MFP – Installation using a Jack up Rig. Dr . Sanjaya Pillai, Business Head, GLND India, Aswathy Ezhampakkel, Sr . Naval Architect, GLND Qatar. History.

Download Presentation

MFP – Installation using a Jack up Rig

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Mfp installation using a jack up rig

MFP – Installation using a Jack up Rig

Dr. Sanjaya Pillai, Business Head, GLND India, Aswathy Ezhampakkel, Sr. Naval Architect, GLND Qatar


History

History

  • October 2006: NDC started operations in Mumbai by opening a project office to execute 4WPP & BCPB2 projects

  • 1stApril 2008: Noble Denton India Pvt Ltd established

  • January 2009: ISO 9001 certification awarded to Noble Denton India PvtLtd

  • April 2009 GL acquired Noble Denton

  • April 2008-May 2012: NDI executed many warranty projects.


Gl group business streams

GL Group Business Streams

  • GL NOBLE DENTON (OIL and GAS)

  • Advanced Engineering and Consulting

  • Marine Operations and Consulting

  • Technical Assurance

  • Design and Execution

  • GL MARINE (CLASS)

  • Classification Society

  • GL GARRAD HASSAN (RENEWABLES)

  • Renewables


Mfps definition

MFPs -Definition

BACKGROUND

1.Production wells on the verge of depletion, Additional wells can be drilled in the near vicinity if some marginal fields are available near the existing facilities.

  • Existing no. of Production wells is not sufficient to take care of increased flow. Additional wells needed for tapping the resources.

  • Marginal fields exploitation, Minimum facilities for feasibility considering other factors like cost, grouping of fields etc.

  • Concept of Minimum Facilities Platforms


Mfp installation

MFP - Installation

INSTALLATION PERSPECTIVES

  • Risk during Load-Out, Transportation and Installation

  • Reconsideration of Design Parameters

  • Safety during Installation

  • Size and Weight of the Structure Involved

  • Installation Methodology - innovative

  • Identify Marine Procedures

  • Reasonable risk from Owners/Underwriter’s points of view


Installation a case study

Installation – A Case Study

INSTALLATION of MFP – A Case Study

  • Operator – Middle East

  • Feasibility Study for Installation with a Rig

  • Additional wells needed for accommodating increased oil flow => adjacent additional platform with Minimum Facilities proposed

  • Input from various contractors taken during feasibility study

  • Feasibility Study confirmed after thorough evaluation of feasibility of Installation

  • GLND developed Installation Procedures and Marine Procedures


Installation a case study1

Installation – A Case Study

INSTALLATION of MFP – A Case Study - Design considerations

  • Deciding parameters

    • Rig Capacity of Lift

    • Rig Reach of Lift

  • Safety of Existing Platform

    • Installation Methods

    • Risk Assessment and Mitigation


Installation a case study2

Installation – A Case Study

INSTALLATION of MFP – A Case Study - Steps

  • Position the Rig near to the existing platform

  • Cantilever extended, Install Pin pile

  • Template loaded, sea-fastened and arrives at the location

  • Template Lift with Rig, Lowered and Placed on the Bottom

  • Install Legs(Conductors)/ Work Platforms

  • Topside Lift after Rigging inspection

  • Final adjustment using tugger winches

  • Positioning Levelling and welding the Topside on the legs


Mfp installation using a jack up rig

MFP – Installation Perspectives

Step #1, #2

Position the Rig near to the existing platform, Cantilever extended, Install Pin pile

Outreach -45’

Port/Sbd- 14.5’


Mfp installation using a jack up rig

MFP – Installation Perspectives

Step #3

Template loaded, sea-fastened and arrives at the location

No welding to the deck (timber)


Mfp installation using a jack up rig

MFP – Installation Perspectives

Step #4

Template Lift with Rig, Lowered and Placed on the Bottom

Mooring:

Bow -1

Stern - 2


Mfp installation using a jack up rig

MFP – Installation Perspectives

Step #5

Install all other Legs/ Work Platforms

Cutting at the desired elevation


Mfp installation using a jack up rig

MFP – Installation Perspectives

Step #6

Topside Lift after Rigging inspection

Crash rail

Air gap


Mfp installation using a jack up rig

MFP – Installation Perspectives

Step #7

Final adjustment using tuggerwinches

Positioning is a delicate job


Mfp installation using a jack up rig

MFP – Installation Perspectives

Step #8

Positioning, Levelling and welding the Topside on the legs


Installation a case study3

Installation – A Case Study

INSTALLATION of MFP – A Case Study - Issues

  • Rig Limitations – DAF to be considered

  • Weather during Installation – very important

  • Positioning of the Rig – rig move and soil assessment

  • Placing of the Topside simultaneously on conductors/legs

  • Tugger Line and Lifting Gear – to be designed

  • Leveling of the Platform – suit to site


Installation a case study4

Installation – A Case Study

SUMMARY

  • Design Parameters - Reconsideration

  • Risk Assessment and Risk Mitigation

  • Installation Methodology – Innovation

  • Custom made procedures/design


Mfp installation using a jack up rig

Thank you for your attention!

For further information visit www.gl-nobledenton.com