Federico Ronchetti INFN, Laboratori Nazionali di Frascati. EMCAL: project update - Italy -. LNF - Frascati Fixture production Module assembly (proto) WLS fibers processing Lead procurement (proto) CT- Catania APD characterization and test SM Crates production. LNF status.

Download Presentation

EMCAL: project update - Italy -

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Emcal project update italy

Federico Ronchetti

INFN, Laboratori Nazionali di Frascati

EMCAL: project update- Italy -

LNF - Frascati

Fixture production

Module assembly (proto)

WLS fibers processing

Lead procurement (proto)

CT- Catania

APD characterization and test

SM Crates production


Lnf status

LNF status

  • Module production

    • design fixed recently (25-26 june)

  • Universal fixture production

    • Completed: Base, tool-plates, sleds, cylindrical rails

    • Ongoing: center-blocks, load cell plates, cross-beam

  • Vacuum chamber for WLS fibers processing

    • Magnetron gun finally delivered and installed

    • Chamber closed

    • Out gassing chamber (10-8 bar)

  • WLS fiber polishing

    • First bundles ice-polished

    • Quality checks underway

  • Lead procurement

    • Lead tiles for prototype delivered

    • Ongoing reshuffling (from by-measure to by-module packs)


Lnf universal fixture

LNF universal fixture

Design by eng. Mario Del Franco


Fixture parts

Module front plate

Is the governing dimension

Fixture parts

Design by Mario Del Franco


Fixtures realization progress

Fixtures realization progress

Picture not up-2-date: more components than shown have been machined


U fixture

U. Fixture

  • All components materials for missing parts are at hand

  • Design for proto is module finalized (WSU EMCAL meeting last 25-26 of June)

  • Full fixture production (2xLNF) over by the end of July.


Compression table

Compression Table


Fiber processing chamber

Fiber processing chamber


At present out gassing phase

At present: out gassing phase


Wls fibers polishing

WLS fibers polishing

Side to be aluminized

APD / light guide coupled side


Fiber module insertion tools

Fiber module insertion tools

Modified WSU design by M. D. F.


Lead tiles metrological tests

Lead tiles metrological tests

Tile thickness


Lead tiles metrological tests1

Lead tiles metrological tests

Hole diameter


Lead tiles metrological tests2

Lead tiles metrological tests

Inter-hole distance


Short term schedule

Short term schedule


Ct work in progress

CT work in progress

  • Undergoing activity in CT:

    • EMCAL Super-Module Crate Prototype

    • Installation of universal module stacking fixture (delivered by LNF)

  • Activity in CERN

    • Mechanical Integration of SM-crate

    • Load Tests


The crate prototype

Thecrate prototype


Sm crate load test @ cern

SM crate load test @ CERN

  • Design

    • blueprints

    • materials

    • safety

  • Realization

    • The SM-crate proto has been tested at 0° angle


Sm crate load test @ cern1

SM crate load test @ CERN

Dummy strip modules


Additional testing phases

Additional testing phases


Mechanical work summary for 2007

Catania planning for 2007-8

(mechanical)

Mechanical work summary for 2007

Work in progress @ CT:

  • Installation of 1 universal stacking fixture and 1 compression table.

  • Procurement of ancillary equipment (load cells, amplifiers, etc)

    Work in progress @ CERN:

  • Load Test of the SM crate proto at 90°

  • Insertion test SM

  • Construction of the insertion plane


Emcal project update italy

Catania activity electronics, offline

  • New lab space available for massive APD tests

  • Procured all the cards of the standard PHOS/EMCal electronic chain to be used for the APD test. This standard CERN set-up is almost ready (work is in progress on the software installation).

  • Draft for protocol for APD test established

  • First prototype for APD characterization as a function of the temperature is ready. Characterization of ALL 85 APD+CSP is done.

  • First version of track-matching ready and in CVS.


Emcal project update italy

First set-up for APD characterization

LED flasher

Box cointaing APD

Alice-jet1 Catania


Emcal project update italy

First prototype for APD characterization as a function of the temperature

Standard –EMCal electronic chain

Fluid from a chiller at a fixed temperaure

Light from LED flasher

Alice-jet1 Catania


Emcal project update italy

Alice-jet1 Catania


Emcal project update italy

Barrelto EMCAL trackmatching

Presented to ACAT07

First version of track-matching ready and in CVS.

Track matching efficiency and contamination for PHYTHIA minimum bias events

Aim:

To clean the cluster sample for photon analysis (jets)

adding PID information from EMCAL to high momentum charged tracks

Alice-jet1 Catania


Emcal project update italy

Catania planning for 2008

(electronics, offline)

  • APD procurement

  • Test setup optimization

  • start of massive APD testing

  • Test beam data and cosmic ray data analysis

  • Track-matching optimization and simulation studies on jet and electron showers.