MJC Measure E Bond Program College Wide Forum January 11, 2008. Facilities Master Plan Status. May 2007, First Draft of Master Plan Issued for review June 2007, Board Accepted Increment I Plan and Revised Measure E MJC Budget November 2007, Second Draft of Master Plan issued for review

Download Presentation

MJC Measure E Bond Program College Wide Forum January 11, 2008

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Mjc measure e bond program college wide forum january 11 2008

MJC Measure E Bond Program

College Wide Forum

January 11, 2008


Mjc measure e bond program college wide forum january 11 2008

Facilities Master Plan Status

  • May 2007, First Draft of Master Plan Issued for review

  • June 2007, Board Accepted Increment I Plan and Revised Measure E MJC Budget

  • November 2007, Second Draft of Master Plan issued for review

  • December- January 25, 2008- Review and Comment Period from College Community

  • February 6, 2008- Final presentation to Board with College Comments


Mjc measure e bond program college wide forum january 11 2008

Facilities Master Plan Status

What is approved?

  • Increment I Site Plans

  • Increment I Project Budgets

    What is currently in review?

  • The remainder of Volume I of the Facilities Master Plan

  • Volume 2 of the Facilities Master Plan


Mjc measure e bond program college wide forum january 11 2008

Board Approved Plan

  • Modesto Junior College – Overall


Mjc measure e bond program college wide forum january 11 2008

Board Approved Plan- West

  • Modesto Junior College – Overall


Mjc measure e bond program college wide forum january 11 2008

Board Approved Budgets

Board Approved Budgets

  • Agricultural Projects$24,800,000

  • Parking Structure$12,000,000

  • Allied Health$25,822,000

  • West Side Site$ 5,037,370

  • Science Comm. Ctr./GVM$70,000,000

  • Student Services$16,000,000

  • Loop Road- West Campus$ 5,000,000

  • Infrastructure- West$ 5,000,000

  • Turlock Site$ 937,185

  • Softball Complex$ 786,300

  • High Tech Center- (Science East)$16,000,000

  • Interim Housing- Founders$ 1,000,000

  • Founders Hall Modernization$12,000,000

  • Library/ LRC$ 6,145,145


Mjc measure e bond program college wide forum january 11 2008

East Campus Planning

  • Modesto Junior College – Overall


Mjc measure e bond program college wide forum january 11 2008

East Campus Planning

  • Modesto Junior College – Auditorium


Mjc measure e bond program college wide forum january 11 2008

East Campus Planning

  • Modesto Junior College – Student Services


Mjc measure e bond program college wide forum january 11 2008

East Campus Planning

  • Modesto Junior College – High Tech Center (existing Science Center East)


Mjc measure e bond program college wide forum january 11 2008

West Campus Planning

  • Modesto Junior College – Overall


Mjc measure e bond program college wide forum january 11 2008

West Campus Planning

  • Modesto Junior College – Science Quadrant


Mjc measure e bond program college wide forum january 11 2008

West Campus Planning

  • Modesto Junior College – Softball


Mjc measure e bond program college wide forum january 11 2008

West Campus Planning

  • Modesto Junior College – Ag Multi Use Pavilion


Mjc measure e bond program college wide forum january 11 2008

West Campus Planning

  • Modesto Junior College – Ag Housing


Mjc measure e bond program college wide forum january 11 2008

Facilities Master Plan Next Steps

  • Faculty and Staff Review of posted FMP, http://www.mjc.edu/news/Draft%20Master%20Plan%2012-07.pdf

  • Review and revision of the Facilities Master Plan

  • Written Response to all comments/ questions

  • February 6, 2008- Final presentation to Board with College Comments


Mjc measure e bond program college wide forum january 11 2008

Question and Answer

January 11, 2008