Activities status and plan for the week
Download
1 / 4

Activities Status and Plan for the week - PowerPoint PPT Presentation


  • 67 Views
  • Uploaded on

Activities Status and Plan for the week. D. Giugni / INFN Milano. Harnesses Stacking Status. Set 4 General Set assigned to C78 Status Done EXCEPT OSP LV STACK Open Issues OSP LV STACK to fix. Set 5 General Set assigned to C56 Status Done EXCEPT OSP LV STACK Open Issues

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' Activities Status and Plan for the week' - mikel


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
Activities status and plan for the week

Activities Status and Plan for the week

D. Giugni / INFN Milano

Monday Meeting 2011-01-30


Harnesses stacking status
Harnesses Stacking Status

  • Set 4

    • General

      • Set assigned to C78

    • Status

      • Done EXCEPT OSP LV STACK

    • Open Issues

      • OSP LV STACK to fix.

  • Set 5

    • General

      • Set assigned to C56

    • Status

      • Done EXCEPT OSP LV STACK

    • Open Issues

      • Need testing

  • Set 6

    • General : only pre-tested

  • Set 1 C34 (X0)

    • Open Issues

      • Need to repair the bend of the OSP stack at the tapes

  • Set 2

    • General

      • Set has NOT been assigned yet.

      • Decided to put in hold: too many faults.

    • Status

      • All usable Harnesses “Prepared” and tested

    • Open Issues

      • Need several repairs

  • Set 3

    • General

      • Set assigned to C12

    • Status

      • done

    • Open Issues

      • OSP LV to stack. Problems in the wire bends

Monday Meeting 2011-01-30


Soldering
Soldering

Agreed sequence :

  • ISP C34 (X0) almost finished

  • ISP C12 (X1) in the pipe line

  • ISP C78 (X2) Ready to go

  • ISP C56 (X3) Ready to go (but needs another week for training the last soldering team)

Monday Meeting 2011-01-30


Schedule for this week
Schedule for this week

  • Stacking

    • Keep going with SET 6 and the others.

    • Activity will be slowed down by 50% due to the ELCO connector pins removal (not quite an issue)

  • Corrugated panel bonding:

    Delay in the SLA parts. 2 panels done for the C34 already assembled in the panel.

    • Restart the production this week as soon as parts are delivered (parts have been shipped).

  • BackBone Not at high priority this week.

  • PP0 boards stiffening and Alu Block bonding

    Done C5, C6, C7 and C8 . C Side has been finished.

    Actually we are not working on the OSP.

    • Priority on the ISP A side boards. Not foreseen this week for stiffening.

  • Soldering

    • Keep going with the ISP C34 (X0) HV routing.

    • Load the C12 PS  PS soldering

    • Kick off the C78  HV-NTC

  • Post Soldering Assembly Final Assembly Trial (X-1)

    • Low priority in loading the OSP 3 and ISP 3 on the trial . Needs ER_bundles!!