1 / 36

The MSC-CI section

The MSC-CI section. Agenda : LHC             Quick status of LHC             NC status + cryomagnet coordination             Overview of ICIT work             Components storage             Components procurements             Section support to MP3 and patrol

Download Presentation

The MSC-CI section

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The MSC-CI section Agenda : LHC             Quick status of LHC             NC status + cryomagnet coordination             Overview of ICIT work             Components storage             Components procurements             Section support to MP3 and patrol             SMI2 status and proposal for storage             X-ray tomography and its mock-up             Possible/Likely interventions for future shutdown: Section participation to new inner triplet             Cryostats - French collaboration             QDXS             Interconnections Cryogenics collimator SPL CERN/France collaboration 29/10/2009 JPh Tock MSC-CI

  2. LHC :           Quick status of LHC The MSC-CI section All sectors < 2 K Leak in 3-4 !! Powering steps : 72 %            Successful injection test Start 2nd half of November at reduced energy (2 kA ; 1.18 TeV)  29/10/2009 JPh Tock MSC-CI

  3. The MSC-CI section LHC     NC status + cryomagnet coordination (Role to be officialised ?)            MB, SSS and IC NCR’s status in LHC • After last interconnection’s closure there were still many open NCR’s: • MB: 215 • SSS: 438 • IC: 17 • The aim of this job is to point out the REAL NCR’s that shall be treated during next shutdown, and to CLOSE all solved NCR’s. 29/10/2009 JPh Tock MSC-CI

  4. The MSC-CI section LHC     NC status + cryomagnet coordination       MB, SSS and IC NCR’s status in LHC • After a BIG work of sorting and treating, the NCR’s still open are as follows: • MB: 63 (152 solved) • SSS: 55 (383 solved) • IC: 4 (13 solved) • All the open ones were addressed to concerned colleagues. • Most of them are in progress, BUT: • 69 (!) need to be closed by CRG. • At least 4 reminders were sent (the 1st one on July 14th….), no reaction at all! • ELQA team (Richard Mompo and Giorgio D’angelo) and ICQA team (Christian Scheuerlein) reacted very fast, despite the big pressure they have to perform electrical tests in the tunnel. 29/10/2009 JPh Tock MSC-CI

  5. The MSC-CI section LHC     NC status + cryomagnet coordination       MB, SSS and IC NCR’s status in LHC 29/10/2009 JPh Tock MSC-CI

  6. The MSC-CI section LHC          LHC CRYOMAGNETS MAINTENANCE WEB SITE Created by José Pereira Lopes TE-MCS-MNC 29/10/2009 JPh Tock MSC-CI

  7. The MSC-CI section LHC             Overview of ICIT work since December 2008 to now US test of bus-bars (sec. 3-4, 4-5, 5-6, 6-7) Analysis of US test results of LHC main bus bar splices obtained during repair works of sector 3-4 (summary and comparison of present and previous US measurements) (by P. Dziewonski) Inspections of magnets taken out from LHC tunnel (endoscopy, video, pictures, removing unwanted objects, cleaning) - SMA18, Bld.904; results assigned to Vincent Baglin (VAC). MB 2192 M2 Preinspections of magnets on SMI2 (visual inspection of extremities, flanges thickness measurement; SC cables checking, endoscopy and reflectometry of beamlines). SSS227 M2 Preinspections of interconnections before assembly work in sectors 1-2, 3-4, 6-7 (general condition after transport to the LHC tunnel, IC length measurement). Inspections of interconnections before closure (cleanness, presence of protection shells, general conditon of equipment). QQBI.13L5 Anna Wozniak (ICIT-HNINP) – Section Meeting - Shutdown 2009 29/10/2009 JPh Tock MSC-CI

  8. The MSC-CI section LHC             Overview of ICIT work since December 2008 to now Endoscopy of beamlines in the tunnel (cut PIM, blocked RF ball, suspicious places; inner triplets) and removing unwanted objects (plastics, MLI pieces). Endoscopy of connection cryostats (checking supports position, bus-bars and isolation condition, assistance during special plastic support installation). Checked CC: E.11R3, E.11L4, E.11R5, E.5L6, E.11L6, E.11R6, E.11L7. Endoscopy of other instalation, i.e. endoscopy of pipes in SPS water cooling system (by P.Borowiec), endoscopy of power supply system in AMS Satelite (by P.Borowiec; A.Wozniak, R.Haber) Documentation of all tasks in MTF, updating MTF data, reporting ICIT tasks on weekly coordination meetings. Beam lines reflectometry in LHC tunnel – sec. 3-4, from QQBI.20R3 to QBQI.32R3 (by P. Borowiec) Anna Wozniak (ICIT-HNINP) – Section Meeting - Shutdown 2009 29/10/2009 JPh Tock MSC-CI

  9. The MSC-CI section LHC             Overview of ICIT work since December 2008 to now • During Shutdown 2009 ICIT : • inspected 55 magnets on surface; • inspected 58 interconnections before assembly works; • big amount of magnets in all sectors were under endoscopy investigations, ie. 2425 meters of beam line in sector 6-7 were inspected; • 166 US tests were done in four sectors (3-4, 4-5, 5-6, 6-7); • As a result of these inspections 363 non-conformitieswere opened: Paweł Borowiec Anna Wozniak-Chrul Ryszard Haber Jerzy Brzezicki Paweł Dziewonski Anna Wozniak (ICIT-HNINP) – Section Meeting - Shutdown 2009 29/10/2009 JPh Tock MSC-CI

  10. LHC     Components storage The MSC-CI section

  11. The MSC-CI section LHC             Components procurements (Nico)            Support post procurement • Visit to CASA last week to present our needs (107 + 90 units). • Good news: keep the same production line as for the series • Waiting for an offer end of October 29/10/2009 JPh Tock MSC-CI

  12. The MSC-CI section LHC             Components procurements W bellows & Vacuum Vessel W Bellows Vacuum vessels Market Survey done with MME and completed Goal: Call for tender in Spring 2010 In parallel, MS for new inner triplets done with CEA/CNRS Market Survey done with MME and completed Goal: Call for tender in Spring 2010 both for LHC spares and new inner triplets (Fixed dimensions !) 29/10/2009 JPh Tock MSC-CI

  13. The MSC-CI section LHC            Section support to MP3 and patrol: * MP3 shifts : Andrea & JPhilippe Will increase as some members are not available anymore * Patrols : Alain & (Arnaud) 29/10/2009 JPh Tock MSC-CI

  14. The MSC-CI section LHC            SMI2 (Michel) Projet: Extension SMI2 Deuxième projet 450m2 a la place du Bat 3194 Budget 400KCHF Premier projet: 375m2 jumellé avec SMI2 Budget 800KCHF SMI2 Bat Actuel 200m2 29/10/2009 JPh Tock MSC-CI

  15. LHC            SMI2 (Michel) The MSC-CI section

  16. LHC             X-ray tomograph The MSC-CI section • System Now Under Calibration Test on CERN Mockup at RAYSCAN • Phase 1 Commissioning Tests at RAYSCAN on 19 and 20 November • Phase 2 Commissioning Tests at CERN During Week 51 • Final Commissioning in the LHC Tunnel During January 2010 access time 29/10/2009 JPh Tock MSC-CI

  17. LHC             X-ray tomograph mock-up The MSC-CI section 29/10/2009 JPh Tock MSC-CI

  18. The MSC-CI section LHC Possible/Likely interventions for future shutdown: • Repair of connection cryostats in 4 sectors if warmed-up (2-3,4-5, 7-8, 8-1) • Consolidation of 6 kA splices if validated (Chamonix, WG) • Leak in 3-4: localisation, repair and check of geometry • Installation of DN200 (3.5 sectors) Who ? • Investigation on open electrical NCs in warmed-up sectors • Installation of DN160 on 2 SAM (if asked by cryo) (L2, L8) • Open issues identified during HWC and operation To be preliminary defined end of January       29/10/2009 JPh Tock MSC-CI

  19. The MSC-CI section New Inner Triplets : Section participation - Regular meetings within the section QRL TE-CRG CryoExt MSC-CI M S C - C I M S C - C I M S C - C I M S C - C I M S C - C I M S C - C I US? (MSC-CI) MSC-CI MSC-CI MSC-CI MSC-CI MSC-CI MSC-CI US MSC- CI MSC- ML MSC- LMF MSC- LMF MSC- LMF MSC- LMF QDXS D1 MSC-CI CP Q3 Q2b Q2a Q1 Cryostats : L Williams (CNRS) IC : A Vande Craen QDXS : N Bourcey US SC Link US DFX 29/10/2009 JPh Tock MSC-CI

  20. CRYOSTAT (Q1,Q2A,Q2B,Q3,D1)

  21. CRYOSTAT (Q1,Q2A,Q2B,Q3,D1)

  22. Triplet Cryostat Particularities • Based on, and as far as possible, using LHC Arc Cryostat Components , tooling and methods • The cryostat body is well advanced, interface details will be adjusted to suit the interconnects etc. • Identical cryostat length and cross-section for all 4 quadrupoles, and the D1 • Shorter cryostat components for the CP • Some similarities concerning the envelope thermal insulation of the QDSX • The MS tooling set will be upgraded (preserving its original function) to be able to cryostat Q1 Q2A Q2B Q3 CP and D1. To be reinstalled in SMI2 after modification • Some part of the CNRS dipole tooling may be incorporated eg: the electric winch

  23. NIT : CNRS Collaboration Orsay le 07/10/2009

  24. NIT : CNRS Collaboration

  25. PROCUREMENT • IPNO has launched their Market Survey for Triplet Vacuum Vessels • Bottom Tray extrusions are in house • Procurement of support posts is underway • Superinsulation Blankets to be obtained - probably from Jehier • Elastomer seals are acceptable in the radiation environment for ~ 10 yrs • The cold/warm transitions not yet designed • Complete cryostat design to be reviewed as part of the triplet cryo-magnet chain in January 2010. • The cold/warm transitions not yet designed

  26. The MSC-CI section New Inner Triplets :             QDXS (Nico) Courtesy of S.Maridor • First integration studies done BY EN-MEF • Discussion launched with TE-CRG to collect their experience and understand cryogenics requirements Courtesy of B.Vullierme • Discussion launched with EN-MME to start first modelisation 29/10/2009 JPh Tock MSC-CI

  27. The MSC-CI section New Inner Triplets :             Interconnection Transversal section • Size of lines • Necessary clearance • Position of lines • Design for pressure 29/10/2009 JPh Tock MSC-CI

  28. The MSC-CI section New Inner Triplets :             Interconnection Longitudinal section • Global view • Details (technical solutions) 29/10/2009 JPh Tock MSC-CI

  29. Cryogenics collimator The MSC-CI section Modification of SC dispersion suppressors to accommodate additional collimators(“cryo-collimators”) halo 2012 : 29/10/2009 JPh Tock MSC-CI

  30. SPL: The MSC-CI section Future Present Proton flux / Beam power 50 MeV Linac2 Linac4 160 MeV PSB LP-SPL 1.4 GeV 4 GeV PS 26 GeV PS2 50 GeV Output energy SPS 450 GeV LHC / sLHC 7 TeV LP-SPL: Low Power-Superconducting Proton Linac (4 GeV) PS2: High Energy PS (~ 5 to 50 GeV – 0.3 Hz) sLHC: “Super-luminosity” LHC (up to 1035 cm-2s-1) Courtesy of R.Garoby 29/10/2009 JPh Tock MSC-CI

  31. Motivation and Objectives fora cryo-module prototype Motivation: Construction of a prototype cryomodule as a major milestone in support to the TDR and project proposal (including costing) in 2012. Objectives: Validate (and eventually improve) the design(thermal and thermo-mechanics) and construction features; Demonstratethe construction capability on a full-scale machine cryomodule housing β=1 cavities and SC quadrupoles; Enable RF testing (cavities, couplers, tuners…) on a multi-cavity assembly in their real operating environment; Validate cryogenic cooling and acquire experience in operation; Learning of the critical assembly phases, in particular the preparation of a long string of cavities in clean room; 31 October 2009

  32. French contribution (Accord Technique No2, Protocole K1597/DG) In support to the SPL study: Participate to the developpement and construction of the prototype cryo-module β=1. • CNRS/IN2P3: • Participate to the detailed design and integration of the cryostat • Supply of cryostat components for the cryo-module prototype. • CEA: • Design and fabrication of two helium vessels for the beta=1 cavities • Design and supply of the assembly tooling for the cryo-module prototype

  33. Funding and resources (2009-2012) French contribution (CEA/CNRS): M = 430 kCHF (267 kEuro) P = ~7 FTE.year (3.5 cat.2, 3.5 cat.3) CERN part (Total-French contribution): M = 870 kCHF (including 1.25FTE.year EN design jobs) P = 9.5 FTE.year 4 FTE.year (cat.2); 5.5 FTE.year (cat.3)  missing resources still to be identified

  34. CERN French collaboration (Vittorio) The MSC-CI section Protocole de Collaboration K1597/DG • Contribution Exceptionnelle de la France en Nature aux Nouveaux Projets du CERN • Signe’ en Decembre 2008 • 4 Accords Techniques: • Linac 4 • SPL • Nouveaux Aimants Supraconducteurs • CLIC • Valeur de la contribution: 11’258’900 Euros (hors TVA) dont: • 7’056’000 Euros en matériel • 4’202’900 Euros en main d’œuvre 1 ere Réunion du Comite’ de Suivi de Protocole, CERN, 9 juillet 2009 29/10/2009 JPh Tock MSC-CI

  35. CERN French collaboration (Vittorio) The MSC-CI section Comité de Suivi de Protocole (CSP) Membres du Comité • Role du CSP: • mise en œuvre générale de la collaboration • veille à la cohérence des actions menées par les responsables des Accords Techniques • Recommande aux Parties les éventuelles propositions d’avenants • tient à jour l’inventaire des achats de biens et services et de l’utilisation du personnel du CEA et du CNRS/IN2P3 dans le cadre des AT sur la base des relevés fournis par ces deux Parties. • Reunions du CSP: • (au moins) deux fois par an, à tour de rôle au CEA, au CERN ou au CNRS/IN2P3, et seront présidées par le représentant de la Partie hôte. • Note importante: • Chaque Accord technique fait l’objet d’un suivi séparé par les responsables des AT. 1 ere Réunion du Comite’ de Suivi de Protocole, CERN, 9 juillet 2009 29/10/2009 JPh Tock MSC-CI

  36. Conclusion (JPhT) The MSC-CI section + ICIT : P Dziewonski, R Haber, A Wozniak + D Perez Caparros 29/10/2009 JPh Tock MSC-CI

More Related