Washington avenue reconstruction project
Download
1 / 12

Washington Avenue Reconstruction Project - PowerPoint PPT Presentation


  • 101 Views
  • Uploaded on

Washington Avenue Reconstruction Project. Public Informational Meeting. City of Chelsea. May 31, 2011. Why Project is Occurring. Poor Roadway Conditions Separation of Sewer and Stormwater Replacement of Water Replacement of Gas (by National Grid). What Does the Project Entail?.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' Washington Avenue Reconstruction Project' - malina


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
Washington avenue reconstruction project

Washington Avenue Reconstruction Project

Public Informational Meeting

City of Chelsea

May 31, 2011


Why project is occurring

Why Project is Occurring

Poor Roadway Conditions

Separation of Sewer and Stormwater

Replacement of Water

Replacement of Gas (by National Grid)


What does the project entail

What Does the Project Entail?

  • Project Details

    • Geographic Scope of the Work

      • Heard St to Route 16

      • Back of Sidewalk to Back of Sidewalk

      • Reconfiguration of Cary Square

    • Full-Depth Roadway Reconstruction Explanation

      • New Street Surface

      • New Sidewalks

      • Streetscape Amenities (Benches, Bike Racks, Trees, Etc.)


What does the project entail1

What Does the Project Entail?

  • Funding Sources

  • Municipal Borrowings through General Obligation

  • Sewer and Water Bonds

  • Chapter 90 Funds

  • Community Development Block Grant Funding

  • MWRA Grant and Zero Interest Loans

  • Total of $6M+


What does the project entail2

What Does the Project Entail?

  • Project Construction Schedule

    • Water, Sanitary & Drain - Spring/Summer/Fall 2011

    • Streetscape – Spring/Summer/Fall 2012

    • Completion – Spring 2013


Project schedule

Project Schedule

  • Contract has been awarded to J. Marchese and Sons

  • Work starts Monday June 6th

  • Work hours approximately 7 AM to 3:30 PM, Monday through Friday