DOME diverse outdoor mobile environment Cluster D Spiral 2 meeting Mark Corner, Brian Levine, Brian Lynn
Progress in Year One • Official Milestones • 1a) Hardware installed (completed) • 1b) Virtualization of OS (completed) • 1c) virtualized WiFi access (completed) • 1d) Setup GENI control framework (completed) • 1e) v1.0 of software (started) • DOME portal (completed) • Experiment execution and control on buses (completed) • 1f) demo basic control functions • 1g) Cluster D framework (ORCA) integration (started)
Integration with ORCA • Development of DOME ORCA controller and handler • Controller: initiate requests for leases • Handler: perform actions based on leases being granted and revoked • DOME portal interfaces to ORCA • Scheduling an experiment invokes ORCA • Portal takes action on behalf of the handler • Leases are communicated to buses • ORCA instance to be shared with ViSE • geni.cs.umass.edu (with ViSE)
Connection to Internet2 • In discussions with local OIT staff • We will connect geni.cs.umass.edu to Internet2 directly • via fiber from campus to Springfield to Boston • Working in tandem with ViSE team • (Won’t be to buses.)
Experiments by Outsiders • DOME Portal (next slide) • Upload experiments for distribution to buses • Schedule experiments • Get status • Interface to ORCA • Experiments on Buses: • Disruption tolerant downloading of experiments to buses • Dynamic creation of VM sandbox to execute experiments • Partitions, networking, devices • Scheduling of experiments based on ORCA leases • Asynchronous logging of guest VM events • Disk space management (Garbage collection, prioritization) • Upload status to portal (Experiments installed, started, failed)
Plans for Year2/Spiral2 • Our goal is to deploy on buses this summer • Reduced bus schedule, greater access • Must do it right the first time • Creating a development/test environment • Undergrad projects in the fall from “Intro to Networking” class. • Also in Spiral 2: • Allow experimenters access to XTend radios • Integration with master GENI clearinghouse • True open access to testbed by experimenters