MJC Measure E Bond Program College Wide Forum January 11, 2008

Loading in 2 Seconds...

play fullscreen
1 / 17

MJC Measure E Bond Program College Wide Forum January 11, 2008 - PowerPoint PPT Presentation


  • 108 Views
  • Uploaded on

MJC Measure E Bond Program College Wide Forum January 11, 2008. Facilities Master Plan Status. May 2007, First Draft of Master Plan Issued for review June 2007, Board Accepted Increment I Plan and Revised Measure E MJC Budget November 2007, Second Draft of Master Plan issued for review

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' MJC Measure E Bond Program College Wide Forum January 11, 2008' - nayda-mckinney


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
slide1

MJC Measure E Bond Program

College Wide Forum

January 11, 2008

slide2

Facilities Master Plan Status

  • May 2007, First Draft of Master Plan Issued for review
  • June 2007, Board Accepted Increment I Plan and Revised Measure E MJC Budget
  • November 2007, Second Draft of Master Plan issued for review
  • December- January 25, 2008- Review and Comment Period from College Community
  • February 6, 2008- Final presentation to Board with College Comments
slide3

Facilities Master Plan Status

What is approved?

  • Increment I Site Plans
  • Increment I Project Budgets

What is currently in review?

  • The remainder of Volume I of the Facilities Master Plan
  • Volume 2 of the Facilities Master Plan
slide4

Board Approved Plan

  • Modesto Junior College – Overall
slide5

Board Approved Plan- West

  • Modesto Junior College – Overall
slide6

Board Approved Budgets

Board Approved Budgets

  • Agricultural Projects $24,800,000
  • Parking Structure $12,000,000
  • Allied Health $25,822,000
  • West Side Site $ 5,037,370
  • Science Comm. Ctr./GVM $70,000,000
  • Student Services $16,000,000
  • Loop Road- West Campus $ 5,000,000
  • Infrastructure- West $ 5,000,000
  • Turlock Site $ 937,185
  • Softball Complex $ 786,300
  • High Tech Center- (Science East) $16,000,000
  • Interim Housing- Founders $ 1,000,000
  • Founders Hall Modernization $12,000,000
  • Library/ LRC $ 6,145,145
slide7

East Campus Planning

  • Modesto Junior College – Overall
slide8

East Campus Planning

  • Modesto Junior College – Auditorium
slide9

East Campus Planning

  • Modesto Junior College – Student Services
slide10

East Campus Planning

  • Modesto Junior College – High Tech Center (existing Science Center East)
slide11

West Campus Planning

  • Modesto Junior College – Overall
slide12

West Campus Planning

  • Modesto Junior College – Science Quadrant
slide13

West Campus Planning

  • Modesto Junior College – Softball
slide14

West Campus Planning

  • Modesto Junior College – Ag Multi Use Pavilion
slide15

West Campus Planning

  • Modesto Junior College – Ag Housing
slide16

Facilities Master Plan Next Steps

  • Faculty and Staff Review of posted FMP, http://www.mjc.edu/news/Draft%20Master%20Plan%2012-07.pdf
  • Review and revision of the Facilities Master Plan
  • Written Response to all comments/ questions
  • February 6, 2008- Final presentation to Board with College Comments
slide17

Question and Answer

January 11, 2008