An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. A New Building Data Center Upgrade capacity and technology step 2011 – May the 4 th– Hepix spring meeting Darmstadt (de) Pascal Trouvé (Facility Manager CC IN2P3)

  2. Summary : • Latest improvements of the current computing room • New computing room - Project scope • New Building – New architecture • Technical commissioning • Virtual tour • Technical data & figures • On going projects • Technical infrastructures phase II • Electrical power supply challenge • Future development project Pascal.trouve@cc.inp3.fr Hepix Spring Meeting - Darmstadt - Mai 4 th 2011

  3. Latest improvements of the computing room • POWER • New transformers have been installed (01/2010) : 3 X 1 MVA • Diesel generator (1.1 MVA) • Second electrical low voltage master distribution panel installed (one dedicated for Operation power [racks and cooling], one dedicated to infrastructure power) • Reactive energy compensation panel ( 4 capacitors banks) - savings • 4 Power distribution panels replaced + Source Transfer Switch for critical Network racks installed • News batteries farm – sealed lead battery – cell watch system Pascal.trouve@cc.inp3.fr Hepix Spring Meeting - Darmstadt - Mai 4 th 2011v

  4. Last improvements of the computing room • COOLING : • A third cooling unit (600 kW) has been installed on roof top,1800 kW available • Cooling capacity is now maximum complying with environmental regulation • HAZARDS • News fire safety detection system and monitoring ( SSI/CMSI) • New extinguishers fleet and reviewed lay out • INFRASTRUCTURE • High density confined racks standardization • InRow air-conditioning racks • PDUs suited to equipment specifications, and monitored Pascal.trouve@cc.inp3.fr Hepix Spring Meeting - Darmstadt - Mai 4 th 2011

  5. IMPROVMENT INPUTS • POWER • No power distribution problems occurred over the last year • Better batteries back up capacity coupled with the GE • COOLING • Still not fully redundant (short of 1600 kW) on the existing computing room • No cooling issues over the last summer, redundancy will be reached with the new computing room commissioning • HAZARDS • Better fire safety with modern fire detection system • Decrease of battery’s Hydrogen Hazard with sealed technology • INFRASTRUCTURE • Better global efficiency and sustainability • Higher general density Pascal.trouve@cc.inp3.fr Hepix Spring Meeting - Darmstadt - Mai 4 th 2011

  6. Power exemplification New aeros on roof top 2 New chillers unit Pascal.trouve@cc.inp3.fr Hepix Spring Meeting - Darmstadt - Mai 4 th 2011

  7. Confinement and Water cooled racks  confinement All the new hardware is installed in “confined racks”, including disks InRaws cooled racks Pascal.trouve@cc.inp3.fr Hepix Spring Meeting - Darmstadt - Mai 4 th 2011

  8. Project scope New computing room • The identified needs : • ~ 60 users groups increased demand • Meet LHC’s requirements • To meet the planned upgrade of LHC • Important identified request for « astroparticules” research activity Pascal.trouve@cc.inp3.fr Hepix Spring Meeting - Darmstadt - Mai 4 th 2011

  9. Project scope - Evolution plan – new Target plan: 2011 50 racks 0.6 MW 2015 125 racks 1.5 MW 2019 216 racks 3.2 MW Total power 3 MW Total power 6 MW Total power 9 MW The new computing room is an extension of the existing computing room (3 MW power + cooling in 2011) Pascal.trouve@cc.inp3.fr Hepix Spring Meeting - Darmstadt - Mai 4 th 2011

  10. A careful hardware selection DELL 1U 1950b 3 GHz 16 GB Blades DELL E5540 (2.53 Ghz) 48 GB IBM iDataplex Intel 5430 LV – 2.66 GHz – 50 W 16 GB Dell C6100 X5650 – 2.66 GHz 72 GB Pascal.trouve@cc.inp3.fr Hepix Spring Meeting - Darmstadt - Mai 4 th 2011

  11. New Building – New architecture Pascal.trouve@cc.inp3.fr Hepix Spring Meeting - Darmstadt - Mai 5 th 2011

  12. Chilled water tank 30 m3 Chillerunits Special construction design – heavy load roof structure Cold Water pumps stations Heavy duty Elevator 3 tons load Dominique Boutigny

  13. Infrastructure design scope Fully confined architecture All the water pipes, electrical distribution and other services are routed from the ceiling Pascal.trouve@cc.inp3.fr Hepix Spring Meeting - Darmsatdt - Mai 4 th 2011

  14. New computing room • 3 levels of 850 Sq. Meters each [ machine room for 850 sq. meters and 2 technical levels including the roof top] + heavy load elevator • We adopted a simplified “Design and build procedure” (single company contracted) delivered the building within18 months • Due to budget constraints the new computer room start with a limited technical infrastructure, but has a modular design that allowed scalable upgrades • First years, room dedicated to worker nodes only • Chilled water and electricity distribution and back up, technical rooms are designed for the 2019 target value Pascal.trouve@cc.inp3.fr Hepix Spring Meeting - Darmstadt - Mai 5 th 2011

  15. The New Data Center Building Setting up of a new building live ! • 12 months construction work • >= 630 tons of concrete • >= 70 tons of steel framework Building work started end of April 2010 Targeted delivery date targeted February 1st 2011 Final delivery date : March 14 th 2011 Technical commissioning : undergoing Go live production ~ Mai 24 th 2011 Pascal.trouve@cc.inp3.fr Hepix Spring Meeting - Darmstadt - Mai 4 th 2011

  16. Virtual Tour Computing room phase I 24 APC racks : InRaw 20 KW each Confined + workers + 2 Penduit racks with Nexus + switch Cisco To be completed by end of year : 26 APC racks InRaw 20 KW and fully confined area Still 600 sqr meters available …… Pascal.trouve@cc.inp3.fr Hepix Spring Meeting - Darmstadt - Mai 4 th 2011

  17. Technical equipment and installation on roof top • 2 Chillers units 800 KW each • Chilled water tank 30 tons – 30 min back up • Insulated piping and electrical tracing • Spare place for future upgrades Pascal.trouve@cc.inp3.fr Hepix Spring Meeting - Darmstadt - Mai 5 th 2011

  18. Power Distribution • 2 UPS Galaxy 7000 – 600 KVa • Main Switch board 2 MW • Redundant Air cooling unit • Fire protection • “Vesda” permanent detection • Conventional fire detection system level one • Sprinkler (automatic water extinguisher system) level 2 • Monitoring Pascal.trouve@cc.inp3.fr Hepix Spring Meeting - Darmstdt - Mai 4 th 2011

  19. Power distribution structure Cellules HTA N 630 kVA N 1 000 kVA N+1 800 kVA N+1 1 000 kVA TGBT Workers 2 400 kVA TGBT UPS critiques + services 2 500 kVA TGBT UPS critiques 400 kVA N 600 kVA N+1 600 kVA N 200 kVA N Modules clim N Modules clim Critiques N x (1+1/5) Modules clim Services N Modules clim N+1 800 kW N N N N Workers Services 574 kW HQ 600 kW HQ N+1 800 kW Critics 115 kW HQ Pascal.trouve@cc.inp3.fr Hepix Spring Meeting - Darmstadt - Mai 4 th 2011

  20. On going projects Phase II • Additional Equipment & facilities • Additional power transformer • Third chiller unit 400 KW • Second Batteries farm • Piping and water pumps • Additional power switch boards Project launched to be delivered by end of October 2011 A “ready to plug in” for 50 more racks units …… Pascal.trouve@cc.inp3.fr Hepix Spring Meeting - Darmstadt - Mai 4 th 2011

  21. Main Electrical Supply redundancy project On going projects Final decision taken to face a new challenge In the first phase the electrical redundancy will be minimal 2011 - 1,7/ 6 MW 2013 – 1,95/ 4 MW 1,95 MW will be backed up by the power supplier 2016 -2019 - 4 / 9MW 4 MW will be guaranteed by the power supplier Pascal.trouve@cc.inp3.fr Hepix Spring Meeting - Darmstadt - Mai 4 th 2011

  22. Future Development project An office space was part of the original extension project but dropped due to budget limitation Project Re-formatted with new functionalities added Multimedia center Amphitheatre accessible to the public A “Hub” for fundamental research, University and public information Dedicated Training center Outreach center Very well perceived by the Region and the city community (Grand Lyon) Pascal.trouve@cc.inp3.fr Hepix Spring Meeting - Darmstadt - Mai 5 th 2011