En-Route Working Group Report Out. 18 Dec 2013. DCIT En-Route Documentation Production. Good progress on two packages TOC/IC Route modifications Deliveries Initial delivery: 28 Feb 2014 Detailed and synched to the level of the FAA Use Cases End-to-End documents (above two)

Download Presentation

En-Route Working Group Report Out

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


En route working group report out

En-Route Working GroupReport Out

18 Dec 2013


Dcit en route documentation production

DCIT En-Route Documentation Production

  • Good progress on two packages

    • TOC/IC

    • Route modifications

  • Deliveries

    • Initial delivery: 28 Feb 2014

      • Detailed and synched to the level of the FAA Use Cases

      • End-to-End documents (above two)

      • Too early for Flight Deck and SDD

    • Second delivery, detailed definitions

      • Detailed and synched to the level of FAA A-level specifications

      • Detailed messaging, route clearance generation, off-nominal cases, etc.

      • End-to-End documents, Flight Deck Guidance, SDD

      • 9/14: NSDA and Initial FAA Domestic En-route Services


En route trials

En-route Trials

  • Engineering trials, summer 2014, are useful

  • Eng Trials satisfy only a sub-set of the agreed DCIT objectives

  • Industry endorses the engineering trials, but would like to work with the Data Comm Program Office on further validation

    • Include extensibility in the trials (e.g. add TOC/IC for inter-center trials, both at the boundaries of NAS-domestic and inside NAS-domestic)

    • Further explore validation activities beyond engineering trials

      • Additional validation activities, defined in 1st half of 2014

      • Early IOC Key Site activites

      • Observing FAA objectives on managing requirements creep

      • Observing FAA objectives on no jeopardizing operational ERAM deployment through trials systems deployment(s)


Future work organization

Future work organization

  • Excellent progress on DCL end-to-end this last few meetings

  • With Operational DCL End-to-End getting to mature draft, need to re-establish WGs

    • Flight Deck to begin working FD Guidance Material from end-to-end

    • SIT to review Interface Requirements Document(s) and determine if SIDD needed

    • ATC and AOC working group needs TBD

    • Combined Working Group sessions to be added back, rather than combining this with the OMWG

    • We also are nearing the need for this in En-Route, so timing is just right

  • Allows OMWG to get back to more like the weekly telecons

    • Focused on operational trials management issues and direction

    • Participants focused on operational issues, not drafting and WG issues