1 / 31

Office of Science Project Review NCSX August 15-17, 2007 Cost and Schedule Ron Strykowsky

Office of Science Project Review NCSX August 15-17, 2007 Cost and Schedule Ron Strykowsky. Topics. Cost, Schedule and Contingency Development Process Basis and Assumptions Contingency Cost Summary Schedule Summary Cost Profile Manpower. Process of Establishing a new Project EAC.

naiara
Download Presentation

Office of Science Project Review NCSX August 15-17, 2007 Cost and Schedule Ron Strykowsky

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Office of Science Project Review NCSX August 15-17, 2007 Cost and Schedule Ron Strykowsky Office of Science Review August 15, 2007

  2. Topics • Cost, Schedule and Contingency Development Process • Basis and Assumptions • Contingency • Cost Summary • Schedule Summary • Cost Profile • Manpower Office of Science Review August 15, 2007

  3. Process of Establishing a new Project EAC • Developed Guidelines for Job Managers (realistic not best case) • Estimates Prepared • Independent Management Review (led by head of PPPL engineering)* • PU Estimating Workshop (May 1-4)* • Refined Estimating packages • Reformatted for consistency • Further Estimate review for completeness and realism • Estimate uncertainty and Risk* • Formally documented basis of estimate* • Updated overhead and labor rates • Prepared resource Loaded Schedule • Design evolution of critical scope (task forces) • Risk brainstorming meeting* • Contingency analysis process (probabilistic approach)* • Re-iterate Resource Loaded Schedule • June 4 PU Review* • Follow-up actions • Final Updates, Packaging, Documentation (signed WAF’s) • Statused through end of June (CPI = 1.2 and SPI = 1.03 for two months) • Office of Science Review August 15-17 *=NEW Office of Science Review August 15, 2007

  4. Refined Estimating packages (table 1 of 6) • Table 1 - Work Approval Form Package includes copy of the resource loaded schedule Office of Science Review August 15, 2007

  5. Refined Estimating packages (table 2 of 6) • Table 2 - Design Office of Science Review August 15, 2007

  6. Refined Estimating packages (table 3 of 6) Materials and Procurements Office of Science Review August 15, 2007

  7. Refined Estimating packages (table 4 of 6) Fabrication and Assembly Office of Science Review August 15, 2007

  8. Refined Estimating packages (table 5 of 6) Estimate Uncertainty and Risk Office of Science Review August 15, 2007

  9. Refined Estimating packages (table 6 of 6) Basis of estimate Office of Science Review August 15, 2007

  10. Key Planning Basis and Assumptions • ETC forward from May 1st, 2007 • Cost Incurred from April 1, 2003(MIE project inception) • MIE project scope only.(Excludes research preparations and conceptual design) • GPP and Infrastructure not part of MIE project.(Progress coordinated and tracked by Erik Perry) • BA constraints(FY07= $16.77FY08 = $15.9, FY09 = $18.56*) • Scope unchanged from current baseline • Institutional Overhead Rates • Standard work week 8hrs/day 5 days/ week (Exception coil winding, Field period assy (sta5 FPA#3), and Final Machine assy) • Holidays • Contingency Allocation by fiscal year(commensurate with risk & cost uncertainty) • Realistic task durations(anticipate manpower shortages & priorities) • Task durations - more detail on critical path and near term • * = assumed Office of Science Review August 15, 2007

  11. Cost Basis - Resource types and Rates • Resource Types, labor and overhead rates Non-Labor Resource Labor Skills (hourly rates) Overhead and escalation rates Office of Science Review August 15, 2007

  12. Contingency - Process • Structured process with support of consultant • Job Manager and Project Team input • Objective was to assess and analyze all areas of uncertainty and risk that might affect the cost and schedule estimates • Used Probabilistic Risk Analysis Techniques (Monte Carlo Analysis) • Recommend Contingency Allowances that provide 90% confidence level that proposed baseline will not be exceeded. • Project Manager Experience Office of Science Review August 15, 2007

  13. Contingency - Components Cost Schedule Estimate Uncertainty $ months + Risk $ months + Schedule (stretch-out) $ + Schedule Mitigation (i.e. 2nd shift) $ + Project Manager Experience $ Total $ Months Office of Science Review August 15, 2007

  14. Contingency – Estimate Uncertainty • Both cost estimates and schedule durations have inherent levels of uncertainty • Uncertainty is a direct result of degree of design maturity and the complexity of the elements involved – in effect, how much definition exists to provide a basis for the estimates • Uncertainty levels can be described in terms of ranges around the point estimates developed by Job Managers and the Project Management team • Used standard industry and DOE estimate classifications to describe individual job estimates • Used determination of design maturity and complexity to equate to estimate classification • Also solicited Job Manager opinions regarding expected range around estimates (+ or – some % of the estimate) Office of Science Review August 15, 2007

  15. Contingency – Estimate Uncertainty Basis for Estimate Ranges • Per AACEI Recommended Practice 18R-97, Cost Estimate Classification System – As Applied to Engineering, Procurement, and Construction in the Process Industries • Five classes of estimates with associated accuracy ranges, dependent on level of project development and definition and estimating techniques used • Equated the five estimate classes to a design maturity and complexity matrix for NCSX Estimate Uncertainty Matrix Office of Science Review August 15, 2007

  16. Contingency – Estimate Uncertainty Estimate Uncertainty Matrix by WBS ETC and Estimate Range Office of Science Review August 15, 2007

  17. Contingency – Estimate Uncertainty Cost Estimate Uncertainty • Established estimate range for each job using the Estimate Uncertainty Matrix • Also had Job Managers describe expected accuracy (as + and – % of base estimate) - as a check on Matrix • Used Monte Carlo Analysis to determine overall project cost probability profile - both approaches yielded similar results (adopted standard approach as conservative. ~1-2% higher than job mgrs) • Each job estimate was treated as an independent variable • Triangular Distributions • Base Estimate as Most Likely Value • Low End of Range as Minimum Value • High End of Range as 80% confidence level* Result = $8,036k * 20% chance that cost could be even higher than uncertainty matrix Office of Science Review August 15, 2007

  18. Contingency – Estimate Uncertainty Schedule Duration Uncertainty • Established estimate range only for Critical and Near Critical Path activities using same approach as for cost • Used Monte Carlo Analysis to determine overall project schedule probability profile • Each critical path activity treated as independent variable • Triangular Distributions • Base Estimate as Most Likely Value • Low End of Range as Minimum Value • High End of Range as 90% confidence level (higher than for costs since schedule workarounds may be possible) • Did not add schedule cont. for some activities (those that could be worked on second shift) – BUT added cost allowance for shift supervision, support and shift differential costs (schedule mitigation cost) Result = 7.9 months Office of Science Review August 15, 2007

  19. Contingency – Risk Risk Assessment and Analysis • Identified risks • Job Manager and Project Team Input and Brainstorming • Assessed Risks • Likelihood of Occurrence • Cost and Schedule Impact Ranges • Ranked risks to focus management attention and mitigation actions (Risk mitigation actions included in baseline estimates) • Used Monte Carlo Analysis model to assess probable residual impacts (after mitigation) on cost and schedule baseline • Process will continue – identification of additional risks and management of identified risks. Result = $1,282k and 3.8 months Office of Science Review August 15, 2007

  20. Contingency – Cost of Schedule Contingency Risk Assessment and Analysis • Cost impact of schedule contingency • Oversight/management cost = $202k/mo. • Cost impact of schedule mitigation by use of second shift • During field period assembly for add’l supervision, metrology, support crews = $64k/mo. Result = $2,347 Result = $355k Office of Science Review August 15, 2007

  21. Contingency – Project Manager’s Increment Additional contingency added to attain 27% cost contingency based upon; • Recent Experience with WX-7 • Recent NCSX experience • Undefined risk • “Unknown unknowns” • Adopt schedule contingency of 11 months Office of Science Review August 15, 2007

  22. Contingency – Results Cost Schedule Estimate Uncertainty $8,036 (16%) 7.8 + Risk $1,282 (3%) 3.8 + Schedule (stretch-out) $2,347 (5%) - + Schedule Mitigation (i.e. 2nd shift) $ 355 (1%) - + Project Manager Experience $1,711 Proposed Baseline Contingency = $ 13,731 (27%) 11 Months Office of Science Review August 15, 2007

  23. Contingency – Results Allocated by WBS Office of Science Review August 15, 2007

  24. Scheduling - Process • Based on deliverables and/or tasks provided by the job managers • Varied from resource loaded schedules to deliverables and resource estimate only • Established tasks, internal milestones (PDR’s, FDR’s, contract awards) • Task durations based on realistic resource loadings, crew sizes, # shifts • Logically linked • Non-critical path tasks scheduled with BA constraints with free float to critical path • Schedule iterated based on • Ongoing design evolutions causing estimates to vary • Contingency quantification exercises • Resource leveling exercises (techs, key engrs) Office of Science Review August 15, 2007

  25. Results – Preliminary Cost Office of Science Review August 15, 2007

  26. Results – Cost Profile • Contingency scheduled consistent with risks and uncertainties • Plan consistent with Funding Office of Science Review August 15, 2007

  27. Results – Preliminary Schedule (Summary) Office of Science Review August 15, 2007

  28. Results – Milestones Office of Science Review August 15, 2007

  29. Results – Prelim. Resource Loaded Schedule EXAMPLE Office of Science Review August 15, 2007

  30. Results – Manpower • Manpower requirements being satisfied • Future needs achievable Office of Science Review August 15, 2007

  31. SUMMARY • Project has followed a disciplined path for updating its cost and schedule estimates highlighted by; • Formal & consistent basis of estimate • Independent reviews by PPPL engineering and PU • Focus on center of the error bars (realistic) estimates from job managers • Project has followed a methodical process for quantifying cost as well as schedule contingency. • Probabilistic contingency methodology for cost and schedule estimate uncertainty • Probabilistic contingency methodology for quantifying cost and schedule risk • Initiated a formal risk registry that will be integrated into our work planning process • Project has produced a proposed baseline cost estimate backed-up by a resource loaded schedule and detailed estimate basis. Office of Science Review August 15, 2007

More Related