FRENCH LTD

FRENCH LTD. BEFORE SUPERFUND: 1950 - 1965 Sandmine 1966 French Ltd. Trucking 1967 TWQB and Riverdale’s telegram to LBJ 1969 Floods 1973: [HOT] Public Hearings TWQB Permit Revoked Giant Fizzzzz Property deeded to State. FRENCH LTD. BEFORE SUPERFUND [CONT] 1979 Floods

mai
Download Presentation

FRENCH LTD

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FRENCH LTD • BEFORE SUPERFUND: • 1950 - 1965 Sandmine • 1966 French Ltd. Trucking • 1967 TWQB and Riverdale’s telegram to LBJ • 1969 Floods • 1973: • [HOT] Public Hearings • TWQB Permit Revoked • Giant Fizzzzz • Property deeded to State

  2. FRENCH LTD • BEFORE SUPERFUND [CONT] • 1979 Floods • 1981 • EPA Removal to repair dikes, • TDWR tests Riverdale wells [OK], • Site on NPL in October • SUPERFUND RI/FS: • 1983 • APRIL- TDWR starts RI/FS under EPA grant • JUNE- Flooding and PCB scare • SEPT- FLTG formed

  3. FRENCH LTD • NOTE: French Limited Task Group (FLTG): • consortium of 7 out of 90 PRP’s, • ARCO’s Dick Sloan takes lead, • much in-fighting about cost allocation • first contractor fired • bio-treatment lab work inconclusive • SUPERFUND RI/FS (CONT.) • 1984 and 1985: Study • 1986 : • JULY Proposed Plan for Sikes • SEPT $92 million ROD signed

  4. FRENCH LTD • SUPERFUND RI/FS: • 1987 • APRIL: Studies completed; contamination in: • 78,000 cu yds sludge, • 70,000 cubic yards soil, • 25 million gallons water. • April: EPA’s Proposed Plan issued for comment. • Preferred remedy: $75 million incineration PROBLEM

  5. My bosses Community Tort Attorneys Other PRP’s State Agency EPA Lawmakers Reduce liability Frustrated $25B = compassion Reduce shares and net liability PRP lead = no 10% Results! Meet SARA Scientists: ‘baloney’ Just deserts FRENCH LTD.AS PRP PROJECT MGR, HOW DO YOU RESPOND?PARTYPERCEIVED DESIRE

  6. FRENCH LTD • PRP PROPOSAL TO EPA: • in-situ biological treatment pilot • $3 million • community involvement • only 4 [more] months needed • EPA RESPONSE: • postpone decisions until after October 30 • public meetings: wary of incin. NIMBY

  7. FRENCH LTD • PRP PILOT PROJECT • May sparging pipes installed • June on.. monthly community events [bingo, lunches, barbecues, raffles] • October 30 submitted to EPA 13 volumes of results [23 feet high!] • EPA REVIEW • seems effective on organics but what about metals, GW impacts & permanence? • DOJ and Natural Resource Trustees interests

  8. FRENCH LTD • NOV • 14- New ATSDR rep. Meets with Mel Whidden [mayor of Riverdale] confuses well data • 15- Crisis re: water, EPA samples • DEC • 15- EPA lab loses samples, re-sampling • JAN • 21- EPA HQ official holds meeting, no answers for community • 28- EPA Teams deliver results to residents [OK!] eat/drink at Whidden’s

  9. FRENCH LTD PROBLEM WHAT REMEDY SHOULD EPA SELECT? WHAT ARE THE DRIVING FACTORS?

  10. FRENCH LTDMarch 31, 1988 Record of DecisionCOMPONENTAPRIL ‘87MARCH ‘88

  11. FRENCH LTD • 1988: • APRIL TO DECEMBER- EPA and DOJ negotiated consent decree with FLTG. Successfully concluded 12/23/88 • 1989: • MARCH 24 … Exxon Valdez. Impacts: • $5M settlement [$2M attny’s, $3M new trucks]. • Settlement of FTLG with community • MAY 12 Floods… PCB’s in Riverdale • JUNE to NOV .. Construction of flood wall [sheet piles 85’ long, 1/2” thick]. • JULY- Start of In-situ Biorremediation

  12. FRENCH … SUMMARY PLAYER/ EVENT IMPACTS

  13. FRENCH LTD • 5.5 YEARS: STUDY PHASE • 1O/81 - 4/83 NPL and Pre-planning • 4/83 - 4/87 RI/FS • 4.1 YEARS: STANDARD SETTING • 4/87 - 3/88 ROD, Pilot • 12/88 - 6/91 RD, Floodwall • 4.0 YEARS: IMPLEMENTATION • 6/91 - 6/95 Remedial Action