An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CXC Manager’s Status Report Chandra Users’ Committee Meeting Roger J. Brissenden 25 January 2005

  2. Topics • Program Level Status • Program Management • Spacecraft • Mission Planning • Science Instruments and Calibration • OCC • Data Processing • CXCDS • CDO • Education and Outreach • Mission Metrics • Chandra Grant Awards CXC Status Report/CUC

  3. Program Level Status 6/30/04 – 1/25/05 • Program Management • Successfully passed the 5 year milestone on July 23, 2004! • CXC remained within budget for FY04 and expect FY05 costs to track to POP04 plan. HRC, ACIS & HETG PI subcontracts moved under SAO, 1 Oct 04. • Staffing: Martin Elvis resigned as Lead for Science Data System Planning, Jonathon McDowell appointed new Lead with Mike Wise (MIT) as Deputy. • Tom Aldcroft certified as 3rd Chandra Flight Director (replaces Rob Cameron). • Facilities: Draper Labs moving ahead with new Hill building attachment. ~1500 sf floor space to be lost to 7th floor including the conference room and 5 offices. ACIS room to be sacrificed to allow for new conference room to be built. ACIS Equipment has been relocated to the TST room. CXC Status Report/CUC

  4. CXC Status Report/CUC

  5. CXC Status Report/CUC

  6. ACIS Present 7th Floor Layout CXC Status Report/CUC

  7. Proposed7th Floor Modifications CXC Status Report/CUC

  8. Program Level Status 6/30/04 – 1/25/05 • Spacecraft • Continues to operate extremely well overall • OBC patch for SCS 101 and SCS 31. Modify 101 to contain all CPE patches; modify 31 to call 101 during eclipse ops, 8/23. Improved eclipse safemode transition. • Helium Channel replacement patch, 9/1, for use of HRC anti-coincidence shield data in place of EPHIN as radiation detector. 6 cases of EPHIN rail voltage anomaly due to high temperatures however no indication of performance degradation; plan to budget ~6 rail voltage drops per year. • Conducted ACA dark current calibration 9/9 and 12/24 – shows expected trend in warm pixel increase • Nominal ’04 summer and ’05 winter eclipse seasons, nominal Lunar Eclipse, 11/12 • Radiation events during ’04 eclipse season resulted in contingency commanding and 3 Normal Sun Mode (NSM) recoveries. • Uneventful Leonids passage 11/19 • Anomalies: Propulsion line cooling, EPHIN rail voltage, unexpected NSM transition CXC Status Report/CUC

  9. Program Level Status 6/30/04 – 1/25/05 • Mission Planning • Thermal heating and constraints starting to impact mission planning • 10 SCS 107 runs due to high radiation events (includes major event last week) • 7 load interrupt TOOs: Date Target Request 07/05/04 AXP 1048-5937 1 day 08/14/04 GRB 040812 3 days 08/31/04 XRF 040825 3 days 09/13/04 GRB 040912 3 days 10/06/04 GRB 041006 3 days 10/06/04 SGR 1806-20 3 days 12/13/04 BL 0520+675 1 day CXC Status Report/CUC

  10. Program Level Status 6/30/04 – 1/25/05 • Science Instruments and Calibration • Operating extremely well overall • ACIS bakeout decision postponed in Sept due to safety concern over use of abort heaters, and simulation questions over contaminant volatility • HRC anticoincidence shield rates show acceptable correlation with high energy EPHIN channel. Antico rates exceeded proposed threshold for prior radiation safing event during mission, i.e., a safe EPHIN alternative • 2004 Calibration Review held 10/25-10/26 • OCC • Linux Migration initial config. 10/4, test started 12/1, to ops 3-4/05 • DSN unexpected commanding, 9/11 Date Version Change 07/23/04 OFLS 11.0 Linux port 12/06/04 ONLS 3.10.6 Linux port; test fixes 12/06/04 OFLS 11.3 Linux port CXC Status Report/CUC

  11. Program Level Status 6/30/04 – 1/25/05 • Data Processing • Automatic processing is current; data delivery time averaged <4 days • Planning underway for Re-processing #3 • CXCDS Date Version Change 07/07/04 CIAO 3.1 Tools, data model, infrastructure 11/29/04 CXCDS 7.4 Automated V&V, MTA DB, AGASC 1.6 12/14/04 CXCDS 7.5 Cycle 7 support 12/15/03 CIAO 3.2 Tool updates (e.g., mkacisrmf), bug fixes • CalDB 2.28 released 8/11, 2.29 on 11/29, and 3.0 on 12/15 CXC Status Report/CUC

  12. Program Level Status 6/30/04 – 1/25/05 • GO and Fellows Program, CDO • Cycle 6 stage 2 cost review held 10/20, results sent to observers 11/1 • Cycle 6 EPO review held 10/20, results announced 11/16 • Cycle 7 CfP released on schedule 12/15 • Cycle 8 Fellows review held 1/19 • Other: Galaxies workshop 7/7, Fellows Symposium 10/13 • Education and Public Outreach • 14 Chandra press releases and 7 additional image releases made CXC Status Report/CUC

  13. Mission MetricsMUPS Fuel Usage CXC Status Report/CUC

  14. Mission Metrics (con’t) CXC Status Report/CUC

  15. Mission Metrics (con’t) Scheduled Observing Efficiency CXC Status Report/CUC

  16. Mission Metrics (con’t)Observing Efficiency CXC Status Report/CUC

  17. Data Delivery Effectiveness CXC Status Report/CUC

  18. Chandra Grant Awards CXC Status Report/CUC

  19. Chandra Grant Awards CXC Status Report/CUC

  20. Grant Award Efficiency CXC Status Report/CUC