80 likes | 212 Views
Development of a FLC Model for Predicting Schedule Impacted by Change Orders in Construction Projects. Jieh-Haur Chen Dec. 14 2001. Introduction. Problem Statement Change orders cause schedule problems raising disputes in construction projects. Methodology
E N D
Development of a FLC Model for Predicting Schedule Impacted by Change Orders in Construction Projects Jieh-Haur Chen Dec. 14 2001
Introduction • Problem Statement • Change orders cause schedule problems raising disputes in construction projects. • Methodology • Find the correlation in historical data. This correlation will be used in establishing a mathematical model, fuzzification, and fuzzy control rules. • Use fuzzy approach to predict and measure construction schedules being impacted by change orders.
Data Analysis • Mechanical and electrical contractors’ roles
Data Analysis • Project Type
Data Analysis • Percent of Change • Public vs. Private (46% vs. 54%) • Distribution of the Percent Change
Data Analysis • Reasons of Change Orders
FLC Model • 5 state variables • Role, Project type, % Change, Feature, And Reasons
Discussion and Future Work • Predicted Schedule = • Yet to process the FLC model successfully. • Fuzzification • Fuzzy rules