1 / 47

CPM 300 Principles of Earned Value Implementation CPM 300B Management Use of EV Data

Training Objectives. Basic concepts of measuring performanceExamplesEVM guidelines for project executionBasic concepts of reporting progressBasic concepts of analysisExamples. Budgeted Cost for Work Performed(BCWP). . the EARNED VALUE concept. . We're at the end of the second month, but only 1 section of track is complete. Earned value of work completed = $1,000.

merrill
Download Presentation

CPM 300 Principles of Earned Value Implementation CPM 300B Management Use of EV Data

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


    1. CPM 300 Principles of Earned Value Implementation CPM 300B – Management Use of EV Data Eleanor Haupt Aeronautical Systems Center eleanor.haupt@wpafb.af.mil +1-937-656-5482

    2. Training Objectives Basic concepts of measuring performance Examples EVM guidelines for project execution Basic concepts of reporting progress Basic concepts of analysis Examples

    4. General Principles of Measuring Performance (BCWP) Establish valid metrics as you establish the time phased baseline Relate true work status Objective and quantifiable Should be a quantitative and discrete way to measure the work May tie in with success criteria or technical measure Example: successful completion of a specific test Must be consistent in following established metric as work progresses BCWP value drives both cost and schedule variances If overstated or understated, it will distort variances Can impact estimate at complete calculations

    5. Discrete Physical, tangible end product Common techniques: milestone, % complete, 0/100, 50/50, units complete Apportioned Discrete, but dependent on another discrete work package Example: quality assurance (depends on assembly labor) Planned as historical estimating factor (e.g., 7%) Level of Effort No tangible end product Basis of measurement: time When clock starts ticking, you automatically accumulate earned value Results in no schedule variance (BCWP will always equal BCWS) Example: management personnel Three Basic Methods of Earning Value

    6. Discrete EV Techniques: Method How Value is Earned 0/100 no EV at opening, 100% EV at close of WP 50/50 50% EV at opening, 50% EV at close of WP Units Completed same budget value for identical units Equivalent Units planned unit standards, allows partial credit Weighted Milestone each milestone weighted based on planned resources ideal to have a milestone each month Percent Complete should be based on some quantitative assessment may be somewhat subjective Be Discrete!

    7. Material and Subcontracts Earned Value: taken no earlier than receipt or progress payments to subcontractors define order receipt or progress payments payment to inventory usage accurate cost accumulation and assignment to contract should perform price and usage variances should plan earned value to match expected payment period BCWP and ACWP should occur in same period to avoid artificial cost variance option: may report “estimated actuals” based on invoice Earning BCWP on Material

    8. Examples of BCWP Calculations

    9. Different EV Methodology Yields Different Results!

    10. Example: Milestone Technique

    11. Example: Level of Effort Technique

    12. Example: 50/50 Technique

    13. Example: Percent Complete Technique

    14. Which Technique Accurately Reflects Work Progress? Milestone SV -100 -20 +120 0 CV -50 -20 +40 -30 LOE SV 0 0 0 0 CV +50 0 -80 -30 50/50 SV 0 -160 +160 0 CV +110 -120 -20 -30 % Compl SV -40 -20 +60 0 CV +10 -20 -20 -30

    15. EVM Guidelines for Project Execution

    16. Work Packages

    17. Can only work on work package if it has been opened Charge costs to open work packages only Contractor system sets procedure Contractor maintains baseline log which tracks: Distribution of budget Additions of authorized work Total equals value of contract at cost Contract changes incorporated in disciplined manner Cannot start work without authorization and budget Baseline changes are controlled Authorizing the Work

    19. Project Control So, your project has been baselined and work has started Is everything going according to plan? Next step in the process: figure out your status figure out the problems figure out what you need to do to fix them figure out what the impact might be

    20. Status Reporting Report on periodic basic weekly monthly Tailor the data to match how you’re managing Provide performance reports to: Senior management Customer Based on contract terms Use data in reports and variance analysis to manage and control project

    21. Contractor Reports Cost Performance Report (CPR) Format 1: cost and schedule progress by WBS (specified reporting level usually at level 3) Format 2: cost and schedule progress by organization Format 3: changes to performance measurement baseline Format 4: manpower forecast Format 5: variance analysis

    22. Formats 1 and 2 Contents header: basic contract information (target, ceiling, name of contractor, etc.) range of final estimates body performance data variances budget at completion, estimate at completion

    23. Format 5 variance analysis should address: separate discussion of CV, SV (current and cum) and VAC clear description of reason for variance quantity variances (e.g., price vs. usage) be specific discuss needed corrective action technical, schedule, and cost impacts impact to estimate at completion should be written by CAM! Variance Explanations

    24. Sample of Variance Analysis

    25. Basic Concepts of Analysis or figuring out where the problems are

    26. Looking Forward To address management with earned value more specifically, it is important to analyze our past performance in order to help us control the future. All too often, earned value data is seen as historical, a nice picture of where we’ve been. It is challenging work to analyze these past trends and use them to project into the future. However, every program manager should be able to answer when the project will finish, what it will cost, and understand the impacts of future risks. Using earned value data allows us to project these trends and then to take the appropriate action to control the project. Acquiring earned value data can take a substantial amount of time and resources, and we must make effective use of it in managing our projects. Earned value is the only management tool that relates cost and schedule progress to technical progress. Earned value should not be seen as a progress report, but the integrating principle of project management. To address management with earned value more specifically, it is important to analyze our past performance in order to help us control the future. All too often, earned value data is seen as historical, a nice picture of where we’ve been. It is challenging work to analyze these past trends and use them to project into the future. However, every program manager should be able to answer when the project will finish, what it will cost, and understand the impacts of future risks. Using earned value data allows us to project these trends and then to take the appropriate action to control the project. Acquiring earned value data can take a substantial amount of time and resources, and we must make effective use of it in managing our projects. Earned value is the only management tool that relates cost and schedule progress to technical progress. Earned value should not be seen as a progress report, but the integrating principle of project management.

    27. Basic Analysis Techniques Find significant variances eliminate almost complete, just starting, etc. Graph and analyze trends Look at comparative data e.g. cumulative performance vs. projected performance Examine written analysis by contractor does it answer why? adequacy of corrective action plans Analysis of schedule trends, critical path Analysis of EAC realism

    28. Types of Variances Values can be expressed as either current period or cumulative current tends to be more volatile use cum data to show trends Easy rule of thumb: negative value = BAD positive value = GOOD index < 1.0 = BAD index > 1.0 = GOOD Absolute expressed in terms of dollars or hours (e.g., -$1,000) may not be able to tell significance from this amount Percent relates absolute variance to a base (e.g., -35%) shows significance Index compares one value to another in a simple ratio if you are on plan, index = 1.00

    29. Where are the significant problems?

    30. Graphing Techniques

    31. CURRENT OR CUM TO DATE Schedule Variance SV ($) = BCWP - BCWS SV (%) = BCWP - BCWS x 100% BCWS Cost Variance CV ($) = BCWP - ACWP CV (%) = BCWP - ACWP x 100% BCWP Analysis of Variances

    32. Performance Indices

    33. Past and Present Cost Efficiency The TCPI(LRE/EAC) depicts the efficiency necessary for the contractor to complete at his estimated EAC. Since we had assumed the contractor had resolved all problems it is no surprise that he only has to work at 100% to achieve his EAC. Of course, he was only working at 42%. The TCPI(LRE/EAC) depicts the efficiency necessary for the contractor to complete at his estimated EAC. Since we had assumed the contractor had resolved all problems it is no surprise that he only has to work at 100% to achieve his EAC. Of course, he was only working at 42%.

    34. Schedule Status

    35. Budget Status

    36. Mutual Goal: Effective Variance Analysis Make it meaningful avoid routine explanations Make it timely Make it streamlined significant variances Make it right work with contractor to get the information we need Get the information to the managers Use the information to control the project

    37. Estimate at Completion (EAC) defined as actual cost to date + estimate to complete contractor develops comprehensive EAC at least annually reported by WBS in cost performance report should examine on monthly basis consider the following in EAC generation performance to date impact of approved corrective action plans known/anticipated downstream problems best estimate of the cost to complete remaining work What will be the final cost?

    38. Need to Estimate Costs for Remaining Work Budgeted Cost for Work Remaining (BCWR) Budgeted, baseline value for remaining work Update estimate of costs for BCWR Can be detailed estimate Can calculate with performance factors (CPI or SPI) Assumes performance will continue at same level of efficiency Basic formula: BCWR / performance factor Example: CPI = .9 BCWR = 1,000 Estimate to complete = 1,000 / .9 = 1,111

    39. Common EAC Formulas: EAC = BAC CPI = ACWPcum + Budgeted Cost of Work Remaining CPI3 = ACWPcum + Budgeted Cost of Work Remaining .5(CPI) +.5(SPI) = ACWPcum + Budgeted Cost of Work Remaining CPI * SPI Common EAC Formulas

    40. Other methods of EAC calculation “Grass Roots” or formal EAC detailed build-up from the lowest level detail hours, rates, bill of material, etc. Average of statistical formulae Statistical regression Complete schedule risk analysis for remaining work, estimate work remaining

    41. Past vs. Projected Efficiency

    42. Earned Value Enables Realistic Forecasts

    43. The “Box of Uncertainty” (courtesy Swedish Defense Material Administration)

    44. Managing with Earned Value Data

    45. Program Manager Responsibilities Assign integrated responsibility to teams Demand accountability Ask tough questions project office contractor Look ahead – manage the risks Integrated analysis and reviews EVMS Integrated Master Schedule Risk Plan Manage to the baseline Control statement of work growth Lead assessment of baseline realism Integrated Baseline Review (IBR) Call for realistic estimates The Program Manager is the key person in making EVM work. Some of the major responsibilities are to assign responsibility to IPT subordinates, and then hold people accountable and ask tough questions. This would be true both on the government and contractor teams. Another key responsibility is to use EVM data to identify trends and potential problems and manage program risks. The PM is also responsible for ensuring that the EVM data ties together with the integrated master schedule, the risk plan and other management indicators. Earned value should be seen as the connecting thread between the contractor’s technical, schedule, and cost performance. The program team should fully integrate EVM analysis into program reviews. The PM should see the EVM baseline as the plan to manage the project. Successful baseline management includes controlling growth of the SOW and assessing the baseline realism. The IBR is the initial review of the baseline, and the baseline should be reviewed continually through the life of the project.The Program Manager is the key person in making EVM work. Some of the major responsibilities are to assign responsibility to IPT subordinates, and then hold people accountable and ask tough questions. This would be true both on the government and contractor teams. Another key responsibility is to use EVM data to identify trends and potential problems and manage program risks. The PM is also responsible for ensuring that the EVM data ties together with the integrated master schedule, the risk plan and other management indicators. Earned value should be seen as the connecting thread between the contractor’s technical, schedule, and cost performance. The program team should fully integrate EVM analysis into program reviews. The PM should see the EVM baseline as the plan to manage the project. Successful baseline management includes controlling growth of the SOW and assessing the baseline realism. The IBR is the initial review of the baseline, and the baseline should be reviewed continually through the life of the project.

    46. Quotes from Project Managers

    47. Additional References http://www.cpm-pmi.org http://www.acq.osd.mil/pm

    48. Summary Be careful to establish correct value for reported BCWP (earned value) Set up and maintain system discipline Maintain a realistic baseline Analyze earned value data Calculate a realistic estimate at completion Manage with earned value data

More Related