An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Capital Cost Estimating@ Fluor June 2006 Arjen Blok Chief estimator Haarlem

  2. Fluor Overview • Publicly owned engineering, procurement, construction and maintenance company • 2005 revenues of $13.2 billion • 2005 new awards: $12.5 billion • 2005 backlog: $14.9 billion • 37,000 employees worldwide • Offices in more than 25 countries • Major European offices: • Haarlem, the Netherlands; • Madrid, Spain; • Camberley,UK; and • Gliwice, Poland. • Consistently one of the world’s safest contractors

  3. Presentation purpose • EPC contractors current outlook • EPC contractors view on Estimating • Integration of Estimating tools in engineering environment • Aspen Kbase solution

  4. EAME Market Summary • Strong UpstreamOil and gas markets • Drivers: high prices, reserve replacement, energy supply security, product demand • Thriving LNG and gas processing sector • Complex projects drive increased client capex spending • Up to $50 billion in new contracts expected in ME alone in 2006 • National oil companies less reliant on international oil majors • Refining upgrades/capacity expansions, new plants in Middle East • Fluor is pursuing about $20bn in regional prospects • Market focus shifts from clean fuels to conversion • Gas-to-Liquids, Integrated Gasification Combined Cycle • Regulatory environment drives European Union biofuels projects • New Petrochems/Chemicals complexes, primarily in Middle East • Chemical/plastics opportunities developing • Chemical markets may be peaking, downturn expected 2009 - 2011

  5. EAME Market Summary • Power Generators focus on capacity shortages / fuel supply • Carbon Agenda drives environmental upgrades, emissions trading • European Union market deregulation, M&A activity • Nuclear new-build debate • Market risks • Shortage of skilled personnel • Geopolitics / political instability • Feedstock / material costs • Regulatory / environmental issues • Contractor Issues • Record backlog levels resulting in veryselective bidding • More lump sum conversion contracts • Pressure on staffing, use of full service low cost engineering centres • Supply chain management, global procurement to contain equipment/ material costs

  6. Impact on Operations • Selectivity • Business risk assessment • Early indication of cost for investment and pursuit decisions • Lump sum conversion contracts • Transparency and accuracy of estimates • Joint development • High focus on contingencies and allowances • Estimate centric execution / Change management • Pressure on staffing  dispersed execution  interfaces • Growth of GEC component, multiple offices • Partnering • National companies • Supply chain management, global procurement for equip. & materials • Price instability & risk • Out of sequence engineering • Increased focus on quantities • Quality • Increased audits, inspection • Reliability is key

  7. EPC contractor view on Estimating • Why preparing estimates • Bidding work • EPCm Services • EPC • Service in project development • Support investment decisions • Project execution basis • Capex Cost only • Engineering • Procurement equipment & materials • Prefabrication • Erection (up to Mechanical Completion)

  8. EPC contractor view on Cap Cost Estimating • Fluor follows AACE classification rules 18R-97

  9. EPC contractor view on Cap Cost Estimating • Estimating tool = AspenTech Kbase • Design estimating tool, provided with • Scope & Construction models, Design rules & Engineering rules of thumb => Quantities • Pricing & labour basis • Estimating scope defined by available engineering data • Equipment data, Flow sheets , Plot Plan, etc • The earlier the estimate, the more use of Kbase technology • Class 4 & 3 • Class 2 • Replace Kbase models by BE info & execution plan

  10. Integrated Design Build SM (IDB) Data Ownership Single Data Entry Data Release Change Notification Data Status History Trail

  11. General specifications Area Information Equipment data Utility Systems P&ID information Plot plan information Estimating data flow Kbase

  12. Connection IDB -> Kbase • AspenTech solution: API • Application Programming Interfaces • Allows automated data sharing in a controlled manner • Considerations • Quality of data • Ownership of data • Timing / availability of data • Status of data • Revision of data • Timing of activities for engineering disciplines is influenced by estimating

  13. Area Manager Aspen Zyqad Equipment API Utility Systems API Electronic Equipment List MHCD Bulk API 3D Model INTOOLS Piping Manual MTO Instrument Manual MTO Fluor’s API’s Kbase

  14. Equipment API • Obtain Equipment data from Kbase to Excel • Import data from Excel file back to Kbase • Advantages • More simple input of equipment data • Link from Kbase to any obtained excel equipment list • Possibility to make use of applicable data from other electronic sources such as Aspen Zyqad Aspen Zyqad Kbase EquipmentAPI Electronic Equipment List MHCD

  15. Conclusion • Market demands us to do it better, cheaper, faster => Automation • Estimating has great desire to connect to Engineering • ! Controlled manner, considering status of project definition • Engineering should have desire to connect to Estimating • Estimate is Base Line Document • Kbase API’s provide great capabilities • ? Can ISO 15926-4 help further developments, considering : • Estimating (in)dependency • Accuracy of an estimate is not driven by details

  16. Capital Cost Estimating@ FluorThank you for you attention June 2006 Arjen Blok Chief estimator Haarlem