTU, Undulator and E-Dump control system installation

  • Coordination of undulator control with ANL

  • Continuing the development of next generation applications software & feedback system


Continuing support for the injector controls

Continuing support for the Injector Controls

  • Ernest Williams heading software engineering including EPICS system

  • “Software Day” concept proved very productive

  • Commissioning of new applications software such the bunch length measurement, MATLAB based feedback system

  • Enhancement and troubleshooting of released software

  • Commissioning of additional diagnostics


The toroid charge monitoring system was successfully commissioned

The Toroid charge monitoring system was successfully commissioned


Absolute charge measurement with toroids

Absolute charge measurement with Toroids

  • Mean ratio of Toroid to BPM charge = 1.45


Laser systems image acquisition and steering feedback

PULNIX

8-bit 640x480

120 fps

CameraLink

Used for centroid feedback

Laser SystemsImage Acquisition and Steering Feedback


Synchronous acquisition to measure resolution

Simultaneous measurement of all BPMs

Fitted beam position versus measured yields resolution

2 microns

at 400 pC

Synchronous Acquisition to measure Resolution

S. Smith et al.


Scp orbit display of injector bpms epics and slc bpms on the same pulse

SCP orbit display of Injector BPMS (EPICS) and SLC BPMS on the same pulse


Bc1 chicane otr screen commissioned

BC1 Chicane OTR Screen commissioned

1 mm thick Al foil


Wire scanners

Wire Scanners

Direction of motion

Based on existing SLAC mechanical design (E. Bong)

Y

U

X

Updated EPICS controls interface

Pulse-by-pulse compensation of bunch charge and trajectory jitter


Electronics and data acquisition for bunch length monitor

collecting

mirror

Annular

mirror

Coh. Diffraction Radiation

+ Coh. Synchrotron Radiation

+ Coh. Edge radiation

Compressor chicane

Electronics and Data acquisition for Bunch Length Monitor

System design by J. Frisch and H. Loos

Filters & Detectors

External optics

vacuum

mirror


Control system overview hamid shoaee controls system manager

Longitudinal Feedback System Commissioned


Save and restore application phase 1

Save and Restore Application (phase 1)


Online model applications

Online Model Applications

“Launcher” for

Other programs

Model control

Beam-line

selector

Orbit data plot


Applications provided in matlab

Image Management

Bunch Length Measurement

Emittance and Energy Application

Applications provided in MATLAB


Llrf work completed since last review

LLRF Work Completed since last review

  • All remaining stations in the injector and L1 were built, programmed and installed:

    • Transverse cavity in L0

    • Phase cavity in L0 (alternative input source for laser phase feedback)

    • Phase cavity in L1 (diagnostic, no feedback)

    • Klystron phase & amplitude detectors (PAD) at 20-5, 20-6, 20-7, 20-8, 21-1 S-band and 21-2 X-band

  • Laser phase feedback enhancements


Control system overview hamid shoaee controls system manager

BC2, Linac Controls System Installation

LTU/DUMP

UNDULATOR

INJECTOR

LINAC/BC2

250 MeV

4.30 GeV

13.6 GeV

6 MeV

135 MeV

Linac-X

L =0.6 m

Linac-0

L =6 m

rf

gun

L0-a,b

Linac-1

L 9 m

Linac-2

L 330 m

Linac-3

L 550 m

25-1a

30-8c

21-3b

24-6d

...existing

linac

21-1

b,c,d

undulator

L =130 m

X

BC2

L 22 m

BC1

L 6 m

‘Wall region’

DL2

L =275 m

2008

2007 down, Sept-Nov

Operational

SLAC linac tunnel

research yard


Control system overview hamid shoaee controls system manager

LCLS Installation and Commissioning Time-Line

X-ray tunnel/FEH Install

Linac/BC2 Controls Install

LTU/Und/Dump

Controls Install

CD-4

(7/30/10)

FEE/NEH Install

S

O

N

D

J

F

M

A

M

J

J

A

S

O

N

D

J

F

M

A

M

J

J

A

S

O

N

D

J

F

M

A

M

2007

2008

2009

2010

PPS

PPS

LTU/Und Commissioning

Tunnel/FEH Commissioning

Linac/BC2 Commissioning

FEE/NEH Commissioning


Linac bc2 controls installation

Linac & BC2 Controls Installation

  • Detailed plans were in place Feb-March 2007

  • The scope includes

    • Adding new magnets including pulsed horizontal dipole magnet

    • Adding BPM, x-collimator, OTR screen

    • Extending the new timing system

    • Safety systems (MPS, BCS)

  • BC2 installation, similar scope to BC1

  • Very little engineering development

  • The biggest challenge has been meeting the schedule


Linac bc2 controls installation proceeding close to original schedule

Linac & BC2 Controls Installation proceeding close to original schedule

Controls Check out to start 11/7/07


Cable plant installations are nearing completion

Cable plant installations are nearing completion


Electronics racks have been installed in the field

Electronics Racks have been installed in the field


Bc2 linac controls checkout to start next week

BC2, Linac Controls checkout to start next week

  • All vacuum control equipment bench tested and loaded.

  • All network Switches, terminal servers, patch panels in place..


Undulator control

Undulator Control

  • Close collaboration between SLAC and ANL

  • Separate weekly video conferences on Controls, BPM, BLM (Beam Loss Monitor)

  • Participation by SLAC personnel in planning, coordination and testing at ANL

  • Cavity BPM tests successful, meet sped

  • Undulator motion control FDR in 2 weeks

  • Have a design for BLM with schedule for development


First beam tests of undulator cavity bpm at anl r lill

First beam tests of Undulator Cavity BPMat ANL (R. Lill)

Cavity BPM

undulator


Controls for ltu undulator e dump

Controls for LTU, Undulator, E-dump

BSY

550 m

emittance diagnostic and collimation

vertical bends

dumpline

horizontal bends

undulator


Controls for ltu undulator e dump1

Controls for LTU, Undulator, E-dump

  • Identification of cable plant is nearing completion and documented in CAPTAR

  • We have developed electronics rack profiles for nearly all systems

  • We have an installation plan which is being integrated with the over all 2008 schedule

  • The challenge is coordination with other installations


Developing detailed schedule for 2008 controls installation

Developing detailed schedule for 2008 Controls installation


Plans for the next six months

Plans for the Next Six Months

  • Complete the BC2 installation and support the commissioning effort

  • Develop detailed plans for LTU, Undulator installation

  • Make major progress on the next generation high level applications software


Conclusions

Conclusions

  • We have been providing ongoing support for the injector controls

  • The commissioning experience and the collaboration with physicists have been very effective in refining the systems

  • BC2/Linac Controls installation is proceeding well and close to the original schedule

  • We are developing detailed controls installation plans for the remainder of the e- regions

  • With the exception of a few systems, we are over the engineering curve, and the remaining challenge is maintaining the schedule


  • Login