Wlcg project status report
This presentation is the property of its rightful owner.
Sponsored Links
1 / 31

WLCG Project Status Report PowerPoint PPT Presentation

  • Uploaded on
  • Presentation posted in: General

WLCG Project Status Report. NEC 2009 September 2009. Introduction. The sub-title of this talk is “Grids step-up to a set of new records: Scale Testing for the Experiment Programme (STEP’09)” STEP’09 means different things to different people

Download Presentation

WLCG Project Status Report

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.

- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript

Wlcg project status report

WLCG Project Status Report

NEC 2009

September 2009



  • The sub-title of this talk is “Grids step-up to a set of new records: Scale Testing for the Experiment Programme (STEP’09)”

  • STEP’09 means different things to different people

    • A two week period during June 2009 when there was intense testing – particularly by ATLAS & CMS – of specific (overlapping) workflows

    • A several month period, starting around CHEP’09, and encompassing the above

  • I would like to “step back” and take a much wider viewpoint – with a reference to my earlier “HEP SSC” talk:

    • Are we ready to “successfully and efficiently exploit the scientific and discovery potential of the LHC”?

The challenge

“The Challenge”

  • This challenge was clearly posed by FabiolaGianotti during her CHEP 2004 plenary talk

  • “Fast forward” 3 years – to CHEP 2007 – when some people were asking whether it was wise to travel to Vancouver when the LHC startup was imminent

  • At that time we clearly had not tested key Use Cases – sometimes not even by individual experiments, let alone all experiments (and at all concerned sites) together

  • This led to the Common Computing Readiness Challenge (CCRC’08) which advanced the state of play significantly

    >> to CHEP’09 – “ready but there will be problems”

Ccrc 08


  • Once again, this was supposed to be a final production test prior to real collisions between accelerated beams in the LHC

  • It certainly raised the bar considerably – and much of our operations infrastructure was completed as a result of that exercise – but it still left some components untested

  • These were the focus of STEP’09

  • The bottom line: we were not fully ready for data in 2007 – nor even 2008. The impressive results must be considered in the light of this sobering thought

So what next

So What Next?

Whilst there is no doubt that the service has “stepped up” considerably since e.g. one year ago, can

We (providers) live with this level of service and the operations load that it generates?

The experiments live with this level of service and the problems that it causes? (Loss of useful work, significant additional work, …)

Where are wrt “the challenge” of CHEP 2004?

An aside

An Aside

Over the past few years there were a number of technical problems related to the LHC machine itself

For me, a particularly large slice of “humble pie” came with the “IT problem”

This was not about Indico being down or slow, or Twiki being inaccessible, it was about the (LHC) Inner Triplets

To many, the collaboration is perceived to be “LHC machine + detectors” – “computing” is either an afterthought or more likely not a thought at all!

Lhc experiments wlcg

LHC + Experiments + WLCG???

  • In reality, IT is needed from the very beginning – to design the machine, the detectors, to build and operate them...

  • And – by the way – there would today be no physics discovery without major computational, network and storage facilities

  • We call this (loosely) WLCG – as you know!

  • But the only way to get on the map is through the provision of reliable, stable, predictable services

  • And a service is determined as much by what happens when things go wrong as by the “trivial” situation of smooth running…

Step 09 service advances

STEP’09: Service Advances

  • For CCRC’08 we had to put in place new or upgraded service / operations infrastructure

    • Some elements were an evolution of what had been used for previous Data and Service challenges but key components were basically new

  • Not only did these prove their worth in CCRC’08 but basically no major changes have been needed to date

  • The operations infrastructure worked smoothly – sites were no longer in “hero” (unsustainable) mode – previously a major concern

  • Rather light-weight but collaborative procedures proved their worth

  • But most importantly, our ability to handle / recover from / circumvent even major disasters!

What has gone wrong

What Has Gone Wrong?

  • Loss of LHC OPN to US – cables cut by fishing trawler

    • This happened during an early Service Challenge and at the time we thought it was “unusual”

  • Loss of LHC OPN within Europe – construction work near Madrid, motorway construction between Zurich and Basle (you can check the GPS coordinates with Google Earth), Tsunami in Asia, fire in Taipei, tornadoes, hurricanes, collapse of machine room floor due to municipal construction underneath(!), bugs in tape robot firmware taking drives offline, human errors, major loss of data due to s/w bugs, …

  • Some of the above occurred during STEP’09 – but the exercise was still globally a success!

Wlcg project status report













Wlcg project status report













Step 09 what were the metrics

STEP’09: What Were The Metrics?

  • Those set by the experiments: based on the main “functional blocks” that Tier1s and Tier2s support

  • Primary (additional) Use Cases in STEP’09:

    • (Concurrent) reprocessing at Tier1s – including recall from tape

    • Analysis – primarily at Tier2s (except LHCb)

  • In addition, we set a single service / operations site metric, primarily aimed at the Tier1s (and Tier0)

  • Details:

    • ATLAS (logbook, p-m w/s), CMS (p-m), blogs

    • Daily minutes: week1, week2

    • WLCG Post-mortem workshop

Wlcg tier1 performance metrics points for discussion

WLCG Tier1 [ Performance ] Metrics~~~Points for Discussion

[email protected]


WLCG GDB, 8th July 2009

The perennial question

The Perennial Question

  • During this presentation and discussion we will attempt to sharpen and answer the question:

  • How can a Tier1 know that it is doing OK?

  • We will look at:

    • What we can (or do) measure (automatically);

    • What else is important – but harder to measure (at least today);

    • How to understand what “OK” really means…



  • In principle, we know what resources are pledged, can determine what are actually installed(?) and can measure what is currently being used;

  • If installed capacity is significantly(?) lower than pledged, this is an anomaly and site in question “is not doing ok”

  • But actual utilization may vary – and can even exceed – “available” capacity for a given VO (particularly CPU – less or unlikely for storage(?))

  • This should also be signaled as an anomaly to be understood (it is: poor utilization over prolonged periods impacts future funding, even if there are good reasons for it…)



  • Here we have extensive tests (OPS, VO) coupled with production use

    • A “test” can pass, which does not mean that experiment production is not (severely) impacted…)

    • Some things are simply not realistic or too expensive to test…

  • But again, significant anomalies should be identified and understood

  • Automatic testing is one measure: GGUS tickets another (# tickets, including alarm, time taken for their resolution)

    • This can no doubt be improved iteratively; additional tests / monitoring added (e.g. tape metrics)

  • A site which is “green”, has few or no tickets open for > days | weeks, and no “complaints” at operations meeting is doing ok, surely?

  • Can things be improved for reporting and long-term traceability? (expecting the answer YES)

The metrics

The Metrics…

  • For STEP’09 – as well as at other times – explicit metrics have been set against sites and for well defined activities

  • Can such metrics allow us to “roll-up” the previous issues into a single view?

  • If not, what is missing from what we currently do?

  • Is it realistic to expect experiments to set such targets:

    • During the initial period of data taking? (Will it be known at all what the “targets” actually are?)

    • In the longer “steady state” situation? Processing & reprocessing? MC production? Analysis??? (largely not T1s…)

  • Probable answer: only if it is useful for them to monitor their own production (which it should be..)

Wlcg project status report

WLCG Site Metrics

Critical service follow up

Critical Service Follow-up

  • Targets (not commitments) proposed for Tier0 services

    • Similar targets requested for Tier1s/Tier2s

    • Experience from first week of CCRC’08 suggests targets for problem resolution should not be too high (if ~achievable)

      • The MoU lists targets for responding to problems (12 hours for T1s)

    • Tier1s: 95% of problems resolved <1 working day ?

    • Tier2s: 90% of problems resolved < 1 working day ?

  • Post-mortem triggered when targets not met!

Ggus summary 2 weeks

GGUS summary (2 weeks)

What were the results

What Were The Results?

  • The good news first:

    • Most Tier1s and many of the Tier2s met – and in some cases exceeded by a significant margin – the targets that were set

  • In addition, this was done with reasonable operational load at the site level and with quite a high background of scheduled and unscheduled interventions and other problems – including 5 simultaneous LHC OPN fibre cuts!

  • Operationally, things went really rather well

    • Experiment operations – particularly ATLAS – overloaded

  • The not-so-good news:

    • Some Tier1s and Tier2s did not meet one or more of the targets



  • The results from Tier2s are somewhat more complex to analyse – an example this time from CMS:

    • Primary goal: use at least 50% of pledged T2 level for analysis

      • backfill ongoing analysis activity

      • go above 50% if possible

    • Preliminary results:

      • In aggregate: 88% of pledge was used. 14 sites with > 100%

      • 9 sites below 50%

  • The number of Tier2s is such that it does not make sense to go through each by name, however:

    • Need to understand primary causes for some sites to perform well and some to perform relatively badly

    • Some concerns on data access performance / data management in general at Tier2s: this is an area which has not been looked at in (sufficient?) detail

Summary of tier2s

Summary of Tier2s

  • Detailed reports written by a number of Tier2s

    • MC conclusion “solved since a long time” (Glasgow)

  • Also some numbers on specific tasks, e.g. GangaRobot

  • Some specific areas of concern (likely to grow IMHO)

    • Networking: internal bandwidth and/or external

    • Data access: aside from constraints above, concern that data access will met the load / requirements from heavy end-user analysis

    • “Efficiency” – # successful analysis jobs – varies from 94% down to 56% per (ATLAS) cloud, but >99% down to 0% (e.g. 13K jobs failed, 100 succeed) (error analysis also exists)

  • IMHO, the detailed summaries maintained by the experiments together with site reviews demonstrate that the process is under control, not withstanding concerns

Step key points

STEP key points

  • General:

    • Multi-VO aspects never tested before at this scale

    • Almost all sites participated successfully

    • CERN tape writing well above required level

    • Most Tier1s showed impressive operation

    • Demonstrated scale and sustainability of loads

      • Some limitations were seen; to be re-checked

    • OPN suffered double fibre cut! ... But continued and recovered...

    • Data rates well above required rates...

Ccrc 2008 vs step 2009

CCRC 2008 vs STEP 2009



2 weeks vs. 2 days

4 GB/sec vs. 1 GB/sec






  • Resolution of major problems with in-depth written reports

  • Site visits to Tier1s that gave problems during STEP’09 (at least DE-KIT & NL-T1) [ ASGC being setup for October? ]

  • Understanding of Tier2 successes and failures

  • Rerun of “STEP’09” – perhaps split into reprocessing and analysis before a “final” re-run – on timescale of September 2009 [ Actually done as a set of sub-tasks ]

  • Review of results prior to LHC restart

General conclusions

General Conclusions

  • STEP’09 was an extremely valuable exercise and we all learned a great deal!

  • Progress – again – has been significant

  • The WLCG operations procedures / meetings have proven their worth

  • Good progress since (see experiment talks) on understanding and resolving outstanding issues!

  • Overall, STEP’09 was a big step forward!

Outstanding issues concerns

Outstanding Issues & Concerns



  • We are probably ready for data taking and analysis and have a proven track record of resolving even major problems and / or handling major site downtimes in a way that lets production continue

  • Analysis will surely bring some new challenges to the table – not only the ones that we expect!

  • If funded, the HEP SSC and Service Deployment projects described this morning will help us get through the first years of LHC data taking

  • Expect some larger changes – particularly in the areas of storage and data handing – after that

  • Login