U.S. 150 / S.R. 56 Road Reconstruction Project in Paoli, Orange County Thursday, August 25, 2011 6:00pm Presentation Ora

U.S. 150 / S.R. 56 Road Reconstruction Project in Paoli, Orange County Thursday, August 25, 2011 6:00pm Presentation Orange County Community Center 1075 Sandy Hook Road in Paoli. Rickie Clark, INDOT Office of Public Involvement Purpose of Meeting / Meeting Format

maralah
Download Presentation

U.S. 150 / S.R. 56 Road Reconstruction Project in Paoli, Orange County Thursday, August 25, 2011 6:00pm Presentation Ora

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. U.S. 150 / S.R. 56 Road Reconstruction Project in Paoli, Orange County Thursday, August 25, 2011 6:00pm Presentation Orange County Community Center 1075 Sandy Hook Road in Paoli

  2. Rickie Clark, INDOT Office of Public Involvement Purpose of Meeting / Meeting Format Informal Q & A with project engineers and INDOT project officials following the formal presentation Introduction of INDOT Project Officials and project design team Recognition of Elected Public Officials WELCOME

  3. Sign-in at attendance table to be added to project mailing list Meeting invitations were mailed to known property owners within project area Announcement of this meeting was posted to INDOT website. A media release was also issued INDOT website at: www.in.gov/indot “Public Involvement Stay informed by receiving updates

  4. Indiana Department of Transportation Indiana Division Federal Highways Administration Orange County Town of Paoli Elected Public Officials Community residents and citizens Commuters Trucking industry School Corporations others Project Stakeholders

  5. Project Development Process Public Hearing (2005) We Are Here

  6. This project was presented during a public hearing held in 2005 Part of a larger project involving widening and reconstruction activities on U.S. 150/S.R. 56 & S.R. 37 from Prospect to Mitchell Orange and Lawrence Counties with a total project length of 20.5 miles Project History

  7. U.S. 150/S.R. 56 from east of C.R. 375 W to east of C.R. 225 W (Indian Boundary Road) for a total length of 1.67 miles Project exception at bridge over Lick Creek with a length of 0.29 miles leaving a net project length of 1.38 miles Project Description

  8. Numerous geometric features: Vehicles passing opportunities Vertical curvatures Shoulder widths Roadside ditches for drainage Areas of sight distance Project Need

  9. Rural 2-lane roadway Two 12-foot travel lanes 2-foot shoulder width Eight vertical curves addressed Limited sight distance at intersection Passing opportunities are limited Existing Facility

  10. Principal rural arterial Design speed of 55 mph Traffic volume projected for year 2032 is 12,810 vehicles per day Project Description

  11. Horizontal alignment will generally follow the existing roadway U.S. 150/S.R. 56 will be shifted to the south to minimize impacts to the historic James Lindley Farm property at northeast corner of the intersection of U.S. 150/S.R. 56 and C.R. 275W. C.R. 275W will also be shifted to the west Project Description

  12. Provide a 4-lane passing section from east of the Project Exception to 1,420 feet west of the intersection of U.S. 150/S.R. 56 and C.R. 225 W for a length of 0.8 mile Project Description

  13. Typical section will generally be two 12-foot wide travel lanes Shoulders will be widened to 10 feet throughout the project limits Pavement section generally will be scarified and overlayed with 1.5 inches of surface asphalt Project Description

  14. 4-lane passing section will consist of four 12-foot wide travel lanes with 4-foot wide shoulders Within the 4-lane passing section, the pavement will be replaced Project Description

  15. At intersection of U.S. 150/S.R. 56 and C.R. 225 W. left-turn for eastbound U.S. 150/S.R. 56 traffic and right-turn lane for westbound U.S. 150/S.R. 56 traffic C.R. 275 W will be reconstructed for a length of approximately 440 feet C.R. 225 W will be reconstructed for a length of approximately 370 feet Project Description

  16. Drainage along the roadway will be provided using roadside ditches Culvert west of C.R. 275 W will be replaced Twin culverts between C.R. 275 and C.R. 225 will remain in place Drainage

  17. Karst features will be evaluated and protected Trees suitable for Indiana Bat will not be cut from April 1st through September 30th Environmental Issues

  18. Due to moderate traffic volumes and lack of a nearby alternate route, traffic will be maintained along U.S. 150 during construction This project will require multiple phases and the use of temporary runarounds and flagging operations Maintenance of Traffic

  19. Real Estate Acquisition Process

  20. Project will require an additional 21.5 acres of permanent Right of Way and an additional 1.1 acres of temporary Right of Way No total property acquisitions, however one barn and a small outbuilding will need to be removed Right of Way

  21. “Uniform Act” of 1970 All federal, state, and local governments must comply Requires an offer for just compensation Acquisition Process Appraisals Review Appraisals Negotiations Real Estate Acquisition Process

  22. Talk with INDOT project team members Comment sheet in information packet E-mail or Mail comments to INDOT Sign-in sheet to be added to project mailing list Visit INDOT website at www.in.gov/indot “Public Involvement” All comments are very much appreciated and will be given full consideration by project team INDOT would like to hear from you

  23. Public Involvement Team Rickie Clark, INDOT Office of Public Involvement (317) 232-6601 rclark@indot.in.gov Abby Mason, Vincennes District Customer Service Manager (800) 279-5758 swincommunications@indot.in.gov Cher Elliot, Vincennes District Media Relations Director (800) 279-5758 cgoodwin@indot.in.gov Chris Gentry, Vincennes District Project Manager cgentry@indot.in.gov INDOT website: www.in.gov/indot “Public Involvement / Media” page

  24. Vincennes District Office, 3650 South U.S. Hwy 41 in Vincennes swincommunications@indot.in.gov (800) 279-5758 Responsible for transportation development, construction and maintenance activities for southwest Indiana Russell A. Fowler, P.E. – Vincennes District Deputy Commissioner Abby Mason, Customer Service Manager Cher Elliot, Media Relations Director Project Resource Location