MJC Measure E Bond Program College Wide Forum January 11, 2008. Facilities Master Plan Status. May 2007, First Draft of Master Plan Issued for review June 2007, Board Accepted Increment I Plan and Revised Measure E MJC Budget November 2007, Second Draft of Master Plan issued for review

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' MJC Measure E Bond Program College Wide Forum January 11, 2008' - nayda-mckinney


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript

MJC Measure E Bond Program

College Wide Forum

January 11, 2008


Facilities Master Plan Status

  • May 2007, First Draft of Master Plan Issued for review

  • June 2007, Board Accepted Increment I Plan and Revised Measure E MJC Budget

  • November 2007, Second Draft of Master Plan issued for review

  • December- January 25, 2008- Review and Comment Period from College Community

  • February 6, 2008- Final presentation to Board with College Comments


Facilities Master Plan Status

What is approved?

  • Increment I Site Plans

  • Increment I Project Budgets

    What is currently in review?

  • The remainder of Volume I of the Facilities Master Plan

  • Volume 2 of the Facilities Master Plan


Board Approved Plan

  • Modesto Junior College – Overall


Board Approved Plan- West

  • Modesto Junior College – Overall


Board Approved Budgets

Board Approved Budgets

  • Agricultural Projects $24,800,000

  • Parking Structure $12,000,000

  • Allied Health $25,822,000

  • West Side Site $ 5,037,370

  • Science Comm. Ctr./GVM $70,000,000

  • Student Services $16,000,000

  • Loop Road- West Campus $ 5,000,000

  • Infrastructure- West $ 5,000,000

  • Turlock Site $ 937,185

  • Softball Complex $ 786,300

  • High Tech Center- (Science East) $16,000,000

  • Interim Housing- Founders $ 1,000,000

  • Founders Hall Modernization $12,000,000

  • Library/ LRC $ 6,145,145


East Campus Planning

  • Modesto Junior College – Overall


East Campus Planning

  • Modesto Junior College – Auditorium


East Campus Planning

  • Modesto Junior College – Student Services


East Campus Planning

  • Modesto Junior College – High Tech Center (existing Science Center East)


West Campus Planning

  • Modesto Junior College – Overall


West Campus Planning

  • Modesto Junior College – Science Quadrant


West Campus Planning

  • Modesto Junior College – Softball


West Campus Planning

  • Modesto Junior College – Ag Multi Use Pavilion


West Campus Planning

  • Modesto Junior College – Ag Housing


Facilities Master Plan Next Steps

  • Faculty and Staff Review of posted FMP, http://www.mjc.edu/news/Draft%20Master%20Plan%2012-07.pdf

  • Review and revision of the Facilities Master Plan

  • Written Response to all comments/ questions

  • February 6, 2008- Final presentation to Board with College Comments


Question and Answer

January 11, 2008


ad