Organics Waste Processing Facility Construction Progress Update January 17, 2011

Loading in 2 Seconds...

play fullscreen
1 / 8

Organics Waste Processing Facility Construction Progress Update January 17, 2011 - PowerPoint PPT Presentation


  • 107 Views
  • Uploaded on

Organics Waste Processing Facility Construction Progress Update January 17, 2011. Organics Waste Processing Facility Construction Progress Update January 17, 2011. T tunnel wall along Gridline 6 and V with cold weather protection.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' Organics Waste Processing Facility Construction Progress Update January 17, 2011' - mitch


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
slide2

Organics Waste Processing Facility Construction Progress UpdateJanuary 17, 2011

T tunnel wall along Gridline 6 and V with cold weather protection

slide3

Organics Waste Processing Facility Construction Progress UpdateJanuary 17, 2011

Veneer brick installation for Administration Building

slide4

Organics Waste Processing Facility Construction Progress UpdateJanuary 17, 2011

Scaffolds for brick veneer installation around Administration Building

slide5

Organics Waste Processing Facility Construction Progress UpdateJanuary 17, 2011

Administration building taking shape

slide6

Organics Waste Processing Facility Construction Progress UpdateJanuary 17, 2011

Frame installation for pre-engineered building over tunnels begins

slide7

Organics Waste Processing Facility Construction Progress UpdateJanuary 17, 2011

Frame installation for pre-engineered building over tunnels

slide8

Organics Waste Processing Facility Construction Progress UpdateJanuary 17, 2011

Frame installation for pre-engineered building over tunnels nearly completed