Particles and Fields Package Weekly Team Meeting, SSL June 1 2010. Dave Curtis, PFP PM. PFP Peer Reviews. All peer reviews completed successfully Next step Peer review leads need to assign people to respond to actions Actions and recommendations should get some kind of response

Download Presentation

Particles and Fields Package Weekly Team Meeting, SSL June 1 2010

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Particles and fields package weekly team meeting ssl june 1 2010

Particles and Fields Package

Weekly Team Meeting, SSL

June 1 2010

Dave Curtis, PFP PM


Pfp peer reviews

PFP Peer Reviews

All peer reviews completed successfully

Next step

Peer review leads need to assign people to respond to actions

Actions and recommendations should get some kind of response

Responses to Actions (not recommendations) shall be provided to the review chair before IPDR (preferably before we make charts)

Better yet is to get concurrence from chair before IPDR.

Need to present peer review results at IPDR

List of actions with status

Expanded chart for contentious actions


Peer review rfa summary

Peer Review RFA Summary

Recommendations closed by concurrence of review lead, PFP PM

Actions closed by concurrence of Review Chair

Details of actions in following presentations


Documents

Documents

Part of preparing for PDR includes delivering documents to MIS, typically 30 days before PDR

Entrance criteria for PDR being tracked by the review team

Many documents have been submitted

MAIP, RMP, CMP, SEMP, WBS, FMDD, PHA, FMEA, LLL, SWR, SDP, MPL, PIL

Some need to be delivered shortly

Instrument specifications (last call for changes)

Drawing Tree (Daniele compiling)

Verification Plans, I&T Plans (Curtis)

SAR (Curtis)

IPDR package (10 days before IPDR)


Pdr agenda day 1

PDR Agenda, Day 1

Minor reordering since last week

Presentation File Names


Pdr agenda day 2 3

PDR Agenda, Day 2,3


Gsfc std 1001 coverage

GSFC-STD-1001 Coverage

GSFC-STD-1001A describes what should be in reviews including PDR

Author of GSFC-STD-1001A is on our review team

Appendix C-2 of GSFC-STD-1001A lists the evaluation factors for an ‘element PDR’ such as our IPDR

I have extracted that appendix and allocated those criteria to presentations (see last week’s team meeting presentation)


Pfp mass

PFP Mass

Final call for changes so we can all be on the same page for PDR


Pfp power

PFP Power

Need to reallocate NTE amongst instruments to level margin

Liens:

Expect to need operational heat during eclipse

None allocated for most instruments; amount needed pending thermal analysis

Preliminary estimates included for MAG and EUV