1 / 49

The World According to Systems (And What it Means for You)

The World According to Systems (And What it Means for You). Presentation Overview. Systems Overview Background: Traction Power, Train Control, Communications, and Systemwide Electrical Conduit, Ductbanks, Cable Troughs & Pullboxes Niches, Stub-ups & Special Provisions

mostyn
Download Presentation

The World According to Systems (And What it Means for You)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The World According to Systems (And What it Means for You)

  2. Presentation Overview • Systems Overview • Background: Traction Power, Train Control, Communications, and Systemwide Electrical • Conduit, Ductbanks, Cable Troughs & Pullboxes • Niches, Stub-ups & Special Provisions • How This Affects You • Questions

  3. Systems Overview

  4. Systems Overview Fremont Milpitas San Jose Berryessa Aerial Montague Trench Hostetter Trench Dixon Landing Trench

  5. Systems Overview Fremont Milpitas San Jose Berryessa Aerial Montague Trench Hostetter Trench Dixon Landing Trench

  6. Systems Overview Fremont Milpitas San Jose S24 S26 S28 S40 S44 S50

  7. Systems Overview Fremont Milpitas San Jose S24 S26 S28 S40 S44 S50 SWA SKR SRR SME SHO SBE

  8. Systems Overview Fremont Milpitas San Jose S24 S26 S28 S40 S44 S50 SLP SRC SWA SKR SRR SME SHO SBE

  9. Systems Overview Fremont Milpitas San Jose S24 S26 S28 S40 S44 S50 SLP SRC SWA SKR SRR SME SHO SBE SXB SXC

  10. Systems Overview Fremont Milpitas San Jose S24 S26 S28 S40 S44 S50 SDL SLA SPD STZ SHR SLP SRC SWA SKR SRR SME SHO SBE SXB SXC

  11. Systems Overview Fremont Milpitas San Jose S24 S26 S28 S40 S44 S50 SDL SLA SPD STZ SHR SLP SRC SWA SKR SRR SME SHO SBE SXB SXC S25 S27 S29 S37 S45 S55 Interlockings

  12. Traction Power 115kV 115kV HVSS SRC HVSS SLP WSX SVBX 34.5kV Ductbank Traction Power… What makes Trains Go.

  13. Traction Power 115kV 115kV HVSS SRC HVSS SLP WSX SVBX 34.5kV Ductbank 34.5kV/FO Ductbank

  14. Traction Power 115kV 115kV HVSS SRC HVSS SLP WSX SVBX 34.5kV Ductbank

  15. Traction Power 115kV 115kV HVSS SRC HVSS SLP WSX SVBX 34.5kV Ductbank

  16. Traction Power 115kV 115kV HVSS SRC HVSS SLP WSX SVBX 34.5kV Ductbank SWA SKR SRR SME SHO SBE TPSS’s

  17. Traction Power 115kV 115kV HVSS SRC HVSS SLP WSX SVBX 34.5kV Ductbank SWA SKR SRR SME SHO SBE TPSS’s AC AC AC AC AC AC 1000V DC DC DC DC DC DC DC 1000V DC To Contact Rail

  18. Traction Power 115kV 115kV HVSS SRC HVSS SLP WSX SVBX 34.5kV Ductbank SWA SKR SRR SME SHO SBE AC AC AC AC AC AC TPSS’s DC DC DC DC DC DC 1000V DC DC Pos. Contact Rail Running Rail

  19. Traction Power 115kV 115kV HVSS SRC HVSS SLP WSX SVBX 34.5kV Ductbank SWA SKR SRR SME SHO SBE AC AC AC AC AC AC TPSS’s DC DC DC DC DC DC 1000V DC DC Pos. Contact Rail BART Train Car Running Rail Paddles

  20. Traction Power 115kV 115kV HVSS SRC HVSS SLP WSX SVBX 34.5kV Ductbank SWA SKR SRR SME SHO SBE AC AC AC AC AC AC TPSS’s DC DC DC DC DC DC 1000V DC DC Neg. DC Pos. Contact Rail BART Train Car Neg. Return Running Rail Paddles

  21. Traction Power

  22. Communications • Network • Unified Optical Network (UON) • Emergency Trip Stations (ETS) • Closed-Circuit Television (CCTV) • Access Control • Telephone • Public Address Systems (PA) • Supervisory Control and Data Acquisition (SCADA) • Radio • Railroad Intrusion Detection System (RIDS)

  23. Communications • Network • Unified Optical Network (UON) • Emergency Trip Stations (ETS) • Closed-Circuit Television (CCTV) • Access Control • Telephone • Public Address Systems (PA) • Supervisory Control and Data Acquisition • Radio • Railroad Intrusion Detection System (RIDS)

  24. Communications … backbone of the BART system. Network / UON

  25. Communications … backbone of the BART system. Network / UON

  26. Communications … backbone of the BART system. Network / UON 34.5kV FO UON Fiber E UON Fiber F

  27. Communications Railroad Intrusion Detection System (RIDS)

  28. Communications

  29. Automatic Train Control …They Drive Themselves Milpitas Station Berryessa Station TCH TCH TCH TCH S24 S26 S28 S40 S44 S50 SWA SKR SRR SME SHO SBE SSL

  30. Automatic Train Control

  31. Electrical • Think conduit, ground wire, & ground rods

  32. Food Break…

  33. Conduit Types & Bend Radii

  34. Cable Trough

  35. Cable Trough Constraints

  36. Ductbank Types & Constraints

  37. Pullbox/Splicebox/MH Req’s& Constraints

  38. Niche Req’s & Adjustment Constraints No Vertical Adjustments Permitted Conduit Stubups Must Match Niche Location

  39. Special Issues: SME

  40. Special Issues: SME

  41. Special Issues: SHO

  42. Sierra Lundy Tunnel • Design coordination

  43. HOW THIS AFFECTS YOU SSH

  44. Guideway At-Grade • Drainage coordination (w/ 34.5kV & cable trough) • Structures coordination (w/ 34.5kV & cable trough installation) • Be gentle (w/ stubups, trough & boxes) • When DC stubups go in, contact rail positioning is set

  45. Trench • Adjustments to crosswalks, niches, invert height, contact rail, and track forms will directly impact systems design & construction • Systems/Electrical conduit is everywhere, call before you pour. • We can adjust our routing, but end points are often fixed • High level of coordination required at trench limits, station ends, overcrossings, and SME & SHO • Niches and conduit must be properly aligned

  46. Aerial • Window cutouts are fixed • Sleeves in the structure have to be moved if contact rail design changes • Traction power, communications, and train control conduit will transfer from the aerial to the ground on the north and south aerial structure

  47. Wayside • Utility coordination • Precisely level, coordinated foundations are key

  48. Stations • We’re everywhere. • Guideway/Stations interfaces will be key

  49. Questions

More Related