Water Services National Training Group. 12th Annual Conference 11 th September, 2008. Water Services National Training Group. Drinking Water Safety & Licensing. Rural Water Licensing Guidance and Training. Jerry Cronin and Richard Church Nicholas O’Dwyer / Entec. Presentation Contents.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Water Services National Training Group' - merrill


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
Water services national training group

Water Services National Training Group

12th Annual Conference

11th September, 2008


Water services national training group1

Water Services National Training Group

Drinking Water Safety & Licensing


Rural water licensing guidance and training

Rural Water Licensing Guidance and Training

Jerry Cronin and Richard Church

Nicholas O’Dwyer / Entec


Presentation contents
Presentation Contents

  • Project Objective

  • Background/ Legislation

  • Application Process

  • Application Form / Assessment

  • Overall Assessment

  • Conditions

  • Project Deliverables


Over riding purpose of rural water licensing
Over Riding Purpose of Rural Water Licensing

  • Key driver: States response to ECJ Drinking Water Judgement

  • To ensure that the required water quality standards are achieved

  • To effect a planned, systematic and sustained improvement to infrastructure capacity along with management and operational standards


Project objective
Project Objective

  • To develop guidance and training for the new Rural Water Services Licensing System introduced under the Water Services Act 2007.


Project team
Project Team

  • Procured by: WSNTG

  • Consultants: Nicholas O'Dwyer and Entec

  • Steering Group:

    • WSNTG

    • DEHLG

    • NFGWS

    • CCMA

  • Other Consultees

    • EPA

    • Operators of five representative GWSs (site visits)

    • Rural Water Liaison Officers from the five WSAs


Background legislation
Background/ Legislation

  • Water Services Act 2007

    • The Act provides for the introduction of a licensing system governing the operations of water services providers other than Water Services Authorities or their agents.

    • Water Services Authority (WSA) is responsible for the overall management and supervision of water services provision by authorised water services providers in its functional area.

  • Licensing Regulations currently being drafted and being informed by the consultation process associated with this project and in the development of the Guidance Document.

  • Key Focus Area: Group Water Scheme Sector


European communities drinking water regulations 2007 s i 278 of 2007

Background/ Legislation

European Communities (Drinking Water) Regulations (2007) – S.I. 278 of 2007

  • EPA have powers to direct a WSA to improve the management or quality of a public water supply.

  • WSA’s have a similar supervisory role in relation to group water schemes or private supplies.

  • Exempted Supplies: a supply which –

    • (i) constitutes an individual supply of less than 10 m3/day on average or serves fewer than 50 persons, and(ii) is not supplied as part of a commercial or public activity (e.g. GAA club, Nursing Home), or

    • Is used exclusively for purposes … that the quality of the water has no interference, either directly or indirectly, on the health of the consumers concerned (e.g. car wash system).


Threshold for licensing
Threshold for Licensing

  • Following the exemption principle applied in S.I. 278 it was decided to employ a similar threshold level for Group Water Schemes (i.e. schemes serving less than 15 residences would be exempt)

  • Approximately 1,400 Group Schemes will be included in the Licensing System (approx. 400,000 persons), split approx. equally by public and privately sourced schemes


Breakdown of licensable gws

50%

22%

18%

10%

Breakdown of Licensable GWS

percentages indicate population served


Phasing of licensing
Phasing of Licensing

  • It is proposed that a risk based approach will be used for the phasing in of the licensing system; and that the

  • EPA Remedial Action List approach is adopted by the WSAs to identify the priority schemes for licensing (EPA Guidance Doc Booklet No. 3, February 2008)


Phasing of licensing system
Phasing of Licensing System

  • Phasing details are to be set out in Regulations

  • Further phasing would be based on scheme size with priority given to the larger schemes


Group scheme registration system
Group Scheme Registration System

  • GWS serving less than 15 residences would be registered

  • Separate monitoring and inspection procedures.


2007 act
2007 Act

  • Licensing covered under Part 6, Chapter 2, Sections 78 to 91

  • Sub-section 78 (2): “Each WSA, for the purpose of the protection of human health and the environment, is responsible for the supervision, in its functional area, of water services provided by a person other than a WSA”.

  • Sub-section 79 (1)(a): “On or after such date or dates as may be prescribed, a person shall not –

    • Provide water for human consumption from a tanker, or

    • Otherwise provide water services except under and in accordance with a water services licence issued under this chapter”.


2007 act1
2007 Act

  • Sub-section 79 (3): provides for the setting of a threshold below which a licence will not be required

  • Sub-section 79 (4): “The provision of water services shall, in the period before a licence………is granted or refused, be deemed not to have contravened subsection (1), if – before the date……...an application has been made………”

  • Sub-section 79 (5): “A person who contravenes subsection (1) or a regulation made………commits an offence”.


2007 act2
2007 Act

  • Section 80: Determination by WSA of an activity to be a licensable

  • Section 81:WSA may grant/refuse a licence following consideration of a range of matters

  • Section 82: WSA to be the licensing authority

  • Section 83: Conditions attached to a licence

  • Section 84: Licence review

  • Section 85: Licence revocation

  • Section 86: Consider all submissions and notify all regarding decision

  • Section 87: Appeals process (district court)

  • Section 88: New Regulations

  • Section 89: Contravention of a condition

  • Section 90: Related licences (e.g. discharge licences)

  • Section 91: Powers to take over O & M on a temporary basis



Pre application
Pre-Application

  • WSA to establish RAL for all GWSs within its functional area in accordance with the Licensing Regulations.


Application process1
Application Process

Stage 1

Stage 2

Stage 3




Stage 3 final assessment
Stage 3 – Final Assessment

Licence is Issued



Section 1 2 and 3 general information
Section 1, 2 and 3 – General Information

Section 1 – About the Applicant

  • Name of GWS

  • Status of the GWS (Co-op, company etc.)

  • Register No.

    Section 2 – Nominated Contact Details

  • GWS contact person's name, address and other contact details.

    Section 3 – Insurance Details

  • Public Liability, Employer’s Liability and Asset Insurance.


Section 4 operational contracts maintenance and service contracts
Section 4 – Operational Contracts/ Maintenance and Service Contracts

  • Details of Contract

  • Contractor Details

  • Date of Commencement

  • Period of Contract


Section 5 scheme source details
Section 5 – Scheme Source Details Contracts

  • Exempts schemes served from public mains

  • Number of Sources – details to be provided for each

    • Name and location

    • Type

    • Abstraction Details

      • Source Capacity

      • Current abstraction details

    • Source protection

    • Details of treatment process


Section 6 treatment plants
Section 6 – Treatment Plants Contracts

  • Number of treatment plants – details to be provided for each

  • Name and location

  • Description of the treatment process

  • Build date

  • Design Capacity

  • Daily throughput

  • Discharge/ Sludge Disposal

  • Bypassing facility

  • Water Quality

  • Control/ Alarms

  • Metering


Section 7 distribution system
Section 7 – Distribution System Contracts

  • Details of Distribution Mains (diameter, length, type, age etc.)

  • Booster/ Pumping stations in network

  • Details of Network Upgrading/ Renewals

  • Service Reservoirs

  • Secondary Disinfection Points

  • Details of Domestic/ Non Domestic Connection

  • Average Day Distribution Input (ADD)

  • Average Day Peak Week (ADPW)

  • Unaccounted for Water (UFW)

    • WSNTG/NFGWS training course

  • Burst Details/ Problem Areas


Section 8 network water quality
Section 8 – Network Water Quality Contracts

  • Details of supply restrictions e.g. Boil Notices, “Do Not Use” notices etc.

  • Cryptosporidium Risk Assessment


Section 9 and 10 scheme management training
Section 9 and 10 – Scheme Management/ Training Contracts

Section 9 – Scheme Governance

  • Details of Scheme Governing Body/ Committee

    • How appointments are made

    • Annual General Meetings

    • Notification of members/ shareholders

      Section 10 – Training

  • Typical details of training undertaken by management and operational staff

    • courses available from WSNTG regional training centres


  • Section 11 and 12 financial
    Section 11 and 12 - Financial Contracts

    Section 11 – Financial Management

    • Details of Financial Accounts

    • Audited/ Certified Accounts

      Section 12 – Capital Investment Programme

    • Details of Capital Investment Programme

    • Asset Management Plan


    Section 13 quality assurance
    Section 13 – Quality Assurance Contracts

    • QA system

    • National Rural Water Monitoring Committee System

    • Water Safety Plan

    • O & M plan

    • Drinking Water Incident Response Plan/ Emergency Plan

    • Water Conservation Plan/ UFW Reduction

    • Charter of Rights/ Complaints Procedure and Feedback.


    Section 14 maps and plans
    Section 14 – Maps and Plans Contracts

    • Overview Map (1:10,000 or 1:5,000)

      • Sources

      • Treatment Plants

      • Distribution Network

      • Reservoirs

      • Boosters

      • Secondary Disinfection Points

  • Treatment Plant – Layout Details

  • Source Protection Maps


  • Section 15 declaration
    Section 15 – Declaration Contracts

    • Certify that information is true

    • Consent to make application available for inspection

    • Certify that signee is duly authorised by GWS to sign on its behalf



    Assessment process
    Assessment Process Contracts

    • WSA to consider:

      • Information contained in the Application Form and Additional Information requested and Submissions received from 3rd parties.

    • WSA also to have regard to (Sub-Section 81(2)):

      • Relevant Strategic Water Plans

      • GWS resources (Financial, Operational, Management)

      • Other WSAs for any cross boundary schemes

      • Alternative supplies

      • Any requests to have GWS taken in charge

      • Water Supply Standards

        • Drinking Water Quality

        • Levels of Service

      • Other Matters


    Assessment process1
    Assessment Process Contracts

    • Vast majority of GWS will receive licences.

    • Where deficiencies are noted – appropriate conditions should be attached

    • Sub-Section 79 (4) provides for GWS to continue in operation after the new system comes into force, provided an application has been made before the commencement date.






    Licence conditions
    Licence Conditions Infrastructure

    • Sub-Section 83(2) requires that conditions relating to water services licensing 'shall' be included in respect of certain categories

    • Sub-Section 83(3) lists further categories from which conditions 'may' be included for consideration


    Standard conditions section 83 2

    (a) Measures to ensure against risk to human health and the environment

    Example conditions for a licence:

    comply with drinking water quality standards

    provide adequate supply, treatment and distribution capacity to meet forecasts

    adequate arrangements to ensure essential and adequate supply at all times

    have all discharges authorised and regulated for disposal by appropriate authority

    ensure adequate measures to prevent contamination of local environment

    Standard Conditions Section 83(2)


    Standard conditions section 83 21
    Standard Conditions Section 83(2) environment

    (b) Water Supply Standards

    • Drinking water quality standards

      • European Communities (Drinking Water) [No. 2] Regulations 2007 (S.I. No. 278 of 2007)

      • European Communities (Quality of Surface Water Intended for the abstraction of Drinking Water) Regulations 1989. (S.I. No. 294 of 1989)


    Standard conditions section 83 22
    Standard Conditions Section 83(2) environment

    (c)Standards of Service

    • Performance standards

      • Defined in strategic resource plans

      • e.g. 15m of head at stop-cock

    • Customer service

      • Reporting

      • Complaints procedure

      • Annual General Meeting


    Standard conditions section 83 23
    Standard Conditions Section 83(2) environment

    (d) Monitoring and Supervision

    • Frequency to meet the Drinking Water Regulations

    • Appropriate reporting schedule to WSA

      (e) Sampling and Analysis Section

    • Responsibility of GWS but undertaken by WSA/HSE

      (f) Other such matters as may be prescribed


    Additional conditions section 83 3
    Additional Conditions – Section 83(3) environment

    (a) Scale of Activity

    (b) Specification of Households, Areas or Activities

    (c) Operational and Management Procedures

    (d) Procurement Procedures


    Additional conditions section 83 31
    Additional Conditions – Section 83(3) environment

    (e) Measures to ensure public safety


    Additional measures section 83 3
    Additional Measures - Section 83(3) environment

    (f) Emergency plans

    (g) Employers and Public Liability Insurance

    (h) Conservation Measures


    Additional measures section 83 31
    Additional Measures - Section 83(3) environment

    (i) Measures to prevent source contamination

    (In the immediate vicinity of source)


    Additional measures section 83 32
    Additional Measures - Section 83(3) environment

    (j) Metering


    Additional measures section 83 33
    Additional Measures - Section 83(3) environment

    (k) Proper treatment, reuse or disposal of by-products


    Additional measures section 83 34
    Additional Measures Section 83(3) environment

    (l) time limits

    (m) provisions to facilitate the application of obligations

    (n) accounts and annual reports

    (o) any other matters as may be prescribed


    Project deliverables
    Project Deliverables environment

    • Background Scoping Document

    • Application Forms

    • Guidance Document

    • Courseware

    • Delivery of Training Courses